Rockaway Boardwalk Reconstruction CB14 Parks Committee Meeting November 18, 2013 7:00 P.M. Knights of Columbus
Agenda • Recap • Community Meetings To Date • Surface Treatment Survey Results • Initial Construction Area • Scope of Work • Project Area Schematic and Renderings • Amenities • Surface Treatment Concepts 2 Rockaway Reconstruction
Previous Community Meetings Meeting Date September 17, 2013 CB14 Parks Committee Presentation – Background and Constraints Neighborhood Listening Sessions – September 23, 24, 25, 2013 Access, Surface, Recreation and Boardwalk Design Full CB 14 Meeting – Update and October 8, 2013 General Design Principles Community Listening Session – October 23, 2013 Access, Surface and Amenities 3 Rockaway Reconstruction
Surface Survey Results 680 Respondents Walking down the boardwalk, which of the following would you rate as most important? Please choose 1. 300 250 200 150 100 50 0 Feel on your feet/roughness Ability to stay cool/temperature Unique Identity 4 Rockaway Reconstruction
Surface Survey Results 680 Respondents If you had to choose a way to highlight special areas of the boardwalk, what would be your top choice? Please choose 1 or 2. 450 400 350 300 250 200 150 100 50 0 Bright Color Sparkle Special Material (shells Sandy Memorial or glass) (examples on boards) 5 Rockaway Reconstruction
Surface Survey Results 680 Respondents Which color preference is more important? Please choose 1. 450 400 350 300 250 200 150 100 50 0 Lighter (cooler but with more glare) Darker (warmer but less glare) 6 Rockaway Reconstruction
Surface Survey Results 680 Respondents For special areas, which do you prefer for decorative finish? Please choose 1. 400 350 300 250 200 150 100 50 0 Tumbled Recycled Glass Colored Stone 7 Rockaway Reconstruction
Surface Survey Results 680 Respondents What types of areas should have special accents (e.g. playgrounds, sitting areas, entrances, etc.) 350 Please choose 1 or 2. 300 250 200 150 100 50 0 Entrances Playgrounds Sitting areas 60 50 40 30 20 10 0 8 Rockaway Reconstruction
Surface Survey Results 680 Respondents Would you like to have a designated bike lane (marked with striped or special paving) or an informal bike lane (with just signs)? 350 300 250 200 150 100 50 0 Designated bike lane Informal bike lane Yes, bike lane No bike lane 9 Rockaway Reconstruction
Surface Survey Results 680 Respondents Do you like the existing precast planks on the boardwalk between Beach 77 and Beach 81? Why or why not? 350 300 250 Positive 200 Negative Mixed 150 100 50 0 Overall Aesthetics Durability Texture Walking, Jogging, and Biking 10 Rockaway Reconstruction
Initial Construction Area Overall Site Plan 11 Rockaway Reconstruction
Boardwalk Accent Preliminary Concepts Option A: Graphic Text Design 12 Rockaway Reconstruction
Boardwalk Accent Preliminary Concepts Option B: Bubble Design 13 Rockaway Reconstruction
Boardwalk Accent Preliminary Concepts Option C: Wave Design 14 Rockaway Reconstruction
Boardwalk Accent Preliminary Concepts Option A: Graphic Text Design 15 Rockaway Reconstruction
Boardwalk Accent Preliminary Concepts Option A: Graphic Text Design 16 Rockaway Reconstruction
Boardwalk Accent Preliminary Concepts Option A: Graphic Text Design 17 Rockaway Reconstruction
Boardwalk Accent Preliminary Concepts Option A: Graphic Text Design 18 Rockaway Reconstruction
Boardwalk Accent Preliminary Concepts Option B: Bubble Design 19 Rockaway Reconstruction
Boardwalk Accent Preliminary Concepts Option B: Bubble Design 20 Rockaway Reconstruction
Boardwalk Accent Preliminary Concepts Option B: Bubble Design 21 Rockaway Reconstruction
Boardwalk Accent Preliminary Concepts Option C: Wave Design 22 Rockaway Reconstruction
Boardwalk Accent Preliminary Concepts Option C: Wave Design 23 Rockaway Reconstruction
Boardwalk Accent Preliminary Concepts Option C: Wave Design 24 Rockaway Reconstruction
Boardwalk Lighting Height Options Lighting Option: 30’ Davit Pole Rockaway Reconstruction
Boardwalk Lighting Height Options Lighting Option: 16’ Davit Pole Rockaway Reconstruction
Lighting Options Davit Pole with City Light LED Solar LED Lighting TBTA Pole LED Cobra Fixture Head 27 Rockaway Reconstruction
Lighting Option Davit Pole with Cobra Head 28 Rockaway Reconstruction
Lighting Option TBTA Pole with Teardrop Head 29 Rockaway Reconstruction
Lighting Option City Light 30 Rockaway Reconstruction
Lighting Option Solar Swan – 25’ 31 Rockaway Reconstruction
Lighting Option Solar Swan – 15’ 32 Rockaway Reconstruction
Boardwalk Elevation Initial Construction Area 33 Rockaway Reconstruction
Boardwalk Construction Engineering Elements 34 Rockaway Reconstruction
Boardwalk Construction Pile Cap Removal and Pile Extensions Pile Cap Demolition of Existing Pile Cap Extension Detail 35 Rockaway Reconstruction
Boardwalk Construction Engineering Elements 36 Rockaway Reconstruction
Benches 1964 World’s Fair Bench with RPL Slats 1964 World’s Fair Backless Bench with and Galvanized Steel Legs RPL Slats and Galvanized Steel Legs 37 Rockaway Reconstruction
Drinking Fountains Haws Fountain WXY Prototype as seen at Transmitter Park 38 Rockaway Reconstruction
Foot Showers 39 Rockaway Reconstruction
Railing Options Pipe Railing – Potential for South Side DPR Standard Rail 40 Rockaway Reconstruction
Bike Racks DPR Standard Bike Rack 41 Rockaway Reconstruction
Trash Receptacles Trash and Recycle Receptacles 42 Rockaway Reconstruction
Questions and Discussion 43
Recommend
More recommend