West Cape Transformer Replacement Purpose Purchase a 50 MVA Load - PowerPoint PPT Presentation

West Cape Transformer Replacement Purpose Purchase a 50 MVA Load Tap Changer power transformer for West Cape substation to replace the failed unit Location Map Transformer Failure 2005 Installed Kuhlman transformer at West Cape


  1. West Cape Transformer Replacement

  2. Purpose • Purchase a 50 MVA Load Tap Changer power transformer for West Cape substation to replace the failed unit

  3. Location Map

  4. Transformer Failure • 2005 – Installed Kuhlman transformer at West Cape substation in position 2759 • December 6, 2017 – Routine maintenance oil sample indicated excess acetylene levels • January 3, 2018 – Second oil sample confirmed December 6 test • January 3, 2018 – Transformer was removed from service • January 9, 2018 – Inspection discovered arcing near the corona shields at the top and bottom of winding

  5. Bidders List ● ABB – Crystal Springs, MS  Superior Power Products – Cape Coral, FL ● Delta Star – Lynchburg, VA  GRESCO – Orlando, FL ● GE Prolec – Apodaca, Mexico  Irby – Orlando, FL ● Pennsylvania Transformer Technology, Inc. – Canonsburg, PA  Engineer Power Products – Royal Palm Beach FL ● Waukesha – Goldsboro, NC  Electric Sales Associates – Weston, FL

  6. Bid Evaluation No-Load Auxiliary Manufacturer Bid Price Load Losses Total Cost Losses Losses Waukesha * * * * * GE Prolec * * * * * ABB * * * * * PA * * * * * Transformer Delta Star * * * * * * Proprietary confidential bid information.

  7. Actions Requested Motion to increase the T&D budget to allow for the purchase of the transformer. Motion to authorize the CEO to award the contract for the West Cape replacement power transformer to Electric Sales Associates for the purchase of a Waukesha transformer in the amount of * . * Proprietary confidential bid information.