Honeoye Falls-Lima Central School District 2016 Additions and Alterations Phase 2 Project Update March 2020 2016 Additions and Alterations Phase 2 Referendum Value $29,986,084 Incidental Budget $ 4,632,681 Construction Contingency $


  1. Honeoye Falls-Lima Central School District 2016 Additions and Alterations Phase 2 Project Update March 2020

  2. 2016 Additions and Alterations Phase 2 Referendum Value $29,986,084 Incidental Budget $ 4,632,681 Construction Contingency $ 1,564,311 Contracts Awarded $22,848,873 State Contract $ 940,219

  3. Construction Contingency Budget Update • Construction Contingency Budget $1,564,311 • Additional Co-Op Purchases $ 187,098 • Additional Credit $ 63,092 • Approved Change Orders $1,098,108 • Remaining Construction Contingency $ 342,197 • Construction Project is 76% Complete • Contingency Budget is 78% spent • Contract allowance approved totals $0 • Project Team is following approximately $267,739 in pending issues.

  4. 2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate Senior High School • Rooms 303 and 305 have been • The Display Cases have been installed in the completed and turned over to the Lobby. District. • Wall tile and floor tile have been installed in • Construction in the Music Room has the Kitchen and Cafeteria. begun. • Ceiling grid is installed throughout the Cafeteria and Kitchen and ceiling tile is being Transportation Building dropped. • Concrete for the Mezzanine has been poured. • The Cougar Mural has been installed in the stairwell adjacent to the Cafeteria. • Overhead plumbing, ductwork and electrical conduit are ongoing. • Demolition has begun in the Robotics Lab. • Masonry block work is ongoing. • Demo of B&G has begun.

  5. 2016 Additions and Alterations Phase 2 Project Status/Schedule Update Lima Intermediate Middle School • The Main Office has undergone • The building has been switched over to the demolition, framing has begun and new Day Automation platform. MEP rough-ins are ongoing. • Rooms 107, 108, 109 and 110 have been abated and new flooring is going in.

  6. 2016 Additions and Alterations Phase 2 What to expect in the upcoming Month Manor Intermediate Senior High School • Heavy demo will continue in the • The Cafeteria will be turned over to the Music Room. District. Lima Elementary • Construction will continue in the Kitchen Area. • Construction in the Main Office will continue. • The Faculty Lounge will be completed and turned over to the District. Transportation Building • Construction in the Robotics Lab will continue. • Masonry work, drywall, floor leveling and MEP rough-ins will all continue. • Parking lot work and concrete sidewalks will continue.

  7. Honeoye Falls-Lima Central School District 2016 Additions and Alterations Phase 2 Progress Photos

  8. New Mezzanine – Transportation Center

  9. New Mezzanine – Transportation Center

  10. Office Space – Transportation Center

  11. Temporary Wall in Manor Cafeteria

  12. New Music Room - Manor

  13. New Music Room - Manor

  14. Cafeteria – High School

  15. Cafeteria – High School

  16. Cafeteria – High School Kitchen

  17. Flexible Learning Lab – High School

  18. Flexible Learning Lab – High School

  19. Robotics Lab – High School

  20. Main Entrance Lobby – High School

  21. Main Entrance Lobby – High School

  22. Main Entrance Lobby – High School

  23. B&G Building Demolition

  24. B&G Building Demolition

  25. B&G Building Demolition

  26. New Concrete Sidewalks – High School

  27. New Concrete Sidewalks – High School

  28. New Main Office – Lima

  29. Room 107 – Lima

  30. Room 108 – Lima

  31. Room 109 – Lima

  32. Room 110 – Lima

  33. Cougar Mural – High School

  34. Honeoye Falls-Lima Central School District Questions?