Mueller Laboratory Renovation BY MARK JACKSON
Project Information • On PSU University Park campus • $18 million project • Gutting, renovation of 4 of 7 floors • Replacement of outdated HVAC, electrical systems • High pedestrian traffic around building • Scheduled to be completed before 2015 school year
Recycling • Penn State requires recycling/reuse of 75% of Materials to Recycle construction waste • Cardboard • Clean dimensional wood • Demolition prime target for recycling • Beverage and food containers • Complete gutting of 4 of 7 floors • Brick and CMU • Demo of large amount of ductwork, piping • Ferrous and non-ferrous metals • Recyclable Plastic • Implementation/Method • Gypsum wallboard • Tight site: where to locate recycling dumpsters? • Asphalt and concrete paving • Transition from demolition to construction • Ceiling Tile • Carpeting • Existing Windows • Used equipment oil • Useable appliances
Asbestos Abatement Duration: • Asbestos in tiles underneath carpeting • Abatement only on floors being gutted (4 of 7) 10 days • Total duration:40 days • Is abatement necessary? 10 days • Cost savings • Schedule savings • Legal repercussions? 5 days 15 days Total: 40 days
Roof Reinforcement • AHUs require roof reinforcement • Installation of reinforcement beams require demo of 6 th floor for access to underside of roof deck • Is reinforcement still necessary if AHUs relocated? • If reinforcement is necessary can components be prefabricated?
Site Location • Very tight site • Accessed off of busy Curtain road • Site on 10% grade • Relocate contractor parking, material storage to south?