Honeoye Falls-Lima Central School District 2016 Additions and Alterations Phase 2 Project Update March 2020
2016 Additions and Alterations Phase 2 Referendum Value $29,986,084 Incidental Budget $ 4,632,681 Construction Contingency $ 1,564,311 Contracts Awarded $22,848,873 State Contract $ 940,219
Construction Contingency Budget Update • Construction Contingency Budget $1,564,311 • Additional Co-Op Purchases $ 187,098 • Additional Credit $ 63,092 • Approved Change Orders $1,098,108 • Remaining Construction Contingency $ 342,197 • Construction Project is 76% Complete • Contingency Budget is 78% spent • Contract allowance approved totals $0 • Project Team is following approximately $267,739 in pending issues.
2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate Senior High School • Rooms 303 and 305 have been • The Display Cases have been installed in the completed and turned over to the Lobby. District. • Wall tile and floor tile have been installed in • Construction in the Music Room has the Kitchen and Cafeteria. begun. • Ceiling grid is installed throughout the Cafeteria and Kitchen and ceiling tile is being Transportation Building dropped. • Concrete for the Mezzanine has been poured. • The Cougar Mural has been installed in the stairwell adjacent to the Cafeteria. • Overhead plumbing, ductwork and electrical conduit are ongoing. • Demolition has begun in the Robotics Lab. • Masonry block work is ongoing. • Demo of B&G has begun.
2016 Additions and Alterations Phase 2 Project Status/Schedule Update Lima Intermediate Middle School • The Main Office has undergone • The building has been switched over to the demolition, framing has begun and new Day Automation platform. MEP rough-ins are ongoing. • Rooms 107, 108, 109 and 110 have been abated and new flooring is going in.
2016 Additions and Alterations Phase 2 What to expect in the upcoming Month Manor Intermediate Senior High School • Heavy demo will continue in the • The Cafeteria will be turned over to the Music Room. District. Lima Elementary • Construction will continue in the Kitchen Area. • Construction in the Main Office will continue. • The Faculty Lounge will be completed and turned over to the District. Transportation Building • Construction in the Robotics Lab will continue. • Masonry work, drywall, floor leveling and MEP rough-ins will all continue. • Parking lot work and concrete sidewalks will continue.
Honeoye Falls-Lima Central School District 2016 Additions and Alterations Phase 2 Progress Photos
New Mezzanine – Transportation Center
New Mezzanine – Transportation Center
Office Space – Transportation Center
Temporary Wall in Manor Cafeteria
New Music Room - Manor
New Music Room - Manor
Cafeteria – High School
Cafeteria – High School
Cafeteria – High School Kitchen
Flexible Learning Lab – High School
Flexible Learning Lab – High School
Robotics Lab – High School
Main Entrance Lobby – High School
Main Entrance Lobby – High School
Main Entrance Lobby – High School
B&G Building Demolition
B&G Building Demolition
B&G Building Demolition
New Concrete Sidewalks – High School
New Concrete Sidewalks – High School
New Main Office – Lima
Room 107 – Lima
Room 108 – Lima
Room 109 – Lima
Room 110 – Lima
Cougar Mural – High School
Honeoye Falls-Lima Central School District Questions?
Recommend
More recommend