hollyw holl ywood ood par ark k
play

Hollyw Holl ywood ood Par ark k Construction Upda Constr - PowerPoint PPT Presentation

Hollyw Holl ywood ood Par ark k Construction Upda Constr uction Update te Meeting Meeting No Novemb ember 19 er 19, , 20 2016 16 PROJECT TEAM Introduction and Welcome Michelle Ballard, VP, Community & Citizenship,


  1. Hollyw Holl ywood ood Par ark k Construction Upda Constr uction Update te Meeting Meeting No Novemb ember 19 er 19, , 20 2016 16

  2. PROJECT TEAM

  3. Introduction and Welcome Michelle Ballard, VP, Community & Citizenship, Turner-Hunt JV Infrastructure Update Juresha Alemayehu, Senior Project Engineer, Turner Casino Demo Elston Ridgle, Safety Manager, Turner-Hunt JV Stadium Update Dave Masel, General Superintendent – Field Operations, Turner-Hunt JV Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

  4. INFRASTRUCTURE

  5. Building Demolition 100% Complete

  6. Site Demo & Crushing 80% Complete

  7. Street Widening & Hardscape 95% Complete

  8. Environmental Remediation: 178 Acres Grading: 27 Acres

  9. Storm Drain Relocation 99% Complete

  10. Offsite Sewer Improvements 100% Complete

  11. GRADING AREA AROUND STADIUM BOWL

  12. GRADING AREA AROUND STADIUM BOWL

  13. Anticipated Work

  14. ANTICIPATED WORK Onsite • Infrastructure will continue to remediate unsuitable soil and demo Northern 60 acre parking lot Prairie • Ground Cover being planted and irrigation systems undergoing final testing. • Minor clean-up work will continue to the end of November. Century • No Anticipated Work at this time.

  15. Prairie Ave Landscaping along Prairie Ave. is nearly complete. Ground Cover is being planted and irrigation systems are undergoing final testing. Anticipated completion in early December 2016.

  16. Paving & Striping on Prairie Prairie Ave. paving and striping is complete. All traffic signals are operational including pedestrian crossing indicators. Minor pickup work remains and is scheduled for completion by the end of November 2016

  17. Century Blvd No Anticipated Work at This Time

  18. Casino and Pavilion Demo

  19. Casino and Pavilion Demo • Casino demo is nearly complete aside from basement. • Pavilion Soft Demo is complete (removal of non structural items) • Pavilion Hard Demo to begin week of 11/28.

  20. Casino and Pavilion Demo Gutting of Pavilion

  21. Stadium Update

  22. Stadium Update • Mass Grading • Nightly Dust Control • Mobilizing trailer complex • Engaging local workforce – Ramping up in January • THJV and the community

  23. Mass Grading

  24. Dust Control • There are currently 13 pieces of Dust Control Equipment working • Water Trucks run continuously from 7:00am to 5:30pm • The quantity of water that is placed averages 1,300,000 gallons/day Kiewit Infrastructure West is the subcontractor currently working on the site. If you or your neighbors have additional concerns please contact one of the following Kiewit Managers immediately: Allison Reinicke (310) 846-2402 Ron Robison (310) 846-8402

  25. Scrapers

  26. Mobilizing Trailer Complex

  27. Engaging Local Workforce Information and Resource Fair Date: Thursday, December 1, 2016 Time: 9:00 am to 2:00 p.m. Location: Rogers Park (Gymnasium & Auditorium), 400 West Beach Avenue, Inglewood, California, 90301

  28. SUMMARY/OVERVIEW

  29. Plan Overview

  30. Stadium – Southeast View

  31. Stadium – Lake Park View

  32. Stadium – Champions Plaza

  33. Stadium – Entrance

  34. Q & A Q & A

  35. To receive construction updates or for questions email inglewoodstadium@tcco.com or call 424-750-3598

  36. Dust Control • There are currently 13 pieces of Dust Control Equipment working • Water Trucks run continuously from 7:00am to 5:30pm • The quantity of water that is placed averages 1,300,000 gallons/day Kiewit Infrastructure West is the subcontractor currently working on the site. If you or your neighbors have additional concerns please contact one of the following Kiewit Managers immediately: Allison Reinicke (310) 846-2402 Ron Robison (310) 846-8402

Recommend


More recommend