East Rockaway Community Meeting Bay Park Sewage Treatment Plant September 17, 2014 Meeting Agenda Review of Last Meeting Milestones and Timeline Active construction projects Schedule Plant treatment performance Questions 2


  1. East Rockaway Community Meeting Bay Park Sewage Treatment Plant September 17, 2014

  2. Meeting Agenda • Review of Last Meeting • Milestones and Timeline • Active construction projects • Schedule • Plant treatment performance • Questions 2 7 October 2014

  3. Review of Last Meeting • Community Concerns: • Temporary engine generator noise • Soil quality • Construction-related dust • Additional lighting in Park • Maintaining trees and berm in the Park 3 7 October 2014

  4. Milestones and Timeline 4 7 October 2014

  5. Schedule Update – Capital Projects Construction Existing Capital Projects Construction Start Complete Odor Control at Bay Park & Cedar Creek 28-Oct-13 12-Oct-15 Influent Screening Facility Improvements 27-May-14 24-Nov-16 Grit Removal Facility Improvements 30-Sept-14 23-Aug-16 Sludge Thickening Facility Improvements 28-Oct-13 27-Oct-15 Cleaning & Repair of Digesters & Storage Tanks 20-May-13 28-May-15 Generator Controls 15-Nov-13 20-Apr-15 Construction Hurricane Sandy Pump Stations Projects Construction Start Complete Dock Place & Southland Drive 28-Oct-13 19-Sept-14 Cedar, Roosevelt, Whitewood, Biltmore & Alhambra 04-May-15 03-Nov-16 Wantagh, Newbridge, Merrick & Ray 20-Apr-15 20-Oct-16 Millar, Mott, Long Beach, Royal & Lido 04-May-15 03-Nov-16 Ocean, Mill, Woodmere, Longagree & Doxey 04-May-15 03-Nov-16 East, Inwood, Doughty & Bayview 4-May-15 3-Nov-16 Roslyn Road 4-May-15 3-Nov-16 Barnes Ave SSO & Hempstead Flow Diverson 11-May-15 10-Nov-16 5 7 October 2014

  6. Schedule Update – Capital Projects Construction Construction Hurricane Sandy Projects Start Complete Final Settling Tank Rehabilitation 28-Oct-13 27-Oct-15 Phase E1 Electrical Distribution System Improvements 27-May-14 26-Mar-16 Phase E2 Substation No.2 & Electrical Distribution 29-Dec-14 28-Oct-16 Phase E3 Main Substation & Electrical Distribution 18-May-15 28-Dec-17 Perimeter Flood Protection 27-May-14 4-Jun-16 Flood Protection Phase 1 Stormwater Pumping Stations 24-Aug-15 06-Sept-17 Flood Protection Phase 2 Stormwater Green Infrastructure 4-Jul-17 3-Jul-18 Sludge Dewatering 22-Jun-15 21-Jun-18 Sludge Dewatering Demolition 11-Sept-14 09-Mar-15 Vehicle Fueling & Tanks Reconstruction 30-Sept-14 26-June-15 Effluent Tide Pumping Building 07-Sept-15 14-Nov-17 Effluent Screening & Disinfection 04-Jan-16 17-Jan-18 Digesters 26-Mar-16 04-Apr-18 Secondary Treatment 21-Mar-16 04-Apr-18 Influent Screens & RSPs 4-Jan-16 17-Jan-18 Grit Removal & Primary Settling 21-Mar-16 04-Apr-18 Central & Distributed HVAC 26-Mar-16 06-Oct-17 Odor Control Systems 21-Mar-16 06-Oct-17 General Plant Site Facilities 21-Mar-16 04-Apr-18 Sludge Thickening 24-Mar-16 12-Apr-17 Lawrence STP & Sage Lake PS 19-Oct-15 20-Apr-17 6 7 October 2014

  7. Plant Treatment Performance 7 7 October 2014

  8. Plant Treatment Performance 8 7 October 2014

  9. Active Construction Projects - East Park 9 7 October 2014

  10. Active Construction Projects - East Park 10 7 October 2014

  11. Active Construction Projects - Perimeter Flood Protection 11 7 October 2014

  12. Active Construction Projects - Perimeter Flood Protection 12 7 October 2014

  13. Active Construction Projects - Perimeter Berm 13 7 October 2014

  14. Active Construction Projects - Perimeter Berm 14 7 October 2014

  15. Active Construction Projects - West Berm 15 7 October 2014

  16. Active Construction Projects - West Berm 16 7 October 2014

  17. Active Construction Projects - Plant-wide Odor Control Upgrades 17 7 October 2014

  18. Active Construction Projects - Plant-wide Odor Control Upgrades 18 7 October 2014

  19. Active Construction Projects - Plant-wide Odor Control Upgrades 19 7 October 2014

  20. Active Construction Projects - Primary Source Power Generation Controls Rehabilitation 20 7 October 2014

  21. Active Construction Projects - Primary Source Power Generation Controls Rehabilitation 21 7 October 2014

  22. Active Construction Projects - Digesters Repair & Cleaning 22 7 October 2014

  23. Active Construction Projects - Sludge Thickening Improvements 23 7 October 2014

  24. Active Construction Projects - Final Settling Tank Rehabilitation 24 7 October 2014

  25. Active Construction Projects - Phase E1 Electrical Distribution System 25 7 October 2014

  26. Active Construction Projects - Phase E1 Electrical Distribution System 26 7 October 2014

  27. Active Construction Projects - Phase E1 Relocation of Site Utilities 27 7 October 2014