WIS 96 Project Update Tim Rank, Project Manager Jeremy Bartz, - PowerPoint PPT Presentation

WIS 96 Project Update Tim Rank, Project Manager Jeremy Bartz, Project Leader WisDOT July 2020 WIS 96 Overview Proposed Project Scope/Need Proposed Improvements Right-of-way Needs Traffic Control Schedule Resources


  1. WIS 96 Project Update Tim Rank, Project Manager Jeremy Bartz, Project Leader WisDOT July 2020

  2. WIS 96 • Overview  Proposed Project Scope/Need  Proposed Improvements  Right-of-way Needs  Traffic Control  Schedule  Resources  Project Contacts

  3. WIS 96 Proposed Project Scope/Need  Projects 4075-35-71 and 4075-35-72 include 4.9 miles of WIS 96 from Claribel Street to County D, between Kaukauna and Wrightstown in Brown & Outagamie County (will be built together)  Last improvement project took place in 2000 and 2005

  4. WIS 96 Proposed Project Scope/Need  Deteriorating pavement, drainage structures, curb and gutter, and sidewalk need repair  Multiple curb ramps along the corridor are currently not Americans with Disabilities Act (ADA) compliant.

  5. WIS 96 Proposed Project Scope/Need

  6. WIS 96 Proposed Improvements • 4075-35-71 (Claribel Street to County J)  Resurface level improvement: mill and overlay within the existing pavement footprint  Culvert pipe repair/replacement-2 locations  Miscellaneous curb & gutter repairs  Curb ramp improvements at Lamp Lighter Dr.  Pavement marking  Shoulder work • Additional project information, including project displays, can be found at the design website listed on the Resources slide.

  7. WIS 96 Proposed Improvements • 4075-35-72 (County J to County D)  Resurface level improvement: mill and overlay within the existing pavement footprint  Culvert pipe repair/replacement-5 locations  Storm sewer repair/replacement-4 locations  Miscellaneous curb & gutter or sidewalk repairs  Curb ramp improvements at all intersections within Wrightstown  Pavement marking  Shoulder/centerline rumble strips: from County J to Van Dyke Street  Shoulder work: from County J to Van Dyke Street • Additional project information, including project displays, can be found at the design website listed on the Resources slide.

  8. WIS 96 Right-of-way Needs  Temporary Limited Easements (TLE) • Will be needed at some culvert replacement locations to allow for temporary disturbance and sufficient work space to repair pipes • Needed at most curb ramp improvement locations within the Village of Wrightstown to allow grading and blending in of adjacent properties  Permanent (Fee) • Will be needed at some curb ramp improvement locations in the village of Wrightstown due to updated layout of the sidewalk • Will purchase area were existing sidewalk is outside of the existing right of way to place the sidewalk into WisDOT right of way for future maintenance needs • May need at select culvert locations…to be confirmed in final design

  9. WIS 96 Traffic Control  Work expected to take place under flagging operations with single lane closures  Road will remain open to traffic during construction for the majority of the project….except: • Short term detour will be needed for culvert pipe replacements • Tentative detour = WIS 55 - I-41 - County U

  10. WIS 96 Schedule  Additional public outreach will be conducted in late 2021 to provide updates prior to real estate acquisition and final design.  Real estate acquisition will begin in early 2022.  Design is on-going and will continue through the summer of 2023.  Construction is tentatively scheduled for 2025 with the possibility of advancement to 2024 if funding becomes available.

  11. WIS 96 Resources  Design website  https://wisconsindot.gov/Pages/projects/by- region/ne/96kauwrit/default.aspx  See website for comment sheet and exhibits  Track the project during construction on the WisDOT Northeast Region Construction Website  https://projects.511wi.gov/region/northeast  In This Together  Recognizes businesses located in work zones have special needs  The program is offered to business and community leaders as an idea source as they plan for road construction in their area  Find out more at: http://wisconsindot.gov/Pages/projects/in- together/default.aspx

  12. WIS 96 Project Contacts Tim Rank, P.E. Jeremy Bartz, P.E. Project Manager Project Leader WisDOT NE Region WisDOT NE Region 944 Vanderperren Way 944 Vanderperren Way Green Bay, WI 54304 Green Bay, WI 54304 Phone: (920) 360-2579 Phone: (920) 363-6356 Email: tim.rank@dot.wi.gov Email: jeremy.bartz@dot.wi.gov