Presentation to the Board of Education Christopher Dillon Ed.D. Assistant to the Superintendent for Facilities October 6, 2015 Lighting Fixture Retrofit district wide Lighting Fixture Control upgrades district wide Light ghtin ing


  1. Presentation to the Board of Education Christopher Dillon Ed.D. Assistant to the Superintendent for Facilities October 6, 2015

  2. • Lighting Fixture Retrofit district wide • Lighting Fixture Control upgrades district wide Light ghtin ing • Transformer replacements district wide • Temperature Setback • Refrigeration Compressor Controllers Energ ergy y • Exhaust Fan/Relief Damper Control Manag nageme ement nt • Boilers/District Hot Water Heaters - Burner Controllers Syst stems ems • Window replacement at Schwarting and Eastplain • Uninvent motor replacement and refurbishment district wide • Air Handling Unit Upgrade district wide Air Quality lity • Exhaust Fan Control district wide

  3. Window replacement at Schwarting and Eastplain • Elementary Schools Updated Energy Management System including • pneumatic refurbishment in the classroom unit ventilators and allow for zone control of units instead of individual classroom control District wide bulb & ballast replacement • Weatherization of exterior doors •

  4. Two school buildings received new windows  Eliminated doing a partial installation and ensured all new  windows were installed in one phase Current heating and fresh air vents in each classroom have  been refurbished and are controlled by zones from remote access This project gave the district the opportunity to improve  lighting, air quality, building structure, and energy management controls 

  5. Lighting and HVAC controls - 90%  Window replacement at Eastplain and Schwarting -100%  Window film tint – 100%  Exhaust and fresh air controls – 100%  Boiler and hot water controls – 95%  Lighting transformer replacement – 90%  Any punch list items will be completed by the end of the  2015-2016 school year