Wappingers Central School District 2016 Capital Project Schematic Design Report Summary September 7, 2016 Schematic Design Report Project Budget Project Scope Site Improvements Accessibility Improvements Sports Improvements Music, Drama


  1. Wappingers Central School District 2016 Capital Project Schematic Design Report Summary September 7, 2016

  2. Schematic Design Report Project Budget Project Scope Site Improvements Accessibility Improvements Sports Improvements Music, Drama and Arts Improvements Facilities Improvements Project Schedule Other Project Initiatives Next Steps 2016 Capital Project Schematic Design Report Wappingers Central School District September 7, 2016 September 23, 2013 R H H I N N E B B E C K C K A R C H C H I T T E C T C T U R E E 1

  3. Project Budgets Scope Construction Budget Incidental Costs Total Facility Improvements $12,140,800 $3,035,200 $15,176,000 Accessibility Improvements $1,529,600 $382,400 $1,912,000 Sports Improvements $4,930,000 $986,000 $5,916,000 Arts Improvements $3,100,000 $619,000 $3,719,000 Total $21,700,400 $5,022,600 $26,723,000 2016 Capital Project Schematic Design Report Wappingers Central School District September 7, 2016 September 23, 2013 R H H I N N E B B E C K C K A R C H C H I T T E C T C T U R E E

  4. District Wide Scope of Work RCK JJ VW WJ BE FE FP GH JE KR MC OG SR VR BG1 Building BCS Building Rating S S S U S U U U U S U S U U U Proposed Improvements Facilities        Pavement - Roads and Lots       Sidewalks    BasketBall Courts      Site Drainage            Exterior Steps, Stairs, Ramps   Windows  Resilient Flooring  Ceilings       Stage Curtains  Lockers   Interior Doors    Interior Stair Rails  Interior Electrical Distribution     Cooling/Air Cond. Systems    Ventilation Equipment   Unit Ventilators   HVAC Controls Accessibility     Elevators           Toilet Rooms                Signage         Stage Access Program Improvements   Arts Program Improvements   Sports Program Improvements 2016 Capital Project Schematic Design Report Wappingers Central School District September 7, 2016 September 23, 2013 R H H I N N E B B E C K C K A R C H C H I T T E C T C T U R E E 3

  5. Roy C Ketcham High School Site Plan Scope of Work • Sports Improvements  Feature Field Improvements: New  Artificial Turf, Lighting,  Portable Bleachers  Improve Soccer and Baseball Fields  Re-sod Practice Football Field  Add storage building for equipment • Paving, Walks, and Drainage Improvements Practice New Paving New Concession Stand and Toilet Rooms (Separate Project) Baseball Soccer Feature Field Soft Ball and Track 2016 Capital Project Schematic Design Report Wappingers Central School District September 7, 2016 September 23, 2013 R H H I N N E B B E C K C K A R C H C H I T T E C T C T U R E E 4

  6. Roy C Ketcham High School Video Recording Classroom 227 Video Ceramics Production and 236 Darkroom 241 Second Floor Scope of Work Arts Program Improvements Main Office  Auditorium Upgrades,  New Stage lighting,  Acoustic Shell for Stage  Band Room Improvements  New Sound and Video Recording  Systems and Production Labs  Video monitors for Green Rooms Band  Renovate Ceramic Classroom,  Replace Art Room Sinks Chorus Air Conditioning Upgrades: First Floor Auditorium Main Office and Music Rooms 2016 Capital Project Schematic Design Report Wappingers Central School District September 7, 2016 September 23, 2013 R H H I N N E B B E C K C K A R C H C H I T T E C T C T U R E E 5

  7. John Jay High School Site Plan Paving, Walks, and Site Improvements New Paving Basketball New Paving Soccer/Soft Ball Toilet Field House Rooms To Baseball Field ` Feature Field Sports Improvements  Feature Field Improvements: New  Re-sod Practice Football Field  Artificial Turf, Upgrade lighting New  New Fencing  Renovate Toilet Rooms, Field House Improvements Scoreboard  Regrade Baseball Field, new Sod at  Add Storage Building for Equipment Soccer and Baseball Fields  Outside Basketball Court Upgrade 2016 Capital Project Schematic Design Report Wappingers Central School District September 7, 2016 September 23, 2013 R H H I N N E B B E C K C K A R C H C H I T T E C T C T U R E E 6

  8. John Jay Senior High School Scope of Work Arts Program Improvements  Auditorium Upgrades  New Stage Lighting  Acoustic Shell for Stage  Band and Chorus Room Improvements  New Practice Rooms  New Sound and Video Recording Chorus Auditorium  Systems and Production Labs  Video monitors for Green Rooms  Renovate 3D Classroom,  Replace Art Room Sinks Replace Ceiling Tiles in Corridors Band Video 3D CR Partial First Floor Plan Recording CR First Floor Plan New Art CR Sinks 2016 Capital Project Schematic Design Report Wappingers Central School District September 7, 2016 September 23, 2013 R H H I N N E B B E C K C K A R C H C H I T T E C T C T U R E E 7

  9. Van Wyck Junior High School Accessible Toilet Rooms - 2 nd floor Second Floor Replace Selected Corridor Lockers Replace Boys Gym Lockers First Floor 2016 Capital Project Schematic Design Report Wappingers Central School District September 7, 2016 September 23, 2013 R H H I N N E B B E C K C K A R C H C H I T T E C T C T U R E E 8

  10. Wappingers Junior High School Scope of Work • Elevator and Accessible Toilet Rooms Accessible Toilet • Wheelchair Lift Rooms • Replace Windows Office • Exterior Stair Repairs • Electrical Panel Replacements New Elevator • Ventilation System Upgrades • Heating Upgrades • Stage Curtains Second Floor Elevator Plan First Floor Similar Wheel Chair Lift Second Floor First Floor 2016 Capital Project Schematic Design Report Wappingers Central School District September 7, 2016 September 23, 2013 R H H I N N E B B E C K C K A R C H C H I T T E C T C T U R E E 9

  11. Brinckerhoff Elementary School Scope of Work • Exterior Caulking at Ramps • Repoint Chimney • Replace Library and Office Rooftop Units First Floor Plan New Roof Top AC units Fishkill Elementary School Scope of Work • Accessible Toilet Rooms • Exterior Stair Rails • Stage Curtains First Floor Plan 2016 Capital Project Schematic Design Report Wappingers Central School District September 7, 2016 September 23, 2013 R H H I N N E B B E C K C K A R C H C H I T T E C T C T U R E E 10

  12. Fishkill Plains Elementary School Faculty Room 280 SF Accessible Toilet Rooms New Accessible Toilet Rooms Reconfigure Faculty Room Faculty Room and New Toilet Rooms First Floor Plan New Stage Curtains New Hand Rails 2016 Capital Project Schematic Design Report Wappingers Central School District September 7, 2016 September 23, 2013 R H H I N N E B B E C K C K A R C H C H I T T E C T C T U R E E 11

  13. Gayhead Elementary School Site Plan Scope of Site Work • Paving and Drainage Improvements • Exterior Stair Repairs • Reconstruct Damaged Sidewalks • Outside Basketball Court Improvements • Remove Modulars 2016 Capital Project Schematic Design Report Wappingers Central School District September 7, 2016 September 23, 2013 R H H I N N E B B E C K C K A R C H C H I T T E C T C T U R E E 12

  14. Gayhead Elementary School Scope of Interior Work • Elevator • Accessible Toilet Rooms First Floor Plan Lower Level First Floor Elevator Elevator New Ramp Lower Level Floor Plan 2016 Capital Project Schematic Design Report Wappingers Central School District September 7, 2016 September 23, 2013 R H H I N N E B B E C K C K A R C H C H I T T E C T C T U R E E 13

  15. James Evans Elementary School Site Improvements Scope of Site Work • Paving and Drainage Improvements • Sidewalk Replacement New Paving 2016 Capital Project Schematic Design Report Wappingers Central School District September 7, 2016 September 23, 2013 R H H I N N E B B E C K C K A R C H C H I T T E C T C T U R E E 14

  16. James Evans Elementary School Scope of Interior Work • Elevator and Accessible Toilet Rooms • Stair Rails Gym • Access to Stage New VCT in 1 st Floor Corridors and Stairs • New Elevator Reconfigure Classroom, Office and OT/PT Elevator Cafeteria OT/PT Office New VCT Office First Floor Plan New New Elevator Classroom Reconfigure Art Classroom and Faculty Room Nurse Accessible Toilet Rooms Lower Level Floor Plan Partial First Floor Plan at Elevator 2016 Capital Project Schematic Design Report Wappingers Central School District September 7, 2016 September 23, 2013 R H H I N N E B B E C K C K A R C H C H I T T E C T C T U R E E 15

  17. Kinry Road Elementary School Scope of Work • Paving, Walks, and Drainage Improvements • Provide ADA Access to Stage • New Stage Curtains New Paving 2016 Capital Project Schematic Design Report Wappingers Central School District September 7, 2016 September 23, 2013 R H H I N N E B B E C K C K A R C H C H I T T E C T C T U R E E 16