Logan Library Site Feasibility Study August 18, 2020 LOGAN LIBRARY | Site Feasibility Study August 18, 2020
Library Site Feasibility Study August 18, 2020 • Site Analysis • Proposed Site Plan • Proposed Building Massing • Project Cost Estimate LOGAN LIBRARY | Site Feasibility Study August 18, 2020
Project Goal: Explore several viable design options for a new library on the existing library site and determine a preferred option(s) with associated project costs. LOGAN LIBRARY | Site Feasibility Study August 18, 2020
Site Analysis LOGAN LIBRARY | Site Feasibility Study August 18, 2020
Site Analysis Site Location LOGAN LIBRARY | Site Feasibility Study August 18, 2020
Site Analysis Solar Orientation LOGAN LIBRARY | Site Feasibility Study August 18, 2020
Site Analysis Pedestrian Access Vehicle Access LOGAN LIBRARY | Site Feasibility Study August 18, 2020
Site Analysis Public Entries Service Entries LOGAN LIBRARY | Site Feasibility Study August 18, 2020
Site Analysis Building Edges LOGAN LIBRARY | Site Feasibility Study August 18, 2020
Site Analysis Acoustic Disturbance LOGAN LIBRARY | Site Feasibility Study August 18, 2020
Site Analysis Views In/Out LOGAN LIBRARY | Site Feasibility Study August 18, 2020
0 0 9 C G # . ! g E 1 " 2 " ) T T " 50 W 12" 15" C900 6 G ! . g ! C900 8 g M ! M M ! C a s t I r o n 4 # g T " T Cast Iron 6 " " ) T T ! M . ! G ! M ) " 8'' " C 9 0 0 1 0 C T T 9 0 0 1 0 C 9 Cast Iron 6 0 0 1 0 M ! ) " C 9 0 0 1 0 ! M ! G g C900 10 M . ! C900 10 C900 10 18" C900 10 " T T 18" # C900 10 300 N " ) ) " " ) ) " 25 spaces C900 10 " # On Street parking (300N) : 25 spaces 5 1 2 ' ' 1 ; 12'' ; ! . ; C900 8 2 1 " E ; ; ; ! . 12'' ) " ; ; 8 ; ; g 6 ! . 1 2 g ' ' g ; " 0 0 g " T T T M ! 1 8 " T " g 0 T T 0 g 9 18" 9 " T T 15" 15" " C C ! M T T T " T 1 8 " g ! M ! M g g 1 8 " " 12" 1 5 " ! M " T T 8 " " T T T T g g ! < " " " T T T T 8 1 g T T " City Hall Police and Library Stafg : 55 spaces 55 spaces " ) ) " ! M " ) " ) C900 8 ! M ; Shared w/ Hotel: 15 spaces ! g M 100 W g T " T g " ) PVC " T T ! M " T T g " T T wer City Hall Existing Library ! M Power Cast Iron 10 Power D u c t i l e I r o n 6 Total: 95 spaces G ! . # ! . parking. M ! ng Power ' ' 8 ! M 0 1 ! M g 57 spaces. n " o T T r I t s a C ! M ; ! . Cast Iron ; Not included g G 15 spaces ! . " T T ! M C900 8 M ! 0 1 ' n ! M ' o 8 r I t s a ! M C g " T T ) " " ) ! M ) " ) ) " " ) " C900 8 ! ; M ! M ! M D u c t i l e I r o n 6 " ) ! M " ) " ) Existing Parking - 95 spaces LOGAN LIBRARY | Site Feasibility Study August 18, 2020
Retain Police and Library Stafg : 55 spaces (includes 5 library stafg) Library (1 per 500 sf ): approx 75 spaces Total : 130 spaces Bicycle parking (10% of Required Parking): 8-13 spaces Target Parking - 130 spaces LOGAN LIBRARY | Site Feasibility Study August 18, 2020
Proposed Site Plan LOGAN LIBRARY | Site Feasibility Study August 18, 2020
Previous Building Studies Preferred : 2-Story, Main Street Frontage 200 N 200 N 100 W 100 W MAIN ST. 300 N MAIN ST. 300 N Option 1 Option 2 200 N 200 N 100 W 100 W MAIN ST. 300 N MAIN ST. 300 N Option 3 Option 4 LOGAN LIBRARY | Site Feasibility Study August 18, 2020
Site Plan 300 N City Hall New New Plaza Library Main St. Post Offjce Hotel LOGAN LIBRARY | Site Feasibility Study August 18, 2020
Site Plan 300 N 25 Spaces Parking Count: City Hall 46 Spaces 130 spaces targeted 134 spaces New provided New Plaza Library 13 Bicycle 44 Spaces Spaces 19 Spaces Main St. 57 Spaces (existing City Hall spaces not included) Hotel Parking Post Offjce Hotel LOGAN LIBRARY | Site Feasibility Study August 18, 2020
300 N Site Plan City Secure police + Staff Parking Hall Cell Tower Staff Entry Main St. New Library New Plaza Entry Bicycle Entry Parking Public Parking LOGAN LIBRARY | Site Feasibility Study August 18, 2020
W 300 N View 1 48’ 55’ New Library View 1 - Corner of Main St and 300N Main St. View 2 Site Plan View 2 - Looking North on Main St. LOGAN LIBRARY | Site Feasibility Study August 18, 2020
48’ 55’ View 1 - Corner of Main St and 300N LOGAN LIBRARY | Site Feasibility Study August 18, 2020
View 2 - Looking North on Main St. LOGAN LIBRARY | Site Feasibility Study August 18, 2020
Cost Analysis Logan Library - Cost Baseline Comparisons Recently completed Utah Library Projects Daybreak Library completed in 2020 Kearns City Library completed in 2020 27,000 sf 35,000 sf Daybreak City, Utah Kearns City, Utah $380.00/sf Project Budget $240.00/sf Project Budget Daybreak Library completed in 2020 27,000 sf Daybreak City, Utah $380.00/sf Project Budget Logan Library - Cost Baseline Comparisons Recently completed Utah Library Projects Kearns City Library completed in 2020 LOGAN LIBRARY | Site Feasibility Study August 18, 2020 35,000 sf Kearns City, Utah
Thank-you! LOGAN LIBRARY | Site Feasibility Study August 18, 2020