Orange County Public Schools Welcome! Please sign in on your mobile device: WINNER http://communitymeeting.ocps.net/ Hidden Oaks Elementary School 40% Construction Community Meeting February 5, 2018 Superintendent Dr. Barbara Jenkins Chief Facilities Officer John Morris
Orange County Public Schools Orange County Public Schools Hidden Oaks Elementary School 40% Construction Update Meeting Agenda February 5, 2018: Hidden Oaks Elementary School Media Center, 6:00pm • Welcome – Daryl Flynn, School Board Member • Introductions – Lauren Roth, Facilities Meeting Organizer • Project Update – Architect: Harvard Jolly Architects Construction Manager: Core Construction Services of Florida, LLC • Questions and Answers • Adjournment
Orange County Public Schools Project Data Capacity 650 Student Stations Buses/Service Building Area Dry Retention 76,796 Gross SF Pond Parking 120 Spaces Car Queuing 122 Cars Suburban Dr Bus Loop Bus Canopy CEP Service Parent Pick Up 151 ft Multi Kitchen Admin Purpose 14 Buses Dumpsters Wet Play Field Retention Pond Parent Canopy 146 ft Future Portables Media Center Portables 7 Portables Tot Youth Hardcourt Site Area Covered Parent/Sta +/- 20.07 Acres Play ff Bikes N Master Site Plan
Orange County Public Schools Rendering at Main Entry
Orange County Public Schools Phase 1 Jun/2017 – May/2018 1. Demolish existing Buildings and Portables 2. New 2-Story Building 3. New Bus Loop and Parking 4. New Parent Loop and Parking 5. New PE Facilities PHASE 1 Pedestrian/Bicycle Route N Phasing Plan
Orange County Public Schools Phase 2a Jun/2018 – Jul/2018 1. Begin Demolition of Existing Portables and PHASE 2 Buildings 2. Extend Bus Drive and Parking 3. Construct New Hardcourt PHASE 2 N Phasing Plan
Orange County Public Schools Phase 3 Oct/2018 1. Complete Playfields 2. Complete Drive PHASE 3 PHASE 3 N Phasing Plan
Orange County Public Schools Construction Update and Milestones - Notice to Proceed (NTP) was issued July 24, 2017. - Tilt Wall Panels were completed on November 06, 2017. - Structural Steel Erection was completed January 05, 2018 - Roofing work has started and will be completed by February 01, 2018 - Window installation started and will be completed by February 28, 2018 - Exterior painting has started and will be completed by February 15, 2018 - Interior finishes have begun. - Project is 40% complete. - Project remains on schedule: Substantial Completion of Phase I - June 8 th 2018 - Substantial Completion of Phase II – August 3 rd 2018 - Substantial Completion of Phase III – September 18 th 2018 - Sustainability
Orange County Public Schools Aerial Photo – Mid August
Orange County Public Schools Aerial Photo – Mid September 2017
Orange County Public Schools Aerial Photo – Mid October 2017
Orange County Public Schools Aerial Photo – Mid November 2017
Orange County Public Schools Aerial Photo – Mid December 2017
Orange County Public Schools Aerial Photo – Mid January 2018
Orange County Public Schools Neighborhood Access to School
Orange County Public Schools Preliminary Site Work Underground Conduit Primary Trenching
Orange County Public Schools Concrete Progress Slab on Grade Pour Forming Tilt Panels
Orange County Public Schools Tilt Panel Progress Elevator Pit & Tilt Panel Rebar Thin-Set Brick Veneer
Orange County Public Schools Tilt Panel Installation Tilt Panel Pour Tilt Panel Erection
Orange County Public Schools Structural Steel Progress Structural Steel Fabrication Structural Steel Erection
Orange County Public Schools Topping Out Roof Deck Installation Fire Proofing
Orange County Public Schools Roofing Membrane Installation
Orange County Public Schools Questions??