Honeoye Falls-Lima Central School District 2016 Additions and Alterations Phase 2 Project Update December 2018
2016 Additions and Alterations Phase 2 Referendum Value $29,986,084 Incidental Budget $ 4,632,681 Construction Contingency $ 1,564,311 Contracts Awarded $22,848,873 State Contract $ 940,219
Construction Contingency Budget Update • Construction Contingency Budget $1,564,311 • There are no approved Change Orders at this time • Contingency Budget is 0% spent • Contract allowance approved totals $0 • Project Team is following approximately $213,700 in pending issues
2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate (Rooms 207, 209, Senior High School 211 and 213) • Excavation along with foundation work for the • Temporary wall has been installed. Main Entrance is underway. • The plumbing fixtures have been • Abatement and Demo of the Art Room and disconnected and removed. New Nurses Office started over Christmas Break and continues. • Demolition and abatement are Papermill Storage complete. • The concrete flooring inside of the South Storage Building has been installed. Transportation Building • Bearing plates for structural steel have been installed. • Structural steel has been ordered. .
2016 Additions and Alterations Phase 2 What to expect in the upcoming Month Manor Intermediate (Room 207, 209, Senior High School 211 and 213) • Foundation work for the Main Entrance • Construction in Manor will continue is scheduled to be completed by mid with the installation of case work, wire January. Once complete the building pad molding, flooring, paint and finishes. will be backfilled with stone and compacted. Transportation Building • Structural steel is to be delivered and • Construction in the Art Room and New installation is to begin. Nurses Office will continue throughout the month of January.
Honeoye Falls-Lima Central School District 2016 Additions and Alterations Phase 2 Progress Photos
Concrete prep – Papermill
Installed Concrete – Papermill
Demo/Abatement – High School Art Room
Demo – High School Art Room
Demo – New High School Nurses Office
Demo – New High School Nurses Office
Foundation Work – High School Main Entrance
Foundation Work – High School Main Entrance
Foundation Work – High School Main Entrance
Forming Foundation Walls – High School Main Entrance
Foundation Work – High School Main Entrance
Mastic to be Abated – High School
Demo – Manor Intermediate
Demo – Manor Intermediate
Mastic Abatement – Manor Intermediate
Abatement – Manor Intermediate
Honeoye Falls-Lima Central School District Questions?