WIS 49 over the South Branch Little Wolf River Main Street, Iola Waupaca County February 6, 2018 Iola Community Center
Introductions Current conditions Proposed improvements Traffic management Project timeline Questions 2
3
Bridge rails rusting 1927 Stone Masonry Arch River bed needs reinforcement Cracks in concrete and Two 12-foot travel lanes approaches On-street parking Sidewalk 4
Replace arch with bridge Asphalt approaches Combination railing Potential real estate needed Concrete aesthetics Project length = 220 feet Sidewalk and crosswalk 5
WIS 49 detoured via local roads 6
Complete environmental process – Fall 2018 Real estate negotiations – Fall 2018 Final plans – November 2019 Construction – Summer 2020 (after Iola Car Show) 7
Wendy Arneson, P.E. Ryan Barz, P.E. WisDOT AECOM (715) 421-7391 (715) 342-3012 Wendy.Arneson@dot.wi.gov Ryan.Barz@aecom.com 8