bond oversight committee bond 2014 and bond 2018 april 25
play

Bond Oversight Committee Bond 2014 and Bond 2018 April 25, 2019 1 - PowerPoint PPT Presentation

Bond Oversight Committee Bond 2014 and Bond 2018 April 25, 2019 1 AGENDA 1. Welcome Joanne Gore, Chair 2. Bond 2014 Update Oscar Perez, Carolina Fuzetti 3. Bond 2018 Update Oscar Perez, Zandra Becerra Contract Updates


  1. Bond Oversight Committee Bond 2014 and Bond 2018 April 25, 2019 1

  2. AGENDA 1. Welcome – Joanne Gore, Chair 2. Bond 2014 Update – Oscar Perez, Carolina Fuzetti 3. Bond 2018 Update – Oscar Perez, Zandra Becerra • Contract Updates • Bond Program Financials/Dashboard • Small Business Initiative Update • Malala Yousafzai (Pkg 001) – ES51 Update • New Construction/Renovation, Work in Progress 4. Communications Update – Veronica Sopher 5. Technology Update – Jojo Jacob 6. Debt Service Fund Update – Steve Bassett 7. Questions/Comments 2

  3. Bond Oversight Committee 2014 Bond program April 25, 2019 3

  4. PROGRAM STATUS Overall Bond Program PHASE/ % COMPLETE DESIGN CONSTRUCTION CLOSE/ SD DD CD BID CONST WNTY I/99% II/100% III/95% LEGEND Complete In progress Next step 4

  5. PROJECTED PROGRAM BUDGET Item Total Current Commitments/ (A) $439.2M Approved Change Orders Estimates/ (B) $ 35.7M Pending Change Orders* Total Projected Budget (C)=(A) + (B) $474.9M 2014 Bond Budget (D) $486.7M Projected Bond Program Balance (E)=(D) - (C) $ 11.8M Notes: Data as of 3/31/2019 Current 2014 Bond Program Contingency = $18.2M Projected Bond Program Balance includes rounding tolerance * Projected estimate to complete (based on estimates and pending commitments) 5

  6. SMALL BUSINESS INITIATIVE Awarded Construction Total SBE Commitment SBE Paid to Date Contracts Board Goal 25% 66% 77% 29% $91,079,616 $69,922,186 $319,308,804 6

  7. James Reese Career and Technical Center Construction Progress • Substantial completion 7/25/2019 • Opening fall 2019 • Construction 72% complete 7

  8. 2014 Bond Wireless Upgrade 8

  9. Bond Oversight Committee 2018 Bond Program April 25, 2019 9

  10. Contract Updates A/E Contracts (Design) 42 of 51 (A/E) Architect/Engineer contracts have been executed JOC Contracts (Construction) 14 of 20 Job Order Contracts (JOC) construction contracts have been executed CSP/CMAR Contracts (Construction) 0 of 29 Competitive Sealed Proposal (CSP)/Construction Manager at Risk (CMAR) construction contracts have been executed 10

  11. Bond Program Dashboard/Financials Commitments Spent to Date $81M $24M 11

  12. Small Business Initiative 2018 Bond Program A/E Services Construction Awarded Construction Awarded Construction 7% 85% Contracts Contracts $39,634,707 $38,402,545 Total SBE Commitment Total SBE Commitment 26% $10,892,247 27% $10,054,444 SBE Paid to Date SBE Paid to Date $4,013,853 10% 0.5% $185,051 12

  13. MALALA YOUSAFZAI New elementary school (#51) in the Aliana Community • 10 Classroom Addition approved by BOT in February 2019, Bond 2018 funded • Construction of classroom addition in progress • Building envelope is 75% complete • Substantial completion date is 12/2019 • Mid-year opening - student on-campus start date is January 2020 13

  14. New Construction/Renovation Progress New Construction Additions/Renovations ES 52, ES 53, HS 12 Neill ES Addition - 12 classroom • Land acquisition in progress • Schematic Design approved by BOT February 2019 • Schematic Design ongoing • Design Development ongoing • BOT approval Summer 2019 Madden ES Addition - 10 classroom Meadows ES • Schematic Design approved by BOT March 2019 • Schematic Design complete and approved by • Design Development ongoing BOT, February 2019 • Demo/Construction start date summer 2019 Fine Arts • Opening date 2021 • Schematic Design ongoing • Projected construction start January 2020 Lakeview ES • Programming complete • Visioning sessions with community ongoing • Construction start date summer 2020 MS 16-Net Zero • Benchmark Case study in progress • Land purchase being evaluated 14

  15. Construction Work in Progress • Door Locks and Window Film (Security) – Install summer 2019 • Playgrounds – Install summer 2019 • Hall Stadium Repairs/Renovation ongoing • Estimated completion date August 2019 • PA/Sound and Clocks • Bond Signage – Summer 2019 • Fencing around Portable Buildings • Water Softeners 15

  16. Communications Plan Update • Bond update included in April FBISD News Magazine Planned: • Back-to-school magazine to include longer article about bond progress. • Video PSA in progress regarding installation of door locks at campuses throughout the District • Additional social media posts and videos to be shared as appropriate 16

  17. Technology Progress  IT HVAC Project  Phase 1 (17 campuses) • Construction work is completed. Access control is installed in about 30% of the campuses.  Phase 2 (A&E) • Currently reviewing the 90% Construction Documents  Majority of project in initial phases (planning, bids, etc.) • Board approved purchases 17

  18. Phase 1 & 2 Classroom Toolset 18

  19. • Currently finalizing counts & gathering quotes • Anticipated Delivery is late July – August 19

  20. • Currently finalizing counts & gathering quotes • Anticipated Delivery is late July – August 20

  21. SUMMARY OF OUTSTANDING DEBT AS OF 3/31/2019 Summary Statistics Principal Composition Total Outstanding Principal $ 977,230,164 Total Fixed Rate 813,325,164 83.23% 24.07% Total Variable Rate 163,905,000 16.77% Total Interest Payments 456,434,221 Callable Principal (%) 0.00% 75.93% Percent of Principal Retired 75.93% w/in 5 years 23.69% w/in 10 years 54.86% Noncallable w/in 15 years 78.74% 24.07% Callable w/in 20 years 90.52% 75.93% w/in 25 years 98.42% w/in 30 years 100.00% Final Maturity 8/15/2048 Underlying Ratings Voted Authorization Fitch AA+ Date Amount Issued Balance CP Issued Unissued S&P AA+ 11/6/2007 $ 428,000,000 $ 409,000,000 $ 19,000,000 $ 10,000,000 $ 9,000,000 11/4/2014 484,000,000 370,000,000 114,000,000 65,000,000 49,000,000 11/6/2018 992,600,000 - 992,600,000 25,000,000 967,600,000 $ 1,904,600,000 $ 779,000,000 $ 1,125,600,000 $ 100,000,000 $ 1,025,600,000 21

  22. SUMMARY OF OUTSTANDING DEBT PRINCIPAL & INTEREST $100,000,000 $90,000,000 $80,000,000 $70,000,000 $60,000,000 Aggregate Debt Service $50,000,000 $40,000,000 $30,000,000 $20,000,000 $10,000,000 $0 Period Ending 8/31 Principal Interest 22

  23. SUMMARY OF OUTSTANDING DEBT CALLABLE BONDS  The following table shows the District’s callable bonds as of March 31, 2019 Callable Call Bond Issue Principal Date Unlimited Tax Refunding Bonds, Series 2009 $ 28,390,000 8/15/2019 Unlimited Tax School Building Bonds, Series 2009 121,860,000 8/15/2019 Unlimited Tax School Building & Refunding Bonds, Series 2010 66,580,000 8/15/2020 Unlimited Tax Refunding Bonds, Series 2012 46,870,000 8/15/2022 Unlimited Tax Refunding Bonds, Series 2014 46,145,000 8/15/2024 Variable Rate Unlimited Tax School Building Bonds, Series 2015A 31,630,000 8/1/2019 Variable Rate Unlimited Tax School Building Bonds, Series 2015B 39,250,000 8/1/2019 Unlimited Tax Refunding Bonds, Series 2016A 35,755,000 8/15/2024 Unlimited Tax Refunding Bonds, Series 2017A (Green Bonds) 36,525,000 8/15/2026 Unlimited Tax Refunding Bonds, Series 2017B 28,080,000 8/15/2026 Variable Rate Unlimited Tax Refunding Bonds, Series 2017C (Green Bonds) 44,060,000 8/1/2020 Variable Rate Unlimited Tax Refunding Bonds, Series 2017D 48,965,000 8/1/2021 Unlimited Tax Refunding Bonds, Series 2018 119,585,000 8/15/2027 Unlimited Tax School Building Bonds, Taxable Series 2018 48,300,000 8/15/2027 23

  24. TAX EXEMPT COMMERCIAL PAPER  The District established a Commercial Paper Program on November 3, 2016  On January 22, 2019, the Board of Trustees approved expanding the commercial paper program from $100 million to $150 million effective February 20, 2019. The Board also approved adding the 2018 Bond to the commercial paper program  Currently, the District has $100 million outstanding in commercial paper with rates ranging from 1.62% to 1.86%  As of 3/31/2019, the District has saved approximately $8.58 million in interest expense Interest Expense Comparison Commercial Paper Notes Fixed Rate Interest Period Total Interest Issue - Total Expense Ending Series A Series B Expense Interest Expense Difference 3/31/2019 $ 1,324,230 $ 48,759 $ 1,372,989 $ 9,960,049 $ (8,587,060) 24

  25. RECAP OF DEBT TRANSACTIONS  Series 2019A Refunded Bonds - $100,000,000 VARIABLE  Commercial Paper refunded at par  Priced 4/23/19 and will close 5/22/19  Three-year put at 1.95%  All-in True Interest Cost (TIC) = 1.98%  Average life of bonds = 16.84 years  District saved approximately $5 million in interest expense savings versus a fixed rate bond in the first three years  Series 2019B Refunded Bonds - $131,550,000 FIXED  Series 2009 and Series 2009 Refunding  Refunded total = $150,250,000  Priced 4/23/19 and will close 5/22/19  Net Present Savings of $26.2 million  All-in True Interest Cost (TIC) = 2.78%  Average life of bonds = 10.13 years  District saved over $7 million in net present value savings by not advance refunding in December 2017 25

Recommend


More recommend