Perth Transport Future Project Phase 2 -Cross Tay Link Road CIHT Presentation 25 February 2020 – AK Bell Library ROSS FLETCHER SENIOR ENGINEER – ROADS INFRASTRUCTURE (PLANNING & DEVELOPMENT)
Introduction Welcome Housekeeping Ross Fletcher – Background to Perth Transport Futures Project & Cross Tay Link Road Denise Ritchie – Design of Cross Tay Link Road Emma Cooper – EIA & Planning Application for the Cross Tay Link Road Ross Fletcher – Procurement & Next Steps
Roads Infrastructure Team Small client team of 5 Set up in 2013/14 Situated within Planning & Development (Corporate & Democratic Services) Work closely with Transport Planning colleagues who progress proposed large roads schemes to end of DMRB Stage 2 Once there is a Business Case and Budget for a scheme it is handed to the Roads Infrastructure Team We manage the delivery phase which generally consists of site investigations, design through to DMRB Stage 3, land purchase, planning process and construction. We rely on support from colleagues in Legal, Planning, Estates, Finance and many others. Also rely on external support from consultants, DVS, Legal Advisors etc.
Perth Transport Futures Project Strategic Rationale Perth – major strategic hub Delivery of sustainable growth in the Tay Cities region Support the Northwest expansion of Perth as envisaged in the Local Development Plan (new LDP recently launched) Perth – AQMA. High priority given current climate crisis. Ambitious City Plan Integrated Series of Measures over Four Phases Phase 1 – A9/A85 scheme (complete) Phase 2 – CTLR Phase 3 – Bertha Park connection Phase 4 – City centre improvements (including greener travel – Perth, People, Place with SUSTRANS)
Phase 1 – A9/A85 Scheme Commenced on-site September 2016 Designer – CH2M Contractor – Balfour Beatty Complete May 2019 (roads opened January 2019 – 3 months early) Benefits / Features New grade separated junction on A9 Link road to Bertha Park development (including new school) New access to industrial estate Relieve pressure on Inveralmond Roundabout and Crieff Road corridor
Phase 1 – A9/A85 Scheme NEC3 Option A Contract (Scape Procure) £37.9m final cost (within 7% of initial price) Collaborative approach Significant Community Benefits Programme Social Value of £12.9 or £0.42 per £1 spent Recognised for collaborative approach Various Awards including: NEC Contract of the Year 2019 CECA Community Award 2019 National Social Value Award 2018 End of Project Review – Lessons learned fed into CTLR strategies
Phase 2 - Cross Tay Link Road AIMS OF THE CROSS TAY LINK ROAD Reduced congestion and improved air quality in the city centre and Bridgend Enable new, planned and committed developments – sustainable economic growth Enable city centre improvements including a move towards greener travel Connecting communities and improving access to Scone Palace and Perth Racecourse for events MAIN FEATURES OF THE CROSS TAY LINK ROAD New crossing of River Tay north of Perth New grade separated junction between Inveralmond Roundabout and Luncarty New link road from the A9 to the A94 (with roundabouts on Stormontfield Road, A93 and Highfield Track) Active travel route for full length of new road
Phase 2 - Cross Tay Link Road LOCAL DEVELOPMENT PLAN 2
Phase 2 - Cross Tay Link Road Reduction in traffic congestion – modelling by SYSTRA / Transport Planning – air quality improvement evident as shown
Phase 2 - Cross Tay Link Road SCHEME TIMELINE 2010 to 2016 Technical Assessment (DMRB – Stages 1 & 2 complete) June 2016 – Council commits Capital funding of £78 million December 2016 - Council approved the Preferred Route Early 2017 – Scheme passed to Roads Infrastructure Team for delivery Early 2017 to Present - liaison with land owners (ongoing_ July 2017 - SWECO appointed as designers (for specimen design) July 2017 to Present - consultation with statutory bodies / environmental groups (ongoing) Early 2018 to mid 2019 Site Investigations / Surveys
Phase 2 - Cross Tay Link Road SCHEME TIMELINE April 2018 to January 2019 Early Contractor Involvement (Balfour Beatty) Summer 2018 – First Public Consultations December 2018 – First draft of Specimen Design completed January 2019 – Scottish Government commits £40 million to project February to June 2019 – Alignment review between A93 and A94 (caused a six month delay) Summer 2019 – Final round of public consultations in advance of planning application
Phase 2 - Cross Tay Link Road SCHEME TIMELINE September 2019 – Design layout finalised for planning application and land purchase September 2019 – Council approval to proceed with Compulsory Purchase of land required Compulsory Purchase Order made on 30 October 2019 (with Scottish Ministers) Planning Application (including EIA) submitted in November 2019 (decision expected by April 2020)
CROSS TAY LINK ROAD CIHT PRESENTATION – SWECO 25 FEBRUARY 2020 DENISE RITCHIE EMMA COOPER 13 2020-03-03
CROSS TAY LINK ROAD SWECO – Stage 3 Input • Scheme Overview and Key Infrastructure • Site Investigations • Constraints • Current Specimen Design Status • Stakeholders and Landowners • Environmental Impact Assessment and Planning • Project Risks • Bulk Quantities 14 2020-03-03
CROSS TAY LINK ROAD SCHEME OVERVIEW 15 2020-03-03
CROSS TAY LINK ROAD SCHEME OVERVIEW (PART 1 of 4) 16 2020-03-03
CROSS TAY LINK ROAD SCHEME OVERVIEW PART 2 of 4 GENDIATUR, QUE REIUNT EXPLABO. UT ASINCTIIS 17 DE VOLLACCAB ISUNT ET EOS QUATIANDANDI DELLECU LLUPTIIST 2020-03-03
CROSS TAY LINK ROAD SCHEME OVERVIEW PART 3 of 4 18 2020-03-03
CROSS TAY LINK ROAD SCHEME OVERVIEW PART 4 of 4 GENDIATUR, QUE REIUNT EXPLABO. UT ASINCTIIS 19 DE VOLLACCAB ISUNT ET EOS QUATIANDANDI DELLECU LLUPTIIST 2020-03-03
CROSS TAY LINK ROAD KEY INFRASTRUCTURE – A9 JUNCTION • Agreed design • Loop arrangement is compact • Future proofed 20 2020-03-03
CROSS TAY LINK ROAD KEY INFRASTRUCTURE – A9 OVERBRIDGE • Structural form • Aesthetics • Piled foundations 21 2020-03-03
CROSS TAY LINK ROAD KEY INFRASTRUCTURE – RIVER TAY CROSSING • Structural form • Clearances and temporary works • Fishing rights, and • Access options to the western pier 22 2020-03-03
CROSS TAY LINK ROAD KEY INFRASTRUCTURE – CTLR ROAD CROSS SECTION • single carriageway • 85kph design speed • Segregated cycleway, and • Grass verges and separation strip. 23 2020-03-03
CROSS TAY LINK ROAD KEY INFRASTRUCTURE – JUNCTIONS Stormontfield Road Roundabout A94 Roundabout A93 Roundabout 24 2020-03-03
CROSS TAY LINK ROAD KEY INFRASTRUCTURE – HIGHFIELD GREEN BRIDGE • Buried precast concrete arch • Aesthetics • Connects NMU infrastructure, and • Provides ecological and landscape connectivity. 25 2020-03-03
CROSS TAY LINK ROAD KEY INFRASTRUCTURE – LANDSCAPE • High quality landscape • Wetland area, and • Park and cycle facility 26 2020-03-03
CROSS TAY LINK ROAD SITE INVESTIGATIONS The following were completed early in Stage 3: • Ecological surveys • Tree surveys; • Topographical, bathymetric and drainage surveys; • NMU CCTV surveys; • Ground investigation in 2018; and • Intrusive archaeological investigations (trial trenching and geophysical surveys) in early 2019 27 2020-03-03
CROSS TAY LINK ROAD SITE INVESTIGATIONS • A9 Ground Conditions – A9 Mainline south - raised tidal flat deposits and alluvium; – Broxy Wood is a drumlin of glacial till; – Grade separated junction - raised marine deposits; and – North of Broxy Kennels - glacial deposits. • CTLR Ground Conditions – Marine deposits and alluvium to Balboughty Farm. Tay Crossing Bridge piles estimated at 40m to 55m in length; and – Glacial deposits with shallow bedrock beyond Balboughty Farm . 28 2020-03-03
CROSS TAY LINK ROAD CONSTRAINTS 29 2020-03-03
CROSS TAY LINK ROAD SPECIMEN DESIGN STATUS • Specimen Design concluded • Stage 1 Road Safety Audit • Final Stage 3 Cost Estimate • Stage 3 Report • (Draft) CAR licenses 30 2020-03-03
CROSS TAY LINK ROAD STAKEHOLDERS AND LANDOWNERS • Consultations with key stakeholders, including: – Transport Scotland (and BEAR); – Network Rail; – HES, SNH and SF; – SEPA; and – Public Utilities. • PKC meetings with landowners/developers with: – Mansfield Estate; – AJ Stephen; – Ritchie; and – I&H Brown. • Early public consultation events / ongoing engagement 31 2020-03-03
CROSS TAY LINK ROAD ENVIRONMENTAL IMPACT ASSESSMENT • Background • Key features • Air Quality • Active travel • Climate change • Biodiversity • Environmental Enhancement 32 2020-03-03
Recommend
More recommend