1 Shippers meeting on 16 December 2014 2 Shippers meeting on 16 December 2014 3 Shippers meeting on 16 December 2014 GRTgaz and TIGF create the TRADING REGION SOUTH . The TRADING REGION SOUTH includes The TRS joint market place;


  1. 1 Shippers meeting on 16 December 2014

  2. 2 Shippers meeting on 16 December 2014

  3. 3 Shippers meeting on 16 December 2014

  4.  GRTgaz and TIGF create the TRADING REGION SOUTH .  The TRADING REGION SOUTH includes ◦ The TRS joint market place; ◦ all existing interconnection points for each TIGF and GRTgaz South balancing zone; ◦ two consumer zones, TIGF and GRTgaz South, grouping all the end-user delivery points in the TIGF or GRTgaz South balancing zones. 4 Shippers meeting on 16 December 2014

  5. 5 Shippers meeting on 16 December 2014

  6.  Introduction 10h – 10h10  Access procedure as of 1st of April 10h10-10h30 • Questions session  Marketed points management 10h40-11h00 • Questions session  Balancing management 11h10-11h30 • Questions session  Electronic data transfer / publications 11h40-12h00 • Questions session  Conclusion 12h20-12h30  Cocktail 12h30-14h30 Shippers meeting on 16 December 2014 6

  7. 7 Shippers meeting on 16 December 2014

  8.  TIGF and GRTgaz have been focused on the objective to offer a contractual solution that would not add complexity to the current contractual setting  They are currently working on an automatic and undifferentiated access switch over to the TRS exchange point through one or the other TSO’s transport contract 8

  9.  Shippers have subscribed with TIGF and/or GRTgaz a contractual section dedicated to the access to the PEG TIGF with TIGF (section 3.1 or 3.2) and/or to the PEG Sud with GRTgaz (section D1 or D2) • Refund ( pro rata temporis ) of the fixed access fees (6,000 Euros/year) at the PEG TIGF  Some of the shippers have booked capacities at the commercial interconnection between both networks : PITT GRTgaz Sud (Appendix C.1) or PIR Midi (Appendix B.1) • No new commercialization of capacity products starting on 1 st of April 2015 or after (through FCFS and through OSP) • Capacity products starting on 1 st of April 2015 or after, already allocated through Open Season, become obsolete 9

  10.  Sections dedicated to the access to the TRS exchange point through TIGF (section 3.1 or 3.2) and/or through GRTgaz (section D1 or D2) remain • Those sections are being updated to concern the TRS exchange point  Appendices and references to PITT GRTgaz Sud or PIR Midi are suppressed • Appendix C.1 with TIGF et Appendix B.1 with GRTgaz  Update of the contractual provisions to the other operational changes • Segmentation, balancing • Capacity reductions, “super - point” management 10

  11.  Shippers with current access to the PEG Sud only • Automatic switch over to the TRS exchange point • Billing operated by GRTgaz  Shippers with current access to both the PEG Sud and the PEG TIGF • Automatic switch over to the TRS exchange point • TIGF’s shipper code suppressed • Billing operated by GRTgaz  Shippers with current access to the PEG TIGF only • Automatic switch over to the TRS exchange point • TIGF’s contract code shipper replaced by GRTgaz’s contract code • Billing operated by TIGF 11

  12.  Renewal of the guarantee • Optimization of the provisions from 1st of April 2015  TRS access fees (fixed and variables) • CRE’s tariff deliberation  Schedule of the contractual updates • Proposal to be submitted to the CRE in January • Expected publication on mid-February 12

  13. 13 Shippers meeting on 16 December 2014

  14. 14 Shippers meeting on 16 December 2014

  15.  Changing of marketed points • PIR and PITT • PEG and TRS  Transitory period management • The capacities • The nominations • The allocations and invoicing 15

  16.  The 1 st of April 2015, disappearance of the interface point between GRTgaz and TIGF • PIR Midi (on GRTgaz side) • PITT GRTgaz Sud (on TIGF side)  The 31 th of March 2015, closing of the existing booked capacities between GRTgaz and TIGF.  The restrictions of capacity between GRTgaz and TIGF are transfered on the other points of the Trading Region South. 16

  17.  Disappearance of the 2 PEG • PEG Sud (GRTgaz side) • PEG TIGF (TIGF side)  Creation of the TRS • Continue to nominate on TIGF side on the operational points PITT, PITS and the delivery zone (PS) • Continue to nominate on GRTgaz side on the operational points PITT, PITS, PIR, PIRR, PITM, PIP and the delivery pool (PL)  Nominations on the TRS exchange point on the GRTgaz side with the code EG001S. 17

  18.  The invoicing method remains unchanged for each TSO except for the TRS.  From the invoicing of June : sending of a document detailing the amounts exchanged on the TRS to each shipper.  GRTgaz  The shippers who have a transmission contract with GRTgaz will be charged by GRTgaz  TIGF  The shippers who have a transmission contract only with TIGF will be charged by TIGF 18

  19. From 1st of April 2015, no marketing process on PITT GRTgaz Sud et PIR Midi.  TIGF on TETRA : • The 20/02/15 : last day of monthly capacity sales for March 2015 on PITT GRTgaz Sud • The 30/03/15 before 02:30 p.m : last day of daily capacity sales for the 31/03/15 on PITT GRTgaz Sud  GRTgaz on T@ : • The 20/02/15 : last day of monthly capacity sales for March 2015 on PIR Midi • The 30/03/15 : last day of daily capacity sales for the 31/03/15 on PIR Midi  At 01:00 p.m : for the FCFS method  At 03:00 p.m : for the auctions 19

  20.  TIGF and GRTgaz  Forecasts and nominations having a gasday after the 31/03/15 on PITT GRTgaz/PIR Midi and PEG TIGF/PEG Sud will be refused (warning : rejection of the entire transmission request batch) Be careful for those who make nominations in M-1  GRTgaz  Forecast on PEG Sud will be automatically migrated on the TRS  Nominations on the TRS will be accepted only from the 30/03/15 for gasdays after the 31/03/15  Nominations on the TRS will be done with a GRTgaz shipper c ode :  For those who already have a GRTgaz shipper code , the code remains the same  For those who do not have, a GRTgaz shipper code will be assigned 20

  21.  TIGF and GRTgaz  Provisional, Definitive and Rectified data published during April and after, regarding the allocations of March or before, will be based on the current rules.  The invoicing terms for period prior to the 1 st of April remain unchanged. 21

  22. 22 Shippers meeting on 16 December 2014

  23. 23 Shippers meeting on 16 December 2014

  24.  Forecasted imbalance  Total imbalance  Contractual imbalance • Categories of shipper • Individual distribution key • Examples  Imbalance invoicing  Summary 24

  25.  In D-1 and D, the forecasted imbalance is calculated across the entire TRADING REGION SOUTH, for each shipper and for the gas day D.  The forecasted imbalance is calculated using the quantities confirmed by operators, for the gas day D and for the shipper, on the following points PITS, PITM,PITP, PIR, PIRR, PITT, PIP, PS, PL and TRS of the TRADING REGION SOUTH.  The forecasted imbalance will be included in programs which operators send to the shippers . 25

  26. GRTGAZ Nord GRTGAZ Sud Zones TIGF ENAGAS

  27. GRTGAZ Nord Example : for a given shipper GRTGAZ Sud - 1 - 5 Exit nomination by TIGF & GRTgaz - 1 -5 -2 -3 -1 = - 12 PL PITS TIGF -3 -1 -2 PS PITS +200 ENAGAS

  28. + 4 GRTGAZ Nord Example : for a given shipper GRTGAZ Sud - 1 - 5 Exit nomination by TIGF & GRTgaz - 1 -5 -2 -3 -1 = - 12 PL PITS +1 TIGF Entry Nomination by TIGF & GRTgaz -3 -1 +6 +4 +6 +1 = +11 -2 PS PITS +200 ENAGAS

  29. + 4 GRTGAZ Nord Example : for a given shipper GRTGAZ Sud - 1 - 5 Exit nomination by TIGF & GRTgaz - 1 -5 -2 -3 -1 = - 12 PL PITS +1 TIGF Entry Nomination by TIGF & GRTgaz -3 -1 +6 +4 +6 +1 = +11 -2 PS PITS +200 ENAGAS Programs sent by GRTgaz et TIGF ∆ = -1

  30.  In D+1 total imbalance is calculated across the entire TRADING REGION SOUTH, for each shipper and for the gas day D  The total imbalance by shipper is calculated based on the quantities allocated by operators for the gas day D and the shipper, on the following points PITS, PITTM, PITP, PIR, PIRR, PITT, NS link, PS, PL and TRS of the TRADING REGION SOUTH. 30

  31.  In D+1, contractual imbalances are calculated by distributing total imbalance over TIGF zone and GRTgaz Sud zone, by shipper and gas day D.  Total imbalance is distributed over TIGF zone and GRTgaz Sud zone using an individual distribution key according to the category of the shipper.  The contractual imbalances are provided with the allocations data to the shipper : • In D+1 asap (provisional data) • in D+n in case of changes (update during the month) • At the latest on 15th of month M+1 (définitive data) 31

  32. There are three different categories of shippers :  CATEGORY 1 : SUPPLIER  Shippers who have capacities on PS and/or PL of the TRADING REGION SOUTH  CATEGORY 2 : SHIPPER  Shippers who don’t have capacities on PS and/or PL of the TRADING REGION SOUTH but have capacities on at least one of the points PITT, NS link, PITS, PITP, PIR, PIRR of the TRADING REGION SOUTH  CATEGORY 3 : TRADER  Shippers who have an access to the point TRS only 32