NORTH MARION School District- Bond Projects BOND OVERSIGHT COMMITTEE May 15, 2019 BOND UPDATE: SCHEDULE: High and Middle School Seismic Projects: Under Construction High School Renovation Project: Todd Construction Under


  1. NORTH MARION School District- Bond Projects BOND OVERSIGHT COMMITTEE May 15, 2019

  2. BOND UPDATE: SCHEDULE: • High and Middle School Seismic Projects: • Under Construction • High School Renovation Project: • Todd Construction Under Contract • Mobilization to commence within next few days • Working on Value Engineering ideas • Primary and Intermediate School Projects: • Bid May 7, 2019. Only received 1 proposal / Over Budget • Recommended and Approved by Board to reject Bid and re-issue later in the year • Middle School: • SD Scope being Modified to proceed with an estimate. • Documents to be ready early 2020 for Bid / Construction after spring break 2020 • Review if Project should be added to Primary and Intermediate School Project Bid Documents

  3. HIGH SCHOOL: • Contractor: Todd Construction – Under Contract. • Ground Breaking Took Place May 8 th , 2019 • Fencing / Mobilization – Week of May 13 th .

  4. HIGH SCHOOL GYM SEISMIC : • All wall and ceiling demolition complete • Sawcutting /removal of concrete slab and excavate for footings in progress • Beam installation in process • Masonry walls to commence after footings

  5. MIDDLE SCHOOL GYM SEISMIC : • All ceiling demolition complete / Process of removing ductwork • Sawcutting of concrete slab and excavation of footing start later in week. • Beam / strapping installation to commence shortly • Concrete wall to commence after footing

  6. MIDDLE SCHOOL PARKING LOT: • ALL CONCRETE FLATWORK IN PROGRESS – Scheduled to be complete this week • WORKING ON LIGHTING • IRRIGATION AND PLANTING TO COMMENCE NEXT WEEK • PAVING SCHEDULED FOR FIRST WEEK OF JUNE :

  7. COMMUNICATION: • Web Page: www.n.marion.k12.or.us - Page has been revised: • Current progress photos • Current bidding opportunities • Current progress reports • Current Financial Reporting sheet. • District Wide Mailers: (attached) • Sent out a couple of weeks ago • Next to be sent about End of August.

  8. BOND FINANICALS:

  9. QUESTIONS: