University Construction Oversight Meeting October 22, 2020 2 Project Updates University Construction / Operations Dr. Alan Robertson Vice President for Finance and Administration / CFO 3 Major Capital Projects Update Center for Access


  1. University Construction Oversight Meeting October 22, 2020

  2. 2

  3. Project Updates – University Construction / Operations Dr. Alan Robertson Vice President for Finance and Administration / CFO 3

  4. Major Capital Projects Update  Center for Access and Student Success (CASS)  FAMU Student Service Center Dining Hub  Student Amphitheater  Bragg Memorial Stadium 4

  5. Center for Access and Student Success (CASS)

  6. Center for Access and Student Success (CASS) Project Status Report: Budget: $41,000,000 Date: 10/22/2020 Project #: Project Name: University Project Manager: Project Status: Center for Access and Student BRFM 337 David Rosenfeld/Craig Talton Success Design Status (% Complete): Designer: Substantial Completion Date: On track with revised schedule 100% JRA Architects Nov 10, 2020 Construction Status (% Contractor: Occupancy Date: Complete): 83% Ajax Construction Dec 31, 2020 Timely Completion Risk: COVID-19, Material Delivery Mitigation Strategy: Contractors Following State & Federal Guidelines Project Contracts: Expenses: Encumbrances: Remaining: $41,000,000 $27,424,112 $10,863,995 $2,711,893

  7. Student Service Center Dining Hub

  8. Student Service Center Dining Hub Project Status Report: Budget: $10,869,230 Date: 10/22/2020 Project #: Project Name: University Project Manager: Project Status: BRFM 343 Student Dining Facility Elston Peets Design Status (% Complete): Designer: Substantial Completion Date: On track with 100% Andy Share and Associates Dec, 2020 revised schedule Construction Status (% Contractor: Occupancy Date: Complete): 50% CTG/Genterra Dec, 2020 Timely Completion Risk: Severe weather, equipment delivery, COVID-19. Developer will work with Auxiliary Services, Metz and Genterra weekly to reduce the Mitigation Strategy: risk associated with long lead time equipment. Project Contracts: Expenses: Encumbrances: Remaining: $10,869,230 $4,725,263 $3,162,187 $2,981,780

  9. Student Amphitheater

  10. Student Amphitheater Project Status Report: Budget: $2,727,934 Date: 10/22/2020 Project #: Project Name: University Project Manager: Project Status: CITF 2019 Student Amphitheater David Rosenfeld Design Status (% Complete): Designer: Substantial Completion Date: On track with 100% GRC Architects January, 2020 revised schedule Construction Status (% Complete): Contractor: Occupancy Date: 74% RAM Construction February, 2020 Timely Completion Risk: Severe weather and delivery of materials Mitigation Strategy: None Project Contracts: Expenses: Encumbrances: Remaining: $2,227,934 $1,516,624 $165,483 $90,605

  11. Bragg Stadium

  12. Bragg Stadium Project Status Report: Budget: $10,000,000 Date: 10/22/2020 Project #: Project Name: University Project Manager: Project Status: Bragg Stadium Renovation - Design Status (% Complete): Designer: Substantial Completion Date: 0% - - RFQ/RFP Process Construction Status (% Complete): Contractor: Occupancy Date: 0% - - Timely Completion Risk: Mitigation Strategy: Project Contracts: Expenses: Encumbrances: Remaining: $ $ $ $

  13. Major Capital Projects – Most Recently Completed Dr. Alan Robertson Vice President for Finance and Administration / CFO 13

  14. Major Capital Projects – Most Recently Completed  700-Bed Residence Hall – Project Phase 1A  Central Energy Plant (CEP) 14

  15. 700-Bed Residence Hall

  16. Central Energy Plant (CEP)