This presentation is for the project on US 10 and WIS 65 in the village of Ellsworth, Pierce County. Rather than holding an in-person meeting, public involvement efforts have moved online as a precaution against COVID-19 based on the most current health information from state, federal and local health departments. All meeting materials, including the handout with a comment form, are posted on the design website for this project. https://wisconsindot.gov/Pages/projects/by-region/nw/us10wis65ellsworth/default.aspx If you have any questions, please contact WisDOT Project Supervisor James Koenig at (715) 838-8391.
Public Involvement Meeting WIS 65 US 10 Village of Ellsworth Village of Ellsworth Main Street Maple Street WIS 65 to N. Beulah St. US 10 to Midway Ave.
Project Team • James Koenig • WisDOT Project Supervisor • Brett Hollister • WisDOT Consultant Project Manager • Julie Martin • WisDOT Real Estate Specialist • Brad Halvensleben • Consultant Project Manager (KL Engineering, Inc.)
Presentation Agenda • Project Location • Project Purpose and Need • Proposed Improvements • Construction Staging • Real Estate • Project Schedule • Contact Information
Project Location
Purpose and Need • Purpose Improve US 10 and WIS 65 pavement condition Improve truck turning at the US 10 and WIS 65 intersection Upgrade curb ramps to meet current standards • Need Deteriorating pavement condition Conflicting truck turning movements at the US 10 and WIS 65 intersection Non-compliant curb ramps
Proposed Improvements • Resurface US 10 with asphalt pavement • Mill and resurface WIS 65 with asphalt pavment • Realign left-turn lanes at US 10 and WIS 65 intersection • Upgrade curb ramps • Replace pavement marking
Proposed Construction Staging • 2021 construction season (June-October) • Open to traffic • Single-lane closures through flagging operations • Pedestrian detours during curb ramp replacement
Real Estate • Real Estate acquisition for US 10 and WIS 65 intersection improvements • Temporary easements for curb ramp upgrades • Real Estate Acquisition Process • Contact: Julie Martin, (715) 836-2875 or julie.martin@dot.wi.gov
Project Schedule • Environmental Document January 2020 • Preliminary Plans January 2020 • Real Estate Plat May 2020 • Public Involvement Virtual Presentation July 2020 • Final Plans November 2020 • Construction Summer 2021
What we need from you Share Your Concerns or Comments https://wisconsindot.gov/Pages/projects/by-region/nw/us10wis65ellsworth/default.aspx Responses returned by Aug. 14, 2020 • By email: HollisterB@AyresAssocites.com • By mail: o James Koenig Wisconsin Department of Transportation 718 W. Clairemont Ave. Eau Claire, WI 54701 Thank you for your time
Project Team • James Koenig, WisDOT Project Supervisor • (715) 838-8391 • james.koenig@dot.wi.gov • Brett Hollister, WisDOT Consultant Project Manager • (715) 834-3161 • HollisterB@AyresAssociates.com • Julie Martin, WisDOT Real Estate Specialist • (715) 836-2875 • julie.martin@dot.wi.gov • Brad Halvensleben, Consultant Project Manager • (608) 663-1218, Ext. 826 • bhalvensleben@klengineering.com