5245-02-02, 72 WIS 23 WIS 11– Mineral Point County Shop Road to Minerva Street Lafayette County Public Involvement Meeting #3 October 11, 2018 5:30 p.m. to 7:30 p.m.
Project Team WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Matt Dapp, PE WisDOT Design Team James Rinzel WisDOT Real Estate Team Teresa Klein Kema Williams 2
Project Team Structure Design Michael Baker International Plat Development and Survey JT Engineering Municipal Design Delta 3 Engineering Vierbicher KL Engineering 3
Overview Project Location Existing Facility Project Needs Project Improvements Project Impacts Project Schedule Open House 4
Project Location Minerva Street County Shop Rd 5
Existing Facility 1.49-mile roadway section Two-lane urban roadway Residential area south of the bridge Concrete replaced in 1966 Asphalt replaced in 1984 6,900 vehicles per day Business area north of the bridge Asphalt replaced in 1989 2,700 – 10,000 vehicles per day Parking lanes Variable Land Terrain 66 foot right-of-way width (typical) 6
Project Needs Pavement Deterioration Structure Deterioration Substandard Roadway Features Intersection Geometry ADA Concerns Crosswalk Locations Utility Replacements Water Sanitary Lighting Storm Sewer 7
Project Improvements Roadway Sections Superstructure Replacement Intersection Improvements OSOW Accommodations ADA Upgrades Utility Replacements 8
Roadway Sections Proposed Section County Shop Road to Center Hill Road 9
Roadway Sections Proposed Section Center Hill Road to Pecatonica River Bridge 10
Retaining Walls Modular Block Retaining Wall 11
Roadway Sections Proposed Section Pecatonica River Bridge to Cornelia Street 12
Roadway Sections Proposed Section Cornelia Street to Harriet Street 13
Roadway Sections Proposed Section Harriet Street to Mary Street 14
Roadway Sections Proposed Section Mary Street to Lucy Street 15
Roadway Sections Proposed Section Lucy Street to Minerva Street 16
Superstructure Replacement Replace Bridge Deck Built 1968, Concrete Overlay 1993 Install Concrete Parapet with Metal Railing Repair Substructure Include 6 ft Sidewalk Lighting on Structure 17
Intersection Improvements Center Hill Road/Union Grove Lane Re-alignment Improved intersection angle with WIS 23 Improved vehicle visibility Proposed Location Proposed Location 18
Intersection Improvements Huntington Court Re-alignments (Minor) Improved intersection angle with WIS 23 Pedestrian accommodations Proposed Location Proposed Location 19
Intersection Improvements Harriet Street Intersection Widenings Improved truck turning movements Wider paved shoulders and corners Proposed Widening Proposed Widening 20
Intersection Improvements Washington Street Cul-de-Sac at Lucy Street Improve intersection layout Cul-de-Sac Location 21
ADA Upgrades ADA Curb Ramps 22
Crosswalk Locations Crosswalks ADA Curb Ramps Crosswalks 23
Utility Replacement Water Utilities Replace watermain and services from Center Hill Road to Lucy Street Sanitary Utilities Replace sanitary main sections south of Alice Street and from Harriet Street to Lucy Street Install sanitary main connections at Huntington Court, Ravine Street and County F Replace services from Center Hill Road to River Street and from Harriet Street to Lucy Street Lighting Replace lighting from bridge to Harriet Street 24
Utility Replacement Storm Sewer Utilities Replace storm sewer main and laterals from Center Hill Road to Lucy Street Install check valves at structure for flooding 25
Project Impacts Detours Access over Pecatonica River Roadway Shift Real Estate 26
Detour WIS 23 Detour (30.3 miles) US 151 – 14.3 miles WIS 126 – 5.7 miles WIS 81 – 10.3 miles 27
Detour WIS 81 Detour (25.9 miles) WIS 23 – 6.1 miles WIS 78 – 13.8 miles WIS 11 – 6.0 miles 28
Access over Pecatonica River Access maintained for emergency services and local residents/businesses One lane open over bridge during construction Temporary Signals 29
Access over Pecatonica River Access maintained for emergency services and local residents/businesses One lane open over bridge during construction Temporary Signals 30
Roadway Shift Existing Land Terrain Steep west of WIS 23 Flat east of WIS 23 Existing Centerline Proposed Centerline 31
Real Estate WisDOT Representatives Teresa Klein Kema Williams Real Estate Acquisitions 85 Total Properties FEE (permanent acquisitions) TLE (temporary limited easements) Appraisal Staking – Fall 2018 Potential Property Impacts Carriage Walk Removal Tree Removal Access Removal Real Estate Acquisition 2019 - 2020 32
Project Schedule Public Involvement Meeting #1 May 2016 Archeological Survey May 2016 Historical Survey May 2016 Hydrology Study May 2016 Soil Testing Summer 2016 Public Involvement Meeting #2 November 2016 Project Plat July 2018 Environmental Report Submittal January 2018 Public Involvement Meeting #3 October 11, 2018 Real Estate Acquisitions 2019 – 2020 Utility Coordination January 2019 Public Involvement Meeting #4 TBD – Prior to Construction Agency Coordination (DNR, etc.) Ongoing Final Plans Due May 2020 Construction Spring – Fall 2021 33
Input ‘Dot’ Exercise STEP 1 – Place number on the map. STEP 2 – Write number and comment on form and submit in comment box. 12 34
35
Recommend
More recommend