heritage hunt pum p station heritage hunt pum p station
play

Heritage Hunt Pum p Station Heritage Hunt Pum p Station Replacem - PowerPoint PPT Presentation

Heritage Hunt Pum p Station Heritage Hunt Pum p Station Replacem ent Project Replacem ent Project 60 % Design Update 60 % Design Update Community Meeting #3 Community Meeting #3 March 7, 2017 March 7, 2017 SA Project Manager: George W.


  1. Heritage Hunt Pum p Station Heritage Hunt Pum p Station Replacem ent Project Replacem ent Project 60 % Design Update 60 % Design Update Community Meeting #3 Community Meeting #3 March 7, 2017 March 7, 2017 SA Project Manager: George W. DiCarlo, P.E., CCM Program Mgmt. Consultant: Rummel, Klepper & Kahl, Inc. Design Engineer: Dewberry Consultants LLC

  2. Agenda Agenda Existing Facility History & Purpose of Project Existing Facility History & Purpose of Project Review Project Status Review Project Status Current Pump Station Design Current Pump Station Design Siting Siting Architecture Architecture Noise & Odor Noise & Odor Landscaping Landscaping Access Access Force Main Project Status Force Main Project Status Remaining Schedule Remaining Schedule Q&A Q&A

  3. Existing Facility History Existing Facility History History of Regional Sewage Pump Station and History of Regional Sewage Pump Station and Force Mains Force Mains • The existing Interim Regional Sewage Pump Station • The existing Interim Regional Sewage Pump Station was constructed in 2001 by US Home Corporation was constructed in 2001 by US Home Corporation before development could progress in Heritage Hunt before development could progress in Heritage Hunt • The interim regional facility was always planned to be • The interim regional facility was always planned to be expanded to meet sewershed demands of region. expanded to meet sewershed demands of region. • The parcel was proffered & deeded by US Home Corp. • The parcel was proffered & deeded by US Home Corp. • Two (2) pressure force mains and portions of a third • Two (2) pressure force mains and portions of a third were constructed in 1998. were constructed in 1998. • Existing sewer sheds serve approx. 8,000 homes and • Existing sewer sheds serve approx. 8,000 homes and expect an increase of 600 to 1,400 residences. expect an increase of 600 to 1,400 residences.

  4. Fieldstone Way Fieldstone Way Heritage Hunt Dr. Heritage Hunt Dr. Service Authority Pump Station Site Alderwood Way ay Heritage Hunt Clubhouse OVERALL MAP

  5. Existing Station Capacity is 3.6 Million Gallons per Day (MGD) PUMP STATION LOCATION

  6. Purpose of the Project Purpose of the Project Purpose Of Project Purpose Of Project • Replace existing pump station facility with a larger • Replace existing pump station facility with a larger station equipped to handle current and future flows. station equipped to handle current and future flows. • Avoid potential sewer overflows. • Avoid potential sewer overflows. • Install the remaining sections of the third force main. • Install the remaining sections of the third force main. Benefits Of Project Benefits Of Project • Increase system capacity. • Increase system capacity. • Maintain service reliability. • Maintain service reliability. • Reduce noise and odors. • Reduce noise and odors.

  7. 60 % Design Update 60 % Design Update Progress On Permitting Progress On Permitting • County’s Public Facilities Review is complete; approval • County’s Public Facilities Review is complete; approval on February 1, 2017. on February 1, 2017. • The Service Authority will follow key commitments, • The Service Authority will follow key commitments, which are: which are: 1) Pump station building to have a residential appearance. 1) Pump station building to have a residential appearance. 2) Use best available technology – odor control. 2) Use best available technology – odor control. 3) Use best available technology – sound control. 3) Use best available technology – sound control. 4) Plant Riparian Forest area over old station bldg. site. 4) Plant Riparian Forest area over old station bldg. site. 5) Supplement landscaping in buffer adjacent to station. 5) Supplement landscaping in buffer adjacent to station. 6) Present plan to address noise/odors at existing station. 6) Present plan to address noise/odors at existing station. 7) Restore damaged property, due to our construction 7) Restore damaged property, due to our construction activities, to existing or better condition. activities, to existing or better condition.

  8. 60 % Design Update 60 % Design Update Progress On Regional Pump Station Design Progress On Regional Pump Station Design • Peak capacity designed for up to 8.0 MGD. • Peak capacity designed for up to 8.0 MGD. • New odor control system is included. • New odor control system is included. • Odor control system blowers are enclosed. • Odor control system blowers are enclosed. • Backup power generator is located inside the building. • Backup power generator is located inside the building. • Brick screening wall to hide the odor control equipment • Brick screening wall to hide the odor control equipment and to provide additional sound attenuation is included. and to provide additional sound attenuation is included. • To the extent possible, fuel and other deliveries are • To the extent possible, fuel and other deliveries are scheduled to be offloaded at the back of the station. scheduled to be offloaded at the back of the station. • Building architecture does match the Community. • Building architecture does match the Community. • Landscaping plans (draft) have been prepared. • Landscaping plans (draft) have been prepared.

  9. Heritage Hunt Sewage Pumping Station Site Existing Site with Aerial Image

  10. Heritage Hunt Sewage Pumping Station Site Existing Site with Aerial Image and 100-Yr Flood Hazard Overlay

  11. Heritage Hunt Sewage Pumping Station Site Existing Site with Aerial Image and Tree Cover Overlay

  12. Heritage Hunt Sewage Pumping Station Site Existing Site with Aerial Image and Contour Lines

  13. Heritage Hunt Sewage Pumping Station Site Existing Utility Corridors Into Station Site

  14. Heritage Hunt Sewage Pumping Station Site

  15. Station Site Plan Station Site Plan

  16. Building Architecture Building Architecture

  17. Rendering – Alderwood Way Rendering – Alderwood Way

  18. Noise & Odor Reduction Noise & Odor Reduction Features Features • Odor Control will have sufficient • Odor Control will have sufficient capacity to handle the entire capacity to handle the entire facility. facility. • Behind screening Wall. • Behind screening Wall. • Blowers will be enclosed. • Blowers will be enclosed. • Generator and channel grinder • Generator and channel grinder motors are inside the building. motors are inside the building. • Generator room will have noise • Generator room will have noise control features. control features.

  19. Proposed Lanscaping Proposed Lanscaping

  20. Proposed Tem porary Easem ent Proposed Tem porary Easem ent for Efficient Access to Site for Efficient Access to Site

  21. Proposed Tem porary Easem ent Proposed Tem porary Easem ent for Efficient Access to Site for Efficient Access to Site

  22. Proposed Tem porary Easem ent Proposed Tem porary Easem ent for Efficient Access to Site for Efficient Access to Site

  23. Fieldstone Way Fieldstone Way Heritage Hunt Dr. Heritage Hunt Dr. Service Authority Pump Station Site Alderwood Way ay Heritage Hunt Clubhouse OVERALL MAP

  24. 24-inch Force Main Corridor

  25. Key Issues - Force Mains Key Issues - Force Mains • The Service Authority’s commitment to restore • The Service Authority’s commitment to restore damaged property, caused by construction activities, to damaged property, caused by construction activities, to original or better condition is firm and unchanged. original or better condition is firm and unchanged. • The SA plans to minimize the daily work zone areas to • The SA plans to minimize the daily work zone areas to reduce travel times and disruption to the Community. reduce travel times and disruption to the Community. • Minimizing the time the Golf Course may be impacted. • Minimizing the time the Golf Course may be impacted.

  26. Exam ple: Project Restoration Exam ple: Project Restoration

  27. Exam ple: Project Restoration Exam ple: Project Restoration

  28. Exam ple: Project Restoration Exam ple: Project Restoration

  29. Exam ple: Project Restoration Exam ple: Project Restoration

  30. Anticipated Project Duration Anticipated Project Duration Design and Permitting Timeframe: Design and Permitting Timeframe: • January 2015 – April 2018 • January 2015 – April 2018 Future Steps - Easement Negotiations With The Future Steps - Easement Negotiations With The HOA. HOA. • On-going • On-going Public Facility Review Process Public Facility Review Process • Approved on February 1, 2017 • Approved on February 1, 2017 Anticipated Sewage Pump Station and Force Anticipated Sewage Pump Station and Force Main Construction Duration: Main Construction Duration: • 24 Months • 24 Months

Recommend


More recommend