Van Dyke Rd Station New 115/13.2kV Station This text box and image - PowerPoint PPT Presentation

Van Dyke Rd Station New 115/13.2kV Station This text box and image This text box and image This text box and image Place your chosen can be deleted and can be deleted and can be deleted and image here. The four replaced with your own


  1. Van Dyke Rd Station – New 115/13.2kV Station This text box and image This text box and image This text box and image Place your chosen can be deleted and can be deleted and can be deleted and image here. The four replaced with your own replaced with your own replaced with your own corners must just selection from Brand selection from Brand selection from Brand cover the arrow tips. Central’s image library. Central’s image library. Central’s image library. For covers, the three pictures should be the same size and in a straight line. March 18, 2015 1

  2. How the System Works 2

  3. Location  Property was purchased in the 1960s for a potential substation site.  Located adjacent to an existing 115kV transmission line.  Only requires short taps to connect transmission to station.  Centrally located to address the load relief issues in the Bethlehem – Delmar region.  Distribution lines can be built in close proximity to serve load.  Load – The amount of ‘electric power’ delivered (or required) at any specified point on a circuit to serve customers.  Minimal environmental impacts  No potential forest impacts  No potential wetland or stream impacts 3

  4. Project Drivers  The primary driver for the proposed Van Dyke substation is load relief within in the Bethlehem – Delmar region.  Improved reliability  Decrease the number of outages  Decrease the length of outages when they do occur  This project will resolve two existing issues;  Juniper Substation is currently exceeding its capacity.  Voorheesville Substation is currently the single source for supplying several distribution circuits which has become a reliability issue. 4

  5. Project Drivers  The new station will allow for the ultimate retirement of the Delmar and Juniper Substations.  The Delmar Station (est.1950’s) has a number of equipment related issues which needs to be addressed in the next few years.  The Juniper Station was built in the 1980’s to serve the residential housing developments along the Delmar Bypass.  The new Van Dyke Station will also add the capacity necessary to provide service to the new Vista Tech Park. One-third of the station load will serve the Vista Tech Park while the remaining two-thirds will serve the Bethlehem – Delmar region. 5

  6. Scope of Work 6

  7. Schedule - Key Milestones  Below Grade Construction – Summer 2015  Site preparation – site grading, grounding grid and stone placement  Storm water controls  Concrete Equipment Foundations  Perimeter Security Fencing  Above Grade Construction (Electrical Equipment) – Winter 2015  Transformers  Metal Clad (Switchgears)  Lightning Masts  Concrete Duct Line Construction – Summer 2016  Van Dyke Rd Underground Concrete Duct Line 7

  8. Substation Site Map 8

  9. Substation Rendering 9

  10. Conceptual Planting Plan 10

  11. Visual Simulation - Existing 11

  12. Visual Simulation – Proposed (Plantings) 12

  13. For More Information To learn more about the Van Dyke Station Project:  Visit our Project Website: www.capitalregionreliability.com  Email the team: info@capitalregionreliability.com  Call us at: (518) 433-3637 13