mobility update
play

MOBILITY UPDATE N O RT H W E S T A U S T I N C O A L I T I O N F - PowerPoint PPT Presentation

MOBILITY UPDATE N O RT H W E S T A U S T I N C O A L I T I O N F E B R U A RY 2 5 , 2 0 1 9 1 REGIONAL MOBILITY PROJECT UPDATES 2 ANDERSON MILL ROAD Final preliminary engineering report completed Sept. 2018 90% design by March


  1. MOBILITY UPDATE N O RT H W E S T A U S T I N C O A L I T I O N F E B R U A RY 2 5 , 2 0 1 9 1

  2. REGIONAL MOBILITY PROJECT UPDATES 2

  3. ANDERSON MILL ROAD • Final preliminary engineering report completed Sept. 2018 • 90% design by March 2019 • Permitting process could last just over a year • Bid process anticipated to take 6 months • Earliest project could begin construction would be summer 2020 3

  4. SPICEWOOD SPRINGS ROAD • Alternative C selected as the build alternative – 2 vehicle lanes each direction – raised median and left-turn bays – shared use path on both sides – new stormwater facilities • Final preliminary engineering report completed December 2018 • Design phase of the project is now underway 4

  5. RM 2222/RM 620 BYPASS Project 1: RM 2222 (Bonaventure Dr to Ribelin Ranch Dr) – Construction already underway – Anticipated completion: mid-2020 – Construction cost: $17.4 million Project 2: RM 620 (Steiner Ranch Blvd to RM 2222) – Construction start: Fall 2019 – Anticipated completion: Winter 2020 – Construction cost: $10 million 5

  6. PARMER LANE Proposed Improvements – 3 lanes in each direction – Improve intersections and turn lanes – Dedicated bicycle/pedestrian path Project Development Timeline – Preliminary Design: 2019 – Final Design/Engineering: 2020 – Utility Relocation: 2021 – Estimated Construction Start: 2022 6

  7. 2016 MOBILITY BOND UPDATE Regional Mobility: $101 million to address regional congestion and enhance safety Corridor Mobility: $482 million for corridor improvement projects Local Mobility: $137 million to local mobility projects, including: – Sidewalks – Safe Routes to School – Urban Trails – Bikeways – Vision Zero – Sub-standard Streets 7

  8. MOBILITY PLANNING ACTIVATES 8

  9. AUSTIN STRATEGIC MOBILITY PLAN (ASMP) Final ASMP draft released on Feb. 22 nd ASMP to be adopted later this spring Important Dates – Council Mobility Committee: Feb. 28 th 1:00-3:00 pm – Planning Commission: • March 12 th 6:00 pm (Public Hearing) • March 26 th 6:00 pm – City Council • March 28 th (Public Hearing) 9

  10. PROJECT CONNECT • CapMetro to adopt Public Engagement Plan in Spring 2019 • High Capacity Transit • Service Type – Commuter Service – Local Service • Important Dates – Joint Meeting of the City Council and Capital Metro Board: March 4 th 10

  11. CAPITAL AREA METROPOLITAN PLANNING ORGANIZATION (CAMPO) • May 2018 adopted the 2019-2022 TIP – Secured $13.7 million for Lakeline Blvd • Project Improvements: – Add two additional travel lanes – Upgrade bicycle facilities and sidewalks 11

  12. RM 620 COLORADO RIVER TO US 183 • RM 2222/RM 620 Bypass Project – Project 1: RM 2222 - Construction already underway – Project 2: RM 620 - Construction start: Fall 2019 • RM 620/Anderson Mill Intersection – Study in progress • RM 620 - Anderson Mill Rd to US 183 – Discussions on going for this segment 12

  13. COMMUNITY PLACEMAKING TOOLKIT Working with City Staff to develop a Community PlacemakingToolkit 13

  14. DISTRICT 6 NEWSLETTER Get ongoing updates from the D6 office on community events and the latest from City Hall! Subscribe today by visiting: http://www.atxd6.org/contact/ subscribe/ 14

Recommend


More recommend