HIGH VOLTAGE TOWER RELOCATION, KENSINGTON 10 APRIL 2018
AGENDA 1. Community issues and concerns 2. Overview of works 3. Communication about these works 4. Open discussion
METRO TUNNEL PROJECT
FUTURE RAIL PATRONAGE • Population growth • Inner city jobs • Road congestion • Parking costs • Environmental impacts
RAIL NETWORK PINCH POINTS CITY LOOP APPROACHING CAPACITY NORTH MELBOURNE TRAINS QUEUE FOR CITY LOOP RICHMOND TRAINS QUEUE PINCH POINTS ARE FOR CITY LOOP AFFECTING RAIL NETWORK OPERABILITY
CAPACITY BENEFITS
OVERVIEW OF HV TOWER WORKS
BACKGROUND ON RELOCATION WORKS
EXISTING HV TOWER ALIGNMENT
STAGE 2- TEMPORARY ALIGNMENT
STAGE 3- PERMANENT ALIGNMENT
ALTERNATIVE LOCATIONS EXPLORED B
HV TOWER HEIGHTS – TOWER 33 • Temporary tower = 56.2m • Permanent tower = 52m • Existing tower = 43.3m
COMMUNITY ENGAGEMENT
COMMUNITY FEEDBACK • Engagement and consultation underway in Kensington since early 2015, including the Environment Effects Statement planning process • Feedback from Kensington residents has informed planning and design for the western tunnel entrance: o Significant reduction in private property acquisition o Removal of rail bridge over Kensington Road o Updated alignment for High Voltage transmission tower location o Significant reduction in impacts from service relocations
INFORMATION SESSIONS • September 2015: Community Information Session, Kensington Recreation Centre • October 2015: Community Information Session, Kensington Recreation Centre • June 2016 : Two EES Information Sessions, Kensington Recreation Centre • April 2017: Early Works Western Portal Community Information Session, Bill Vanina Pavilion • September 2017 : Pop-up Information Session, Tankard Reserve (Wakefield Street) • October 2017: Two Pop-up Information Sessions, JJ Holland Park • November 2017: Presentation to the Kensington Association • December 2017: Pop-up Information Session, Kensington Recreation Centre
INFORMATION CHANNELS metrotunnel.vic.gov.au - works overview information & latest notifications
INFORMATION CHANNELS Fact sheets (April 2017)
INFORMATION CHANNELS Letter and map (August 2017)
INFORMATION CHANNELS Letter and map (August 2017)
INFORMATION CHANNELS Works notifications
INFORMATION CHANNELS Works notifications
KEEPING THE COMMUNITY INFORMED • Dedicated MMRA and contractor engagement staff • Community representation on Kensington and Arden Community Reference Group • One-on-one meetings with residents and businesses • Regular works notifications • Information sessions • 24/7 Metro Tunnel Project Information Line 1800 105 105
QUESTIONS