citizen s general obligation bond oversight committee
play

Citizens General Obligation Bond Oversight Committee Presentation - PowerPoint PPT Presentation

San Francisco Recreation & Parks Department Port of San Francisco Citizens General Obligation Bond Oversight Committee Presentation January 27, 2020 Inspire, Connect, Play! 2008 Bond Overview Approved in February 2008, The Clean


  1. San Francisco Recreation & Parks Department Port of San Francisco Citizen’s General Obligation Bond Oversight Committee Presentation January 27, 2020 Inspire, Connect, Play!

  2. 2008 Bond – Overview Approved in February 2008, The Clean and • Safe Neighborhood Parks (CSNP) bond Authorized $185 million for parks and open spaces across three components. Neighborhood Parks- $115.8 million • Citywide Programs- $38.5 million • Waterfront Parks- $33.6 million • The Waterfront Parks component is led by • the Port of San Francisco. The other two components were led by the Recreation and Parks Department San Francisco Clean and Safe Parks GO BONDS 1

  3. 2008 Bond – Completed Waterfront Parks Pier 43 Bay Trail Link- Completed • November 2012 Brannan Street Wharf- Completed July • 2013 Blue Greenway Planning & Design • Guidelines- Completed July 2012. Bayfront Park- Completed February 2012 • Heron’s Head Park- Completed September • 2012 Blue Greenway Public Art- Completed • April 2018 Blue Greenway Signage and Site • Furnishings- Completed July 2017 Bayview Gateway- Completed September • 2015 San Francisco Clean and Safe Parks GO BONDS 1

  4. 2008 Bond – One Project Remaining Crane Cove Park: • Main park construction scheduled to be completed in April 2020 • Parking Lot and Building 49 scheduled to be completed in July 2021 • Bond Funds were only used on main park construction San Francisco Clean and Safe Parks GO BONDS 2

  5. 2008 Bond – Fund Expenditures • $33.6 million was allocated to Waterfront Parks • $33.3 million was been expended. • Remaining Balance expected to be spent by February 2020 San Francisco Clean and Safe Parks GO BONDS 2

  6. 2008 Bond – Fund Expenditures 2008 Clean & Safe Neighborhood Park G.O. Bond Program Budget Reports - Expenses as of 12/31/2019 2008 G.O. Bond All Sources Project Budget Expenditures Encumbered Balance Budget Expenditures Encumbered Balance 7,655,330 7,655,330 - - 10,169,038 10,169,038 - - Pier 43 Bay Trail Link 2,941,050 2,941,050 - - 25,024,340 25,024,340 - - Brannan Street Wharf Blue Greenway- Planing & Design 325,472 325,472 - - 325,472 325,472 - - Bayfront Park 2,330,367 2,330,367 - - 2,330,367 2,330,367 - - Heron's Head Park 2,351,000 2,351,000 - - 2,397,861 2,397,861 - - Tulare Park 196,577 196,577 - - 196,577 196,577 - - Blue Greenway- Public Art 684,000 622,651 - 61,349 684,000 622,651 - 61,349 Crane Cove Park 11,244,828 10,841,756 25,860 377,212 36,668,586 22,172,193 6,258,822 8,237,571 Blue Greenway- Signage & Furnishings 928,344 928,344 - - 928,344 928,344 - - Bayview Gateway 4,692,520 4,678,233 - 14,287 4,782,951 4,754,588 - 28,363 CEQA Review & Permitting 444,040 444,040 - - 444,040 444,040 - - Bond Interest applied to Crane Cove Park 193,528 193,528 - - 193,528 193,528 - - WATERFRONT PARKS $ 33,600,000.00 $ 33,314,820.00 $ 25,860.00 $ 452,848.00 $ 83,951,576.00 $ 69,365,471.00 $ 6,258,822.00 $ 8,327,283.00 San Francisco Clean and Safe Parks GO BONDS 2

  7. 2012 Bond – Overview Approved in November 2012, The • Clean and Safe Neighborhood Parks (CSNP) bond Authorized $195 million for parks and open spaces across four components. Neighborhood Parks- $99.6 million • Citywide Programs- $39 million • Waterfront Parks- $34.5 million • Citywide Parks- $21 million • The Waterfront Parks component is led • by the Port of San Francisco. The other three components were are being by the Recreation and Parks Department San Francisco Clean and Safe Parks GO BONDS 1

  8. 2012 Bond- Waterfront Parks (Update) Completed Project: Cruise Terminal Plaza at Pier 27- Completed September 2014 • Active Projects- Planning & Design Agua Vista Park • Currently in Design phase • Will be delivered with the Mission Bay Ferry Landing project • Project Scope includes: New grading, pathways, irrigation & • drainage, lighting and improved access to fishing pier. Project completion scheduled for Fall 2021. • Islais Creek • Planning phase –Bond funds will be used to perform • preliminary analysis and engineering. Heron’s Head Park Improvements • Currently in Design phase • Project Scope includes: Improved pathways, ADA improvements • lighting, planting and upgrades to the EcoCenter’s Solar panels and electrical system. Project completion is scheduled for November 2020. • Pier 27 Public Art • Currently in Planning phase • San Francisco Arts Commission will begin the artist selection • process in the Spring of 2020 Project completion is scheduled for Fall 2021 • San Francisco Clean and Safe Parks GO BONDS 4

  9. 2012 Bond- Waterfront Parks (Update) Rendering Active Projects- Construction Crane Cove Park Main park & parking lot are currently in • construction. Completion is scheduled for Spring • 2020. Jan 2020 San Francisco Clean and Safe Parks GO BONDS 4

  10. 2012 Bond – Fund Expenditures • $34.5 million was allocated to Waterfront Parks • $23.7 million was been expended. • Current Balance $12 million San Francisco Clean and Safe Parks GO BONDS 2

  11. 2012 Bond – Fund Expenditures 2012 Clean & Safe Neighborhood Park G.O. Bond Program Budget Reports - Expenses as of 12/31/2019 2012 G.O. Bond All Sources Project Budget Expenditures Encumbered Balance Budget Expenditures Encumbered Balance 2,000,000 106,783 - 1,893,217 2,000,000 106,783 - 1,893,217 Agua Vista Park 14,329,744 7,740,551 4,488,010 2,101,183 36,668,549 22,172,192 6,125,497 8,370,860 Crane Cove Park Islais Creek Improvements 250,000 1,118 - 248,882 250,000 1,118 - 248,882 Northwest Wharf Plaza & Pier 27/29 Tip 15,870,000 15,727,672 - 142,328 15,870,000 15,727,672 - 142,328 Heron's Head Park 1,720,256 115,365 - 1,604,891 1,720,256 115,365 - 1,604,891 Pier 27 Public Art 330,000 330,000 330,000 330,000 Bond Interest applied to Crane Cove Park 357,227 192,964 111,882 52,380 357,227 192,964 111,882 52,380 WATERFRONT PARKS $ 34,500,000.44 $ 23,691,489.00 $ 4,488,010.00 $ 12,000,501.44 $ 62,518,804.98 $ 38,123,130.00 $ 6,125,497.00 $ 18,270,177.98 San Francisco Clean and Safe Parks GO BONDS 2

  12. Schedules of Remaining Projects Initiation/ Planning Pln 2017 2018 2019 2020 2021 Design/ Bid & Award Des Des Construction/ Close Out J Con Con F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Start Date End Date Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q Q Q Q AGUA VISTA PARK July 2014 June 2021 PlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnDesDesDesDesDesDesDesDesCon Con ConConConConConCon CRANE COVE PARK September 2011 July 2021 DesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDes HERON'S HEAD PARK April 2018 March 2021 PlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDes Con ISLAIS CREEK IMPROVEMENTS October 2013 TBD PlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPln PIER 27 PUBLIC ART July 2018 February 2022 PlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnDesDesDesDesCon Con Con Con Con Con Con Con * GO Bond Funded protion of Crane Cove Park will be completed in Spring 2020 San Francisco Clean and Safe Parks GO BONDS 13

  13. Comments and Questions 14

Recommend


More recommend