den brook wind farm
play

Den Brook Wind Farm Community Liaison Group May 2016 Den Brook - PowerPoint PPT Presentation

Den Brook Wind Farm Community Liaison Group May 2016 Den Brook Wind Farm RES Construction Phase Team Den Brook Wind Farm Headline Project Details Consented 2009 Construction commenced July 2015 6.5km of site road 33kV


  1. Den Brook Wind Farm Community Liaison Group May 2016

  2. Den Brook Wind Farm RES Construction Phase Team

  3. Den Brook Wind Farm Headline Project Details • Consented 2009 • Construction commenced July 2015 • 6.5km of site road • 33kV grid connection at North Tawton • 9 V90 Vestas 2MW turbines with 75m hub height • 18MW installed capacity

  4. Den Brook Wind Farm – Progress Engineering Element S tatus Civil Infrastructure detailed design Complete Foundation detailed design Complete Grid S ubstation detailed design Complete WF substation detailed design Complete Procurement Civil works Complete S ubstation package Complete Turbines Complete

  5. Den Brook Wind Farm – Progress Construction Progress Works Completed: • Off-site highway works complete • S ite roads/ signage and all crane hardstandings complete • All 9 turbine foundations complete and backfilled • HV Cable network for the wind farm between the substation and all turbines is complete • Turbine delivery Trial Run complete • Overhead protection for railway tunnel installed Works Ongoing: • Fencing and gate installation ongoing • S ubstation construction ongoing – foundations/ drainage constructed, electrical phase to follow • Ecological works for the environmental mitigation plan currently being discussed • Planning for the turbine delivery/ installation and commissioning phase ongoing

  6. Den Brook Wind Farm – Civil Infrastructure Layout

  7. Den Brook Wind Farm – Civil Infrastructure Track to Turbine 5 Water Crossing Track from site entrance Blade fingers constructed

  8. Den Brook Wind Farm – Civil Infrastructure Railway tunnel protection works HV cable network installation

  9. Den Brook Wind Farm – Turbine Foundations

  10. Den Brook Wind Farm – Turbine Foundations T 6 foundation/hardstanding area reinstated and finished

  11. Den Brook Wind Farm – Turbine Foundations Truck pave material installed and topsoiled for visual purposes

  12. Den Brook Wind Farm – Turbine Foundations View of T6

  13. Den Brook Wind Farm – S ubstation construction

  14. Den Brook Wind Farm – Progress Grid Connection Works (carried out by WPD) • WPD’s cabling works on the wind farm site approximately 90% complete • Grid contractor now working east from site towards A3124 • Directional drilling is complete under the Den Brook as well as the A3124 and A3072 to remove any disturbance to local traffic • WPD expected finish date is early July

  15. Den Brook Wind Farm - Programme Commencement at site July 2015 Civil Works July 2015 – April 2016 Substation Works January 2016 – August 2016 Grid Available August 2016 Turbine Works August 2016 – November 2016 Project Completion - November 2016

  16. Den Brook Wind Farm – Wind Turbines Each turbine consists of • 3 tower sections • 3 blades • Nacelle • Hub

  17. Den Brook Wind Farm – Upcoming Turbine component deliveries – currently planned for late June 2016 Turbine erection and commissioning – July to November 2016 Ecology – hedgerow planting and bird boxes – August to October 2016 Local Electricity Discount Scheme • Expression of interest at 28 % of eligible properties since launch in May 2014 • Direct mailer scheduled for late May/early June with instructions on how to join via website/LEDs team • Registration ends October 2016 • First payment end of 2016/early 2017 Community Benefit Fund • Available once the wind farm is operational • Administered locally

  18. Any Questions?

Recommend


More recommend