university construction oversight meeting
play

University Construction Oversight Meeting June 29, 2020 University - PowerPoint PPT Presentation

University Construction Oversight Meeting June 29, 2020 University Construction Oversight Meeting Monday, June 29, 2020 8:30 AM Conference Call AGENDA I. Call to Order Trustee Moore II. Roll Call Dr. Turner III. Opening Remarks Chair Lawson


  1. University Construction Oversight Meeting June 29, 2020

  2. University Construction Oversight Meeting Monday, June 29, 2020 8:30 AM Conference Call AGENDA I. Call to Order Trustee Moore II. Roll Call Dr. Turner III. Opening Remarks Chair Lawson IV. Major Capital Projects Updates: VP Robertson a. Center for Access and Student Success (CASS) b. 700-Bed Residence Hall – Project Phase IA c. Central Energy Plant (CEP) d. FAMU Student Service Center Dining Hub e. Student Amphitheater V. Questions VI. Adjournment Trustee Moore 2

  3. Project Updates – University Construction / Operations Dr. Ala lan n Ro Robe bertson rtson Vi Vice e Pres esident ident for or Fin inance ance and nd Admin minist istrat ration ion / C / CFO 3

  4. Major Capital Projects Update ❖ Center for Access and Student Success (CASS) ❖ 700 Bed Residence Hall ❖ Central Energy Plant (CEP) ❖ FAMU Student Service Center Dining Hub ❖ Student Amphitheater 4

  5. Center for Access and Student Success (CASS)

  6. Center for Access and Student Success (CASS) Project Status Report: Budget: $41,000,000 Date: 6/29/2020 Project #: Project Name: University Project Manager: Project Status: Center for Access and Student BRFM 337 David Rosenfeld/Craig Talton Success Design Status (% Complete): Designer: Substantial Completion Date: Material Delay 100% JRA Architects Nov 10, 2020 Construction Status (% Contractor: Occupancy Date: Complete): 64% Ajax Construction Dec 31, 2020 Timely Completion Risk: COVID-19, Material Delivery Mitigation Strategy: Contractors Following State & Federal Guidelines Project Contracts: Expenses: Encumbrances: Remaining: $41,000,000 $22,071,240 $15,367,432 $3,561,327

  7. 700-Bed Residence Hall

  8. 700 Bed Residence Hall Project Status Report: Budget: $59,500,000 Date: 6/29/2020 Project #: Project Name: University Project Manager: Project Status: BRFM 343 700 Bed Residence Hall David Rosenfeld/Craig Talton Design Status (% Complete): Designer: Substantial Completion Date: On Time 100% Finfrock Design Inc. July 27, 2020 Construction Status (% Contractor: Occupancy Date: Complete): 94% Construct Two Group (CTG) August 11, 2020 Timely Completion Risk: Completion of the Central Energy Plant by April 25 th Mitigation Strategy: A temporary chiller and boiler will be utilized. Project Contracts: Expenses: Encumbrances: Remaining: $56,635,386 $46,205,103 $9,973,702 $456,580

  9. Central Energy Plant (CEP)

  10. Central Energy Plant (CEP) Project Status Report: Budget: $3,363,348 Date: 6/29/2020 Project #: Project Name: University Project Manager: Project Status: BRFM 343 Central Energy Plant David Rosenfeld Substantial Completion Design Status (% Complete): Designer: Date: 100% Pinnacle Engineering Group March 30, 2020 Weather Delay Construction Status (% Contractor: Occupancy Date: Complete): 98% Lang Mechanical Inc. April 30, 2020 Timely Completion Risk: Mitigation Strategy: Project Contracts: Expenses: Encumbrances: Remaining: $3,364,614 $3,293,557 $71,057 0

  11. Student Service Center Dining Hub

  12. Student Service Center Dining Hub Project Status Report: Budget: $10,869,230 Date: 6/29/2020 Project #: Project Name: University Project Manager: Project Status: BRFM 343 Student Dining Facility Elston Peets Design Status (% Complete): Designer: Substantial Completion Date: 100% Andy Share and Associates Oct 30, 2020 Weather Delay Construction Status (% Contractor: Occupancy Date: Complete): 12% CTG/Genterra Nov 30, 2020 Timely Completion Risk: Severe weather, equipment delivery, COVID-19. Developer will work with Auxiliary Services, Metz and Genterra weekly to reduce the Mitigation Strategy: risk associated with long lead time equipment. Project Contracts: Expenses: Encumbrances: Remaining: $10,869,230 $2,407,497 $5,045,350 $3,416,382

  13. Student Amphitheater

  14. Student Amphitheater Project Status Report: Budget: $2,727,934 Date: 6/3/2020 Project #: Project Name: University Project Manager: Project Status: CITF 2019 Student Amphitheater David Rosenfeld Design Status (% Complete): Designer: Substantial Completion Date: 100% GRC Architects Aug, 2020 On Time Construction Status (% Complete): Contractor: Occupancy Date: 82% RAM Construction Sep, 2020 Timely Completion Risk: Severe weather (impact will be minimal), delivery of materials Mitigation Strategy: None Project Contracts: Expenses: Encumbrances: Remaining: $2,227,934 $1,516,624 $165,483 $90,605

  15. “At FAMU, Great Things are Happening Every Day!” 15