perth transport future project phase 2 cross tay link road
play

Perth Transport Future Project Phase 2 -Cross Tay Link Road CIHT - PowerPoint PPT Presentation

Perth Transport Future Project Phase 2 -Cross Tay Link Road CIHT Presentation 25 February 2020 AK Bell Library ROSS FLETCHER SENIOR ENGINEER ROADS INFRASTRUCTURE (PLANNING & DEVELOPMENT) Introduction Welcome Housekeeping


  1. Perth Transport Future Project Phase 2 -Cross Tay Link Road CIHT Presentation 25 February 2020 – AK Bell Library ROSS FLETCHER SENIOR ENGINEER – ROADS INFRASTRUCTURE (PLANNING & DEVELOPMENT)

  2. Introduction  Welcome  Housekeeping  Ross Fletcher – Background to Perth Transport Futures Project & Cross Tay Link Road  Denise Ritchie – Design of Cross Tay Link Road  Emma Cooper – EIA & Planning Application for the Cross Tay Link Road  Ross Fletcher – Procurement & Next Steps

  3. Roads Infrastructure Team  Small client team of 5  Set up in 2013/14  Situated within Planning & Development (Corporate & Democratic Services)  Work closely with Transport Planning colleagues who progress proposed large roads schemes to end of DMRB Stage 2  Once there is a Business Case and Budget for a scheme it is handed to the Roads Infrastructure Team  We manage the delivery phase which generally consists of site investigations, design through to DMRB Stage 3, land purchase, planning process and construction.  We rely on support from colleagues in Legal, Planning, Estates, Finance and many others. Also rely on external support from consultants, DVS, Legal Advisors etc.

  4. Perth Transport Futures Project  Strategic Rationale  Perth – major strategic hub  Delivery of sustainable growth in the Tay Cities region  Support the Northwest expansion of Perth as envisaged in the Local Development Plan (new LDP recently launched)  Perth – AQMA. High priority given current climate crisis.  Ambitious City Plan  Integrated Series of Measures over Four Phases  Phase 1 – A9/A85 scheme (complete)  Phase 2 – CTLR  Phase 3 – Bertha Park connection  Phase 4 – City centre improvements (including greener travel – Perth, People, Place with SUSTRANS)

  5. Phase 1 – A9/A85 Scheme  Commenced on-site September 2016  Designer – CH2M  Contractor – Balfour Beatty  Complete May 2019 (roads opened January 2019 – 3 months early)  Benefits / Features  New grade separated junction on A9  Link road to Bertha Park development (including new school)  New access to industrial estate  Relieve pressure on Inveralmond Roundabout and Crieff Road corridor

  6. Phase 1 – A9/A85 Scheme  NEC3 Option A Contract (Scape Procure)  £37.9m final cost (within 7% of initial price)  Collaborative approach  Significant Community Benefits Programme  Social Value of £12.9 or £0.42 per £1 spent  Recognised for collaborative approach  Various Awards including:  NEC Contract of the Year 2019  CECA Community Award 2019  National Social Value Award 2018  End of Project Review – Lessons learned fed into CTLR strategies

  7. Phase 2 - Cross Tay Link Road AIMS OF THE CROSS TAY LINK ROAD Reduced congestion and improved air quality in the city centre and Bridgend  Enable new, planned and committed developments – sustainable economic growth  Enable city centre improvements including a move towards greener travel  Connecting communities and improving access to Scone Palace and Perth Racecourse  for events MAIN FEATURES OF THE CROSS TAY LINK ROAD New crossing of River Tay north of Perth  New grade separated junction between Inveralmond Roundabout  and Luncarty New link road from the A9 to the A94 (with roundabouts on  Stormontfield Road, A93 and Highfield Track) Active travel route for full length of new road 

  8. Phase 2 - Cross Tay Link Road LOCAL DEVELOPMENT PLAN 2

  9. Phase 2 - Cross Tay Link Road Reduction in traffic congestion – modelling by SYSTRA / Transport Planning – air quality improvement evident as shown

  10. Phase 2 - Cross Tay Link Road SCHEME TIMELINE 2010 to 2016 Technical Assessment (DMRB – Stages 1 & 2 complete)  June 2016 – Council commits Capital funding of £78 million  December 2016 - Council approved the Preferred Route  Early 2017 – Scheme passed to Roads Infrastructure Team for delivery  Early 2017 to Present - liaison with land owners (ongoing_  July 2017 - SWECO appointed as designers (for specimen design)  July 2017 to Present - consultation with statutory bodies / environmental groups (ongoing)  Early 2018 to mid 2019 Site Investigations / Surveys 

  11. Phase 2 - Cross Tay Link Road SCHEME TIMELINE April 2018 to January 2019 Early Contractor Involvement (Balfour Beatty)  Summer 2018 – First Public Consultations  December 2018 – First draft of Specimen Design completed  January 2019 – Scottish Government commits £40 million to project  February to June 2019 – Alignment review between A93 and A94 (caused a six month  delay) Summer 2019 – Final round of public consultations in advance of planning application 

  12. Phase 2 - Cross Tay Link Road SCHEME TIMELINE September 2019 – Design layout finalised for planning  application and land purchase September 2019 – Council approval to proceed with  Compulsory Purchase of land required Compulsory Purchase Order made on 30 October 2019 (with  Scottish Ministers) Planning Application (including EIA) submitted in November  2019 (decision expected by April 2020)

  13. CROSS TAY LINK ROAD CIHT PRESENTATION – SWECO 25 FEBRUARY 2020 DENISE RITCHIE EMMA COOPER 13 2020-03-03

  14. CROSS TAY LINK ROAD SWECO – Stage 3 Input • Scheme Overview and Key Infrastructure • Site Investigations • Constraints • Current Specimen Design Status • Stakeholders and Landowners • Environmental Impact Assessment and Planning • Project Risks • Bulk Quantities 14 2020-03-03

  15. CROSS TAY LINK ROAD SCHEME OVERVIEW 15 2020-03-03

  16. CROSS TAY LINK ROAD SCHEME OVERVIEW (PART 1 of 4) 16 2020-03-03

  17. CROSS TAY LINK ROAD SCHEME OVERVIEW PART 2 of 4 GENDIATUR, QUE REIUNT EXPLABO. UT ASINCTIIS 17 DE VOLLACCAB ISUNT ET EOS QUATIANDANDI DELLECU LLUPTIIST 2020-03-03

  18. CROSS TAY LINK ROAD SCHEME OVERVIEW PART 3 of 4 18 2020-03-03

  19. CROSS TAY LINK ROAD SCHEME OVERVIEW PART 4 of 4 GENDIATUR, QUE REIUNT EXPLABO. UT ASINCTIIS 19 DE VOLLACCAB ISUNT ET EOS QUATIANDANDI DELLECU LLUPTIIST 2020-03-03

  20. CROSS TAY LINK ROAD KEY INFRASTRUCTURE – A9 JUNCTION • Agreed design • Loop arrangement is compact • Future proofed 20 2020-03-03

  21. CROSS TAY LINK ROAD KEY INFRASTRUCTURE – A9 OVERBRIDGE • Structural form • Aesthetics • Piled foundations 21 2020-03-03

  22. CROSS TAY LINK ROAD KEY INFRASTRUCTURE – RIVER TAY CROSSING • Structural form • Clearances and temporary works • Fishing rights, and • Access options to the western pier 22 2020-03-03

  23. CROSS TAY LINK ROAD KEY INFRASTRUCTURE – CTLR ROAD CROSS SECTION • single carriageway • 85kph design speed • Segregated cycleway, and • Grass verges and separation strip. 23 2020-03-03

  24. CROSS TAY LINK ROAD KEY INFRASTRUCTURE – JUNCTIONS Stormontfield Road Roundabout A94 Roundabout A93 Roundabout 24 2020-03-03

  25. CROSS TAY LINK ROAD KEY INFRASTRUCTURE – HIGHFIELD GREEN BRIDGE • Buried precast concrete arch • Aesthetics • Connects NMU infrastructure, and • Provides ecological and landscape connectivity. 25 2020-03-03

  26. CROSS TAY LINK ROAD KEY INFRASTRUCTURE – LANDSCAPE • High quality landscape • Wetland area, and • Park and cycle facility 26 2020-03-03

  27. CROSS TAY LINK ROAD SITE INVESTIGATIONS The following were completed early in Stage 3: • Ecological surveys • Tree surveys; • Topographical, bathymetric and drainage surveys; • NMU CCTV surveys; • Ground investigation in 2018; and • Intrusive archaeological investigations (trial trenching and geophysical surveys) in early 2019 27 2020-03-03

  28. CROSS TAY LINK ROAD SITE INVESTIGATIONS • A9 Ground Conditions – A9 Mainline south - raised tidal flat deposits and alluvium; – Broxy Wood is a drumlin of glacial till; – Grade separated junction - raised marine deposits; and – North of Broxy Kennels - glacial deposits. • CTLR Ground Conditions – Marine deposits and alluvium to Balboughty Farm. Tay Crossing Bridge piles estimated at 40m to 55m in length; and – Glacial deposits with shallow bedrock beyond Balboughty Farm . 28 2020-03-03

  29. CROSS TAY LINK ROAD CONSTRAINTS 29 2020-03-03

  30. CROSS TAY LINK ROAD SPECIMEN DESIGN STATUS • Specimen Design concluded • Stage 1 Road Safety Audit • Final Stage 3 Cost Estimate • Stage 3 Report • (Draft) CAR licenses 30 2020-03-03

  31. CROSS TAY LINK ROAD STAKEHOLDERS AND LANDOWNERS • Consultations with key stakeholders, including: – Transport Scotland (and BEAR); – Network Rail; – HES, SNH and SF; – SEPA; and – Public Utilities. • PKC meetings with landowners/developers with: – Mansfield Estate; – AJ Stephen; – Ritchie; and – I&H Brown. • Early public consultation events / ongoing engagement 31 2020-03-03

  32. CROSS TAY LINK ROAD ENVIRONMENTAL IMPACT ASSESSMENT • Background • Key features • Air Quality • Active travel • Climate change • Biodiversity • Environmental Enhancement 32 2020-03-03

Recommend


More recommend