urbana elementary feasibility study board presentation
play

Urbana Elementary Feasibility Study Board Presentation - PDF document

Urbana Elementary Feasibility Study Board Presentation


  1. Urbana Elementary Feasibility Study Board Presentation ����������������� ����������������� ����������������� ����������������� ���������������������������������������������������� ���������������������������������������������������� ���������������������������������������������������� ���������������������������������������������������� Crabtree, Rohrbaugh & Associates, Architects Feasibility Study Milestones Steering Committee Meetings • Faculty / Student / Community “Charrettes” • Educational specification/Program Comparison • Physical site and Building Assessment • Option Development/Refinement • Cost Analysis • What is Next? • � Community Input Meeting � Faculty/Staff Input Meeting � Committee Review of Draft Report � Present Final Report and Recommendations to BOE 1

  2. Feasibility Study Team Feasibility Study Steering Committee � Brad Ahalt FCPS Construction - Senior Project Manager Consultant Team � Ray Barnes FCPS Executive Director of Facilities Services � Roger Fritz FCPS Director of Construction � Jan Hollenbeck Urbana Elementary School Principal � Robert Johnson FCPS Supervisor Cluster Maintenance Program � Gloria Mikolajczyk MSDE Schools Facilities Architect Supervisor � Beth Pasierb FCPS Facilities Planner � Kathy Prichard FCPS Elementary Instructor Director � Emily Reedy FCPS Communications � Brett Stark FCPS Director of Curriculum � Karen Wills Urbana Elementary School Teacher Feasibility Study Process Overview of Key Objectives of the Study • Existing Facility and Site Study • Built in 1960 with Additions in 1965 &1975 (1/3 renovated in 1975) = 64,133 SF • Adhere to Maryland Public School Construction Program (PSCP) Guidelines • Educational Program Review • Develop options w/constructability justification: 1. Renovate existing school 2. Modernization - Partial demo, additions & renovations 3. Complete demo & replacement of the school on site • Complete estimated costs & schedules for each option 2

  3. Community Engagement • Definition and Goals of Charrette • Staff & Community Engagement • Questions/Results Community Engagement • Student Participation • Staff and Community Update Events – Online Survey Results If nothing else this project must…. 3

  4. Urbana Elementary Student Input Student Artwork Comments: � Indoor/Outdoor School � Windows � Safety and Emergency Concerns � STEM � Nice Teachers � Green House � Two Stories � Café � Collaboration Space � Magnet Programs Existing Building Assessment � Built: 1960 � Size: 64,133 SF � Site: 19.87 Acres � Enrollment: 985 (Equated) � State Rated Capacity: 511 � Years of Major Construction 4

  5. Existing Building Assessment � EXISTING SITE: � Site is rectangular with limited street frontage on Urbana Pike. � Dedicated Bus Loop in front of school with Parent drop on adjacent Urbana N Volunteer Fire Department Property on the western border � Great Heron Wetland borders the eastern side of the site. � Interstate 270 borders the south side of the site . � Existing Site Plan Existing Building Assessment � Great Heron Wetlands • Originally constructed through a grant in 2000. • 1of 11 sites monitored by the Watershed Management Division of Frederick County and directly affects Chesapeake Bay. • Hands on outdoor learning environment includes two ponds and native plants. 5

  6. Existing Building Assessment 14 Portable Classrooms � Existing Urbana Elementary School Floor Plan with Portable Classrooms Existing Building Assessment 6

  7. Existing Building Assessment Feasibility Study Options Overview of Proposed Options � Option 1 – Phased Additions/Renovations While Occupying Existing Building � Option 2 – Replacement School While Occupying Existing Building � Option 3A – Replacement School While Relocated to Sugarloaf Elementary School � Option 3B – Replacement School While Relocated to Portables 7

  8. Feasibility Study Options Summary of Option 1 TOTAL PROJECT COST $54,165,520 Construction Duration – 44 Months � Longest construction duration of all options; phased over 44 months. � Most disruption of all options to the educational program, during construction. � Most expensive option. Option 1 – Phased Additions and Renovations while Occupying the Existing Building Feasibility Study Options Summary of Option 2 TOTAL PROJECT COST $41,433,200 Construction Duration – 28 Months � Less disruption to educational program than Option 1. � Reduced construction time frame from Option 1. � The new facility is located in central portion of the site, further from Urbana Pike. � Option requires negotiations with adjacent Fire Department for construction access. � Play areas and rear playfields will not be accessible during construction. OPTION 2 – REPLACEMENT SCHOOL WHILE OCCUPYING THE EXISTING BUILDING 8

  9. Feasibility Study Options Summary of Option 3A TOTAL PROJECT COST $40,128,436 Construction Duration – 24 Months � Least disruption to educational program of all the options. � Shortest construction time frame of all the options. � Lowest cost of all options. � Dependant on funding as requested by the Board of Education. � Potential to delay the opening of Sugarloaf Elementary School by one to two (1-2) years. OPTION 3A – REPLACEMENT SCHOOL WHILE RELOCATED TO SUGARLOAF ELEMENTARY SCHOOL Feasibility Study Options Summary of Option 3B TOTAL PROJECT COST $45,875,476 Construction Duration – 28 Months � More disruption to the educational program during construction than Option 3A. � Slightly longer construction time frame than Option 3A. � Difficult site access during construction for parent drop-off access. OPTION 3B – REPLACEMENT SCHOOL WHILE RELOCATED TO PORTABLES 9

  10. Recommendation It is the recommendation of this steering committee and supported by the majority of the Urbana community comments received by on-line survey, that Option 3A is preferred method to modernize Urbana Elementary School. The committee makes this recommendation with the following assumptions: 1. Sugarloaf Elementary School will be used as temporary swing space during construction. This will affect the timing of planned redistricting in the Urbana community. 2. Construction funding for the Urbana Elementary School modernization will be awarded as requested by the Board of Education in their current Educational Facilities Master Plan. OPTION 3A – REPLACEMENT SCHOOL WHILE RELOCATED TO SUGARLOAF ELEMENTARY SCHOOL Urbana Elementary School Feasibility Study QUESTIONS 10

Recommend


More recommend