MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE Add photo of pipeline install MPWSP Governance Committee Meeting July 18, 2018 1
MPWSP ANTICIPATED SCHEDULE 2017 2018 2019 2020 2021 EIR/EIS AUTHORIZATIONS CDP CPCN IN- PWM SERVICE IN- MONTEREY PL & PS SERVICE START IN- DESAL CONSTRUCTI SERVICE ON
Status Update Pipeline and Pump Station 3
MONTEREY PIPELINE CONSTRUCTION Pump Station Pipeline Crew Bridge Crew ~6.5 miles of 36” pipe installed 8
ASR 5 & 6 RFPs 5
ASR Wells 5 & 6 RFPs • ASR Well Drilling • Design – Bid - Build (DBB) • ASR Well Above Ground Facilities • Design - Build (DB) Interconnects RR-B & HH-TG 6
ASR Wells 5 & 6 Anticipated Schedule Estimated Schedule Start Construction Q2 - Q3 2019 2017 2018 2019 2020 J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D PDR Well Construction/Testing ASR-5 and ASR-6 Wells Specs Bidding PDR Site Prep Facility Construction Start-up Bidding Design Fitch Park ASR Facility Note: Aniticpated schedule is dependent on permit approvals and could shift by up to six months. 7
GC Review of RFPs 8
ASR Wells 5 & 6 RFP Evaluation Criteria 9
Additional future RFPs • Castroville Pipeline • Satellite system interconnect pipelines • Slant Wells Civil & Electrical Work Interconnects RR-B & HH-TG 10
Q & A 11
Recommend
More recommend