Clinton Street Bridge over the Maumee River ODOT Project DEF-15-14.77 September 13, 2016 Public Meeting Purpose of Public Meeting Review project and developments since the last public meeting in May 2015 Discuss how traffic should be


  1. Clinton Street Bridge over the Maumee River ODOT Project DEF-15-14.77 September 13, 2016 Public Meeting

  2. Purpose of Public Meeting  Review project and developments since the last public meeting in May 2015  Discuss how traffic should be maintained during construction  Identify concerns and get public comments

  3. Project Purpose  Replace the deteriorated bridge  Improve pedestrian access and bicycle accommodations

  4. Deteriorated condition of existing bridge

  5. Improve Pedestrian Access

  6. Improve Bicycle Accommodations

  7. Connectivity with Local Bike Plans

  8. Proposed Clinton Street Bridge Section  Bridge cross section view

  9. Bridge Aesthetics (How the new bridge will look)  ODOT, the City of Defiance and Burgess & Niple have worked together to choose bridge aesthetics  Funding will be a combination of ODOT bridge funding, ODOT Transportation Alternatives Program funds, and contributions from the City of Defiance.  Plans includes lighting, decorative piers and railing, and lookouts

  10. Proposed Clinton Street Bridge

  11. Proposed Clinton Street Bridge

  12. Proposed Clinton Street Bridge

  13. Options for Maintaining Traffic During Construction Two options:  Full Closure - Bridge can be closed during construction and traffic can utilize other river crossings  Part-width - Traffic can cross the bridge using one lane of traffic in each direction while the other half of the bridge is being constructed.

  14. Speed of Construction  Full Closure – Faster construction  Allows work to happen on the entire bridge at one time.  Part- width – Slower construction  Requires the bridge to be built in two separate halves at two separate times and then connected.

  15. Detour  Full Closure – Detour required  Traffic will not be able to cross bridge  Part-width - No detour required  Traffic will be able to cross the bridge with one lane in each direction for the duration of the project

  16. Pedestrian/Bicycle Access  Full Closure  No plans to maintain access across the river  Part - width  One sidewalk (minimum 5 feet wide) will remain available to cross river

  17. Safety Service & Hospital Access  Full Closure  Safety services utilize other crossings  Hospitals on both sides of Maumee River  Part - width  Safety services can cross bridge

  18. Traffic Impacts Downtown  Full Closure  Traffic cannot cross the bridge  Less downtown traffic  Traffic management plan to be developed with City  Part - width  Traffic can cross the bridge but with fewer lanes  More downtown congestion and delays possible  Traffic management plan to be developed with City

  19. Traffic Impacts on Other Roadways  Full Closure  Traffic wanting to cross river will use SR 281 and US 24 river crossings  State route traffic will have a signed detour  Part - width  Traffic can cross the bridge but with fewer lanes  Some traffic will choose to use other crossings

  20. Traffic Impacts

  21. R/W Impacts  Full Closure  Less temporary right-of-way required  Part - width  More temporary right-of-way required

  22. Defiance College and Defiance City Schools  Full Closure  College – Students south of bridge need to detour to get to campus  City Schools – Bus routes need to change to account for detour  Part - width  College – Students south of bridge can still cross river on Clinton Street to get to campus  City Schools – Bus routes can stay the same

  23. Current Project Schedule  Construction in 2019  Right-of-way acquisition anticipated to begin in 2017  Project schedule updates will be provided as changes in the schedule are known

  24. Next Steps  Written comments due October 13, 2016  Decision on what to do with traffic during construction: October 20, 2016  Decision announced through media and website

  25. Public Meeting Concerns/Input  Comments, concerns, or any information you can provide are appreciated!  Comments after the meeting should go to:  Jenn Gasser, ODOT District 1, (419) 999-6871, jennifer.gasser@dot.ohio.gov or  Jeff Griffin, Burgess & Niple, (614) 459-2050, jeff.griffin@burgessniple.com  Future project information – go to District 1 website, Construction Projects & click on DEF SR 15 Clinton Street Bridge www.transportation.ohio.gov/dist1