Hollyw Holl ywood ood Par ark k Construction Upda Constr uction Update te Meeting Meeting No Novemb ember 19 er 19, , 20 2016 16
PROJECT TEAM
Introduction and Welcome Michelle Ballard, VP, Community & Citizenship, Turner-Hunt JV Infrastructure Update Juresha Alemayehu, Senior Project Engineer, Turner Casino Demo Elston Ridgle, Safety Manager, Turner-Hunt JV Stadium Update Dave Masel, General Superintendent – Field Operations, Turner-Hunt JV Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany
INFRASTRUCTURE
Building Demolition 100% Complete
Site Demo & Crushing 80% Complete
Street Widening & Hardscape 95% Complete
Environmental Remediation: 178 Acres Grading: 27 Acres
Storm Drain Relocation 99% Complete
Offsite Sewer Improvements 100% Complete
GRADING AREA AROUND STADIUM BOWL
GRADING AREA AROUND STADIUM BOWL
Anticipated Work
ANTICIPATED WORK Onsite • Infrastructure will continue to remediate unsuitable soil and demo Northern 60 acre parking lot Prairie • Ground Cover being planted and irrigation systems undergoing final testing. • Minor clean-up work will continue to the end of November. Century • No Anticipated Work at this time.
Prairie Ave Landscaping along Prairie Ave. is nearly complete. Ground Cover is being planted and irrigation systems are undergoing final testing. Anticipated completion in early December 2016.
Paving & Striping on Prairie Prairie Ave. paving and striping is complete. All traffic signals are operational including pedestrian crossing indicators. Minor pickup work remains and is scheduled for completion by the end of November 2016
Century Blvd No Anticipated Work at This Time
Casino and Pavilion Demo
Casino and Pavilion Demo • Casino demo is nearly complete aside from basement. • Pavilion Soft Demo is complete (removal of non structural items) • Pavilion Hard Demo to begin week of 11/28.
Casino and Pavilion Demo Gutting of Pavilion
Stadium Update
Stadium Update • Mass Grading • Nightly Dust Control • Mobilizing trailer complex • Engaging local workforce – Ramping up in January • THJV and the community
Mass Grading
Dust Control • There are currently 13 pieces of Dust Control Equipment working • Water Trucks run continuously from 7:00am to 5:30pm • The quantity of water that is placed averages 1,300,000 gallons/day Kiewit Infrastructure West is the subcontractor currently working on the site. If you or your neighbors have additional concerns please contact one of the following Kiewit Managers immediately: Allison Reinicke (310) 846-2402 Ron Robison (310) 846-8402
Scrapers
Mobilizing Trailer Complex
Engaging Local Workforce Information and Resource Fair Date: Thursday, December 1, 2016 Time: 9:00 am to 2:00 p.m. Location: Rogers Park (Gymnasium & Auditorium), 400 West Beach Avenue, Inglewood, California, 90301
SUMMARY/OVERVIEW
Plan Overview
Stadium – Southeast View
Stadium – Lake Park View
Stadium – Champions Plaza
Stadium – Entrance
Q & A Q & A
To receive construction updates or for questions email inglewoodstadium@tcco.com or call 424-750-3598
Dust Control • There are currently 13 pieces of Dust Control Equipment working • Water Trucks run continuously from 7:00am to 5:30pm • The quantity of water that is placed averages 1,300,000 gallons/day Kiewit Infrastructure West is the subcontractor currently working on the site. If you or your neighbors have additional concerns please contact one of the following Kiewit Managers immediately: Allison Reinicke (310) 846-2402 Ron Robison (310) 846-8402
Recommend
More recommend