East Rockaway Community Meeting Bay Park Sewage Treatment Plant March 24 th 2015
Meeting Agenda • Announcements • Address Previous Public Comments & Concerns • Noise • Road Maintenance • Vibrations • Outfall Pipe • Sand and salt piles on south side of Park • Plant Treatment Performance • Construction Schedule • Active Construction Projects • Community Parks • Questions 2 26 March 2015
Announcements The 5 th Avenue guardhouse will be closed at the beginning of April and all traffic will be detoured to the southwest corner of the plant using Marjorie Lane and the East Park road. 3 26 March 2015
Review of Last Meeting Concerns Corrective Measures Noise reduction measures in place Noise •Working with Road Maintenance to reduce noise •Sent letters to vendors & contractors to abide by the pick up/drop off times as stipulated in their contracts Effluent testing measures in place Treated Effluent into Bay • Verifying accuracy of results H2S perimeter detection system Odor • Digester cleaning completed • Monitoring odor very closely Augered piles to reduce vibrations Vibrations • Less vibrations expected moving forward Community Park Park construction in progress • Sand and salt piles • Resolving for next year Notifications of meetings and other events Website, mailers, and calls 4 26 March 2015
Plant Treatment Performance – TSS 5 26 March 2015
Plant Treatment Performance – CBOD 6 26 March 2015
Construction Schedule [As of March, 2015] *Schedule subject to change 7 26 March 2015
Community Park (East Park) [As of March, 2015] 8 26 March 2015
Community Park (East Park) [As of February, 2015] 9 26 March 2015
Community Park [As of March, 2015] 10 26 March 2015
Odor Control at Bay Park [As of February, 2015] 11 26 March 2015
Odor Control at Bay Park [As of February, 2015] 12 26 March 2015
Odor Control at Bay Park [As of February, 2015] 13 26 March 2015
Odor Control at Bay Park 14 26 March 2015
Phase E1 Electrical Distribution System [As of February, 2015] 15 26 March 2015
Phase E1 Electrical Distribution System [As of February, 2015] 16 26 March 2015
Sludge Dewatering Demolition [As of February, 2015] 17 26 March 2015
Generator Controls [As of February, 2015] 18 26 March 2015
Perimeter Flood Protection (Berm) [As of February, 2015] 19 26 March 2015
Perimeter Flood Protection (Berm) [As of February, 2015] 20 26 March 2015
Bay Park STP – Berm Update 21 26 March 2015
Bay Park STP – Berm Update 22 26 March 2015
Bay Park STP – Strategic Plan – Berm Progress 23 26 March 2015
Website www.bayparknc.com BPSTPSandyRecovery@nassaucountyny.com 24 26 March 2015
Your Questions
Recommend
More recommend