LNG Bunkering Course: Section 3.12 – Transfer 2015 Process LNG Bunkering Course Section 3.12 – Transfer Process 1 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Overview of Section 3.12: Transfer Process • Two Rules that Need to be Always Followed • Importance of Communication • Following the Process Unless otherwise noted, all of the information in this section is based on the above publications, as well as the professional experiences of Capt. John Egan. 2 2015 LNG Bunkering Course: Section 3.12 – Transfer Process References • An Introduction to LNG Bunkering, Nigel Draffin, Petrospot Limited, England, 2013 • LNG Operations Manual, Washington State Ferries, Report N o : PP061307-3, Rev. 3, Document N o : 167NWYK-12, Dated: 2014-10-22 3 2015 LNG Bunkering Course: Section 3.12 – Transfer Process 1
LNG Bunkering Course: Section 3.12 – Transfer 2015 Process References • Gas as a Marine Fuel, Safety Guidelines , The Society for Gas as a Marine Fuel (SGMF) • Recommended Practice – Development and Operation of Liquefied Natural Gas Bunkering Facilities , DNV•GL-RP- 0006:2014-01 4 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Transfer Process • Regardless of transfer method, there are common procedures that should be followed AND … Two Rules to Follow 5 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Transfer Process • Connection RULE 1 Never let fuel gas (NG) and air be present at the same time in the same space RULE 2 If you fail to follow RULE 1 then make sure there is no uncontrolled source of ignition Source: An Introduction to LNG Bunkering , Nigel Draffin, Petrospot Ltd, England, 2013, Page 4 6 2015 LNG Bunkering Course: Section 3.12 – Transfer Process 2
LNG Bunkering Course: Section 3.12 – Transfer 2015 Process Transfer Process • Uncontrolled Source of Ignition • Uncontrolled sources of ignition are those not considered in the design of the facility and may not be under the direct controlled of the operator. • Examples: Smoking, static build up on clothing and subsequent discharge, dropped objects, and the use of non- approved portable electrical equipment. Source: An Introduction to LNG Bunkering , Nigel Draffin, Petrospot Ltd, England, 2013, Page 4 7 2015 LNG Bunkering Course: Section 3.12 – Transfer Process LNG Bunker Transfer Communications Each operator must have: UHF walkie talkie. A direct phone line. The ability to view level, temperature and pressure of their tanks. 8 2015 LNG Bunkering Course: Section 3.12 – Transfer Process LNG Bunker Transfer Communications • LNG Bunker Transfer Communications Each operator must have: The ability to monitor temperature and pressure of transfer process The ability to monitor alarms The ability to activate an ESD 9 2015 LNG Bunkering Course: Section 3.12 – Transfer Process 3
LNG Bunkering Course: Section 3.12 – Transfer 2015 Process Transfer Process • Standard transfer method via flexible cryogenic hose or hard arm between supply source and receiving ship. • Supply sources: Shore tank Barge Bunker ship Road tanker Cassette tank system 10 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Transfer Process • Regardless of transfer modality, procedures common to all: Safe zone establishment Connection Purging Cooldown Test of ESD system 11 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Transfer Process • Regardless of transfer modality, procedures common to all: LNG bunker transfer Gas freeing De-icing Disconnection Custody transfer 12 2015 LNG Bunkering Course: Section 3.12 – Transfer Process 4
LNG Bunkering Course: Section 3.12 – Transfer 2015 Process Safe Zone Establishment Set up appropriate safe zone to keep all personnel not directly involved in bunker operation away from: From bunker manifold area. From any potential exposure to vapor or liquid escape. 13 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Connection Connect hoses / arms / cryogenic hose to bunker manifold. Inspect flanges and clean flanges / mating surfaces. Gasket / O-ring installed (new each transfer). 14 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Connection Insulated flanges per SIGTTO, ISGOTT, and the ISO guideline. Leak test hose/arm connections: Liquid line connection tested at approximately 5 bar. Vapor line connection pressure tested 1–2 bar. 15 2015 LNG Bunkering Course: Section 3.12 – Transfer Process 5
LNG Bunkering Course: Section 3.12 – Transfer 2015 Process Connection Soap test all connections: Soap will bubble if there is a leak. 16 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Transfer Process • Purging: Displace O 2 from hoses/arms with N 2: Supplied by ship/terminal by hose connection. Purging end points: O 2 = <1% Dewpoint < 40ºC 17 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Transfer Process • Cool-down: Small quantity of LNG is admitted to the transfer line, vaporizing to methane gas. Cold methane gas cools down the line until it is displaced by LNG. 18 2015 LNG Bunkering Course: Section 3.12 – Transfer Process 6
LNG Bunkering Course: Section 3.12 – Transfer 2015 Process Transfer Process • Test of ESD system: Ship to shore: System tripped from ship control. All ESD valves close. System reset. 19 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Transfer Process • Test of ESD system: Shore to ship: System tripped from shore control. All ESD valves close. System reset. 20 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Transfer Process • LNG bunker transfer: Start pumps and ramp up to maximum agreed upon transfer rate: Monitor temps / pressure / tank level. Ramping down (reduce transfer rate). 21 2015 LNG Bunkering Course: Section 3.12 – Transfer Process 7
LNG Bunkering Course: Section 3.12 – Transfer 2015 Process Transfer Process • LNG bunker transfer: Topping off: Further reduced transfer rate. Complete transfer / stop pumps-close valves. 22 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Transfer Process • Gas Freeing: • LNG remaining in hoses/arms must be displaced by: Allowing LNG in the line to vaporize the remaining LNG back into storage on the ship and/or suppliers storage tank, or Pressurizing line with N 2 displacing LNG to ship and/or suppliers storage tanks. 23 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Transfer Process • Gas Freeing: Gas free end point <1% CH 4 24 2015 LNG Bunkering Course: Section 3.12 – Transfer Process 8
LNG Bunkering Course: Section 3.12 – Transfer 2015 Process Transfer Process • De-icing lines/hoses: Water spray on hoses/arms to de-ice. 25 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Transfer Process • Disconnection: Once gas free and de-iced hoses/arms are disconnected and returned to stowed location/position. 26 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Transfer Process • Custody transfer: The quantity of LNG bunkers transferred is determined by a mutually agreed upon method between the bunker supplier and receiver. Two most common methods are: Volume determined by calculations from vessel tank level system, or Volume measured by flow meter 27 2015 LNG Bunkering Course: Section 3.12 – Transfer Process 9
LNG Bunkering Course: Section 3.12 – Transfer 2015 Process Transfer Process • Custody transfer Regardless of method used, volume transferred to be agreed upon by both parties Independent Surveyor may be used to certify volume transferred Appropriate documentation signed by both parties After LNG Transfer Checklist 28 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Transfer Process • At every step of the LNG bunker transfer REMEMBER : 29 2015 LNG Bunkering Course: Section 3.12 – Transfer Process Summary and Conclusions • The transfer process is based on two very important rules: Rule #1: Never let air and gas in the same space and time. Rule #2: Make sure that there is no source of ignition. • All require very specific steps. • Above all: Safety, Safety, and Safety 30 2015 LNG Bunkering Course: Section 3.12 – Transfer Process 10
Recommend
More recommend