renovation and addition project
play

Renovation and Addition Project School Board Information Item - PowerPoint PPT Presentation

Construction Contract Change Order for Abingdon Elementary School Renovation and Addition Project School Board Information Item February 2, 2017 Expanded Scope Original contract award did not include replacement of the existing electrical


  1. Construction Contract Change Order for Abingdon Elementary School Renovation and Addition Project School Board Information Item February 2, 2017

  2. Expanded Scope • Original contract award did not include replacement of the existing electrical switchgear equipment. • Staff has determined that it is in the best interests of APS to replace the switchgear concurrent with the renovation project. • A change order is required for switchgear replacement. • School Board approval is required for an individual change order greater than $100,000. 2

  3. Project Contingency Construction Contingency (12.5%) 1 $2,791,031.00 Deduct approved change orders ($26,596.16) ($130,920.05) Deduct proposed change order for switchgear replacement Contingency Remaining $2,633,514.79 Notes: 1. Approved by the School Board on May 19, 2016. 3

  4. Recommendation • Staff recommends approving the proposed change order funded by the project’s contingency. • The change order is incorporated into the current funding available approved by the School Board so no increase in funding is necessary. 4

  5. Construction Contract Change Order for Abingdon Elementary School Renovation and Addition Project School Board Information Item February 2, 2017