us 150 eastbound mcclugage bridge over the illinois river
play

US 150 Eastbound (McClugage Bridge) over the Illinois River PRE-BID - PowerPoint PPT Presentation

US 150 Eastbound (McClugage Bridge) over the Illinois River PRE-BID MEETING www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project Meeting Agenda Introduction US 150 Corridor Construction Sequence Permits


  1. US 150 Eastbound (McClugage Bridge) over the Illinois River PRE-BID MEETING www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  2. Meeting Agenda • Introduction • US 150 Corridor • Construction Sequence • Permits • Commitments • Environmental Key Elements • Additional Key Elements • Questions/Discussion www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  3. Project Aerial Photo Eastbound US 150 – 1.55 mi. IL Route 29 - 0.24 mi. SB IL 116/US 24 - 0.59 mi www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  4. Construction Sequence – July 2019 thru March 2020 Earthwork EB Foundations, US150 and SW Piers Ramp Earthwork/Route Pavement 29 Bridge Half Widening Construction www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  5. Construction Sequence – April 2020 thru March 2021 Foundations, No Work * Earthwork Piers No Work * No Work * * No Lane Closures or Lane Reductions April 1 thru November 30 www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  6. Construction Sequence – April 2021 thru March 2022 Approach Span and Main Span Construction New Ramp Mainline Paving Paving Interchange Finalize Work Ramp E www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  7. Construction Sequence – April 2022 thru March 2023 Traffic on New Bridge (April 1, 2022) – *Begin Bridge Removal Final Ramp Construction Final Work Complete Interchange Construction IL 29 Bridge *Final Bridge Removal and Project Restoration Remaining March 31, 2023 Completion Construction www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  8. Construction Key Items • Summer 2019 Start • Approximate 3-3/4 year schedule • Completion Date – March 31, 2023 • No lane closures or lane reductions in 2020 • Cooperation with other contracts www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  9. Construction Key Items Cooperation with other contracts Contract Contract 89723 68D85 (Bridge (RR Bridge Rehab) Deck Rehab) Contract 68D22 (Resurface) www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  10. Permits • IDNR Permit • IL EPA 401 Water Quality Permit • ACOE 404/Section 10 and 408 Permit • US Coast Guard Section 9 Permit • RELATED ITEMS – Removal and Disposal of Regulated Substances – River Sediment Management – Wetlands www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  11. Permits • IDNR Permit – Approved based on determination that the project will neither restrict the river’s flood carrying capacity nor adversely impact the public’s interests in the public body of water. – One special condition: bridge removal shall be conducted such that it will not unnecessarily interfere with navigation or create a hazard to boating safety. www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  12. Permits • IL EPA 401 Water Quality Certification Condition – Maintain water quality standards, prevent water pollution, prevent excavated or dredged material from returning back to the waterway or beneath normal flooding levels, implement BMPs and erosion control measures both on land and in the river such as using floating silt curtains. www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  13. Permits • ACOE 404/Section 10 and 408 Permit Conditions – Consultation with IDNR on potential impacts to listed species and aquatic habitat once the method of bridge demolition is selected – Notify the Corps Illinois Waterway Project Office 72 hours prior to the commencement of work – Procedures to follow for unanticipated discoveries of historic, archaeological, or human remains during construction. www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  14. Permits • US Coast Guard Section 9 Permit – No falsework will be used in the navigation channel and no more than 48 hours will be allowed for navigational channel closures; – In order to facilitate times needed for a temporary navigation construction clearance of 315 feet, a tug with a minimum 1200 horsepower will be provided to assist vessels through the bridge on demand. – The existing piers will be removed to at least two feet below existing ground, with the exception of the piers adjacent to the nav channel, which will be removed to 12 feet below normal pool elevation. – Any material accidently falling into the river will be removed and disposed out of the waterway. www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  15. Related Items • Removal and Disposal of Regulated Substances – Areas listed in the plans and specifications shall be managed as specified. • River Sediment Management – Because the depth of the Illinois River is shallow, a temporary causeway and/or dredging of the river sediment, or other access measures, may be required to allow access to construct the bridge. The means and methods are up to the contractor, but a dredging and causeway construction has been estimated for the permit applications. – If dredging is proposed, the method is assumed to be by mechanical removal. Placement locations are assumed to be either certified disposal locations, as specified in the specifications, or possible upland beneficial re-use areas, which would need to be approved by the Department and Illinois EPA. www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  16. Related Items Wetlands Sites 7, 8 and 11 have been delineated www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  17. Commitments • Tri County Search and Rescue – River Access Tazewell County Peoria County www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  18. Commitments Illinois American Water Co. – Sludge and Potable Water Pipelines www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  19. Commitments Lorentz Avenue Pleasure Parkway www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  20. Environmental Key Elements • Endangered Species Protection (Decurrent False Aster) www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  21. Environmental Key Elements • Falcon Protective Netting www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  22. Additional Key Elements • Contractor Staging Area www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  23. Additional Key Elements Parking Lots and Parks Peoria County Tazewell County www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

  24. Thank You Questions/Discussion US 150 McClugage Bridge Project

Recommend


More recommend