I-70 Blanchette Bridge 2020-2021 Rehabilitation Eastbound I-70 - PowerPoint PPT Presentation

I-70 Blanchette Bridge 2020-2021 Rehabilitation Eastbound I-70 over the Missouri River Existing Eastbound Bridge 3700 Long Bridge Truss (3 spans) Steel Plate Girder (16 spans) Bridge history Opened in 1978 Provided


  1. I-70 Blanchette Bridge 2020-2021 Rehabilitation Eastbound I-70 over the Missouri River

  2. Existing Eastbound Bridge • 3700’ Long • Bridge Truss (3 spans) • Steel Plate Girder (16 spans)

  3. Bridge history  Opened in 1978 − Provided separate eastbound bridge  Major rehab in 2005 − Expansion Joint replacement − Repairs to deck, structural steel, substructure − Full paint overcoated original paint  2005 to present − Driving surface repair, crack repairs  Current Operations − 5 lanes on a 68-ft roadway − 77,000 vehicles per day on eastbound bridge

  4. Upcoming needed Maintenance  Full Paint Replacement  Expansion Joints  Barrier Wall Repair  Structural Repairs  Epoxy Overlay

  5. Why didn’t MoDOT do this in 2012-2013?  Components were not to end of useful life yet  Required to utilize companion Bridge to manage traffic  Project accelerated to 2020 from 2021 original start date because of I- 270 North Design Build Project

  6. Traffic Impacts  Westbound I-70 bridge traffic reduced to 3 WB Lanes + 2 EB Lanes separated by barrier  Eastbound I-70 bridge traffic reduced to 2 EB Lanes during peak commuting times  Nighttime closure of the Eastbound bridge and EB70 on ramps from 5 th Street  Closure of S. 5 th Street beneath Blanchette for joint replacement

  7. I-70 Traffic Configuration for 2020

  8. Schedule  Construction contract expected to be awarded in January  Construction starts March 2020  Goal to have major traffic restrictions completed by Thanksgiving 2020. Closures will continue in 2021. Lane restrictions on Eastbound I-70 only (4 lanes open, additional lane closures off-peak)

  9. Fifth Street Access  Full-duration closure of Eastbound I-70 onramp (VMP)  Nighttime closures Eastbound I-70 onramp (5 th )  Traffic detoured to MO-364 via S. River Road

  10. South Main Street  Short-term closures for expansion joint rehab & painting  Traffic detoured to 5 th Street  Coordination with City of St. Charles

  11. Katy Trail  Short-term closures to allow overhead rehab work  Coordination with Dept. of Natural Resources  On-street detour available during long-term closures

  12. Alternate Routes

  13. Key Stakeholders  St. Charles County businesses  Maryland Heights/North Co businesses  Hospitals  Emergency responders  Attractions/Event facilities  Regional major employers  St. Charles/St. Louis commuters  Regional, state and national trucking companies  Interstate travelers

  14. Key Stakeholder Issues  Access on I-70, at Fifth Street, at Earth City  Schedule for the work and its impacts  Availability and location of alternate routes  Increased commute times  Increased congestion on alternate routes  Emergency response time to the bridge  Increased trucking delivery times

  15. Initial Public Outreach  Creation of I-70 Blanchette Bridge Community Advisory Committee − High level regional issues − Representatives from St. Charles and St. Louis sides of the project − Provide information to regions they represent  Presentations to groups  Media Outreach over winter 2019-2020  Web page on https://www.modot.org/i-70- blanchette-bridge-project

  16. For more information Email: BlanchetteI70@modot.mo.gov Project website: https://www.modot.org/i-70-blanchette-bridge-project CONTACTS I-70 Blanchette Bridge Project Manager Chris Kelly, 314-453-5034 Christopher.Kelly@MoDOT.mo.gov MoDOT St. Charles Area Engineer Andy Tuerck, 314-453-5046 Andrew.Tuerck@MoDOT.mo.gov