SuDs Management at Glenconway Windfarm SuDS
Introduction to Gael Force Renewables SuDs
• Gael Force Renewables Ltd was formed in 2011 by McLaughlin & Harvey Ltd and William & Henry Alexander (Civil Engineering) Ltd to target onshore Wind Farm opportunities in GB & ROI. SuDs
Gael Force Renewables – What We Do : • 150 years of Civil Engineering Experience • Gael Force offer full Design and Build Services • Early client and designer involvement so that innovative, safe, buildable solutions are developed. • At Gael Force we implement lessons learnt to ensure our teams constantly progress, develop and refine skills, methodologies and work sequences • Full time on site Environmental Professionals SuDs
Project - Balmurrie Fell Wind Farm, Stranraer, South West Scotland. (7 x 1.3 MW Siemens WTG) SuDs
Project – Glenconway Windfarm, Limavady, Northern Ireland (20 x 2.3MW WTG) SuDs
Design to Construction SuDS
Settlement Ponds SuDS
Silt Fencing SuDS
Clean water cut off drains SuDS
Swales & check dams SuDS
Breakouts SuDS
Settlement Areas SuDS
Monitoring Effectiveness • Water Quality testing (internal & external) • External inspections by Designers • Internal weekly inspections by Environmental Representative • SEARS (Safety Environmental Awareness Reporting Scheme). Positive and Negative issues raised by everyone on site. SuDS
SuDS
Water Quality Testing • External water quality testing was carried out every two weeks at 5 locations for Phase 1 and 8 locations for Phase 1 & 2 • Testing covered 21 chemical parameters and biological (macro invertebrate) monitoring • Internal samples took place daily for phase 1 and weekly for phase 2. Parameters included turbidity, dissolved oxygen, pH, temp & EC. SuDS
Environmental Awareness • Water Quality results are displayed on site • Correlation between turbidity and rainfall is also presented on graphs. SuDS
Toolbox Talks • Every Tuesday morning • Covers key issues such as waste, energy, water pollution • All site staff shared the responsibility SuDS
Environmental Awareness SuDS
Environmental Coaching Environmental Sessions to date:- SuDS (McCloys) Peat Stability / Peat Slides (BLP) Archaeology (Gahan & Long) Flora and Fauna (Blackstaff) SuDS
SuDS
Conclusion • SuDS design must account for inclement weather conditions • SuDS design must be site specific • SuDS features must be installed prior to works starting • Very beneficial to have an on site environmental representative • Water Quality monitoring is important during construction – even visual inspection of water courses • Maintenance of SuDs Features is critical SuDS
Construction-Phase Temporary SuDS: A75 Case Study Richard Collins BSc MSc AIEMA
Construction Context 3.67km carriageway realignment and upgrade: • include earthworks, drainage and culverts, utility works, surfacing & underpass construction Existing drainage mitigation inadequate • Filter drains & 4 balancing ponds with reed beds • Key Environmental Aim ‘Protecting the Pow Water tributaries during construction’
Challenges & Uncertainties Geology & soils • Earthworks intensive EIA stated ‘potentially increased sedimentation’ True nature of soils
Fine Clays
Spatial constraints • Limited opportunity for temporary SuDS locations
Temporal Constraints • Not scheduled in programme of works Resources to complete with immediate effect Costs
Usual Suspects Exposed soils: ensuring capping/seeding is completed ASAP Stockpiles: limiting, stabilising Washing & washout facilities Haul roads: wheel wash operative (spatial constraints) Dewatering: sumps, releasing at suitable times Inclement weather: be prepared
Water Management Strategy Liaise with local SEPA representative Alum sulphate required: minimal dosing policy Tiered, impermeable treatment zones Maintenance plan: Daily checks pH (6-8) & turbidity (<10ntu) testing Controlled release
Tangible Results
Permanent Pond Installation • Isolated pond • Limited opportunity for treatment • Use of existing vegetation • Lined sediment forebay • Aquatic bench in permanent pool; ecology, amenity & safety
Native Species Planting Pond Edge Mix Yellow Flag Iris Water Avens Meadowsweet Benefits of bio-retention and enhanced biodiversity
Learning Points Detailed pre-construction review of EIA Robust planning, management & maintenance required Micro-managed retention & release Maximise use of sub-catchments in design
Thank you
Recommend
More recommend