Tillamook County TLT Grants Report to Tillamook County Commission - PowerPoint PPT Presentation

Tillamook County TLT Grants Report to Tillamook County Commission January 24, 2018 TLT Facilitie Grants: Coastal Segment Planning $100,000 TLT Facilities Grant: Salmonberry Project Manager Position Support $50,000 Coastal Segment


  1. Tillamook County TLT Grants Report to Tillamook County Commission January 24, 2018

  2. TLT Facilitie Grants: • Coastal Segment Planning $100,000

  3. TLT Facilities Grant: • Salmonberry Project Manager Position Support $50,000

  4. Coastal Segment Planning Process: • Initiated in June of 2016 • Work performed by Parametrix • Completed in February 2017 • Included public meetings and workshops • Included review and input from Coastal Segment Planning Advisory Committee

  5. Coastal Segment Advisory Committee: Bill Baertlein, Tillamook County Commissioner • (Co-convener) Jack Mulder, POTB Commissioner/Tillamook • Creamery (Co-convener) Stevie Burden, Mayor, City of Wheeler • Joanne Aagard, Mayor, City of Rockaway Beach • John O’Leary, City Manager, City of Garibaldi • Shaena Peterson, Mayor, City of Bay City • Suzanne Weber, Mayor, City of Tillamook • Terry Fullan, Port of Nehalem Commissioner • Val Folkema, Port of Garibaldi Commissioner •

  6. Coastal Segment Advisory Committee: Jessica Jung, Oregon Coast Scenic Railroad • Justin Aufdermauer, Tillamook Chamber of • Commerce Nan Devlin, Visit Tillamook Coast • Dave Kunert, Hampton Lumber • Jennifer Purcell, North Coast Regional Solutions • Coordinator, Oregon DEQ Kate Skinner, Oregon Department of Forestry • Dean Burdick, Tillamook County Sheriff’s Office • Lisa Phipps, Tillamook Bay Estuary Partnership •

  7. Coastal Segment Planning Study Area: 22.6 miles from Mohler to Latimer Road

  8. Coastal Segment Planning Process Reports: • Technical Report No. 1, Trail Type and Alignment Analysis (Sept 2016) • Technical Report No. 2, Bridge and Trestle Evaluations and Cost Estimates (Nov 2016) • Coast Segment Planning Study Final Plan Report (Jan 2017)

  9. Coastal Segment Plan Topics: • Alternative trail types • Alternative trail alignments & designs • Bridge and trestle assessments • Boardwalks and other structures • Bypass options • Environmental permitting • Phasing options

  10. Salmonberry Trail Project Manager: • Funding for 2015-17 Biennium • Funded full-time position at OPRD (Dec 2015-June 2017) • Partner funding: Tillamook County - $50,000 • Washington County - $50,000 • Cycle Oregon - $50,000 • ODF - $25,000 • OPRD – balance (~$25,000) •

  11. Key Duties: • Staff to Salmonberry Trail Intergovernmental Agency Formed in • late 2016 Eleven member • IGA formed to provide governance

  12. Key Duties: • OPRD Liaison to Tillamook Forest Heritage Trust (Fundraising and Development for STIA)

  13. Key Duties: • Liaison to STIA member agencies for Salmonberry related projects: Tillamook Code Adoption project • Tillamook County • Brownfields project

  14. Key Duties: • Project management for ongoing planning and preparation work: Valley Segment Planning process • Canyon Segment Scoping • Banks-Vernonia connector design •

  15. Future Planning Planned Mar-17 Jun-17 Sep-17 Dec-17 Salmonberry Critical Task Timeline OperationalTasks -STIA Member Agencies Fundraising and Development Tasks -TFHT POTB/STIA Railbanking Fundraising (Capacity Building) TC BrownfieldsProject Valley Segment Planning Valley Planning Advisory Committee EstablishCapital Campaign Committee Benefits Study O&M Work Group TillamookCatalyst Project In Process CanyonScoping Canyon Segment Planning Mar-18 CapitalCampaign (ongoing) Jun-19 Sep-19 Canyon Planning Advisory Committee Interpretive Plan Development Dec-19 Nehalem Segment Planning WashingtonCounty Land Use Planning Nehalem Planning Advisory Comm Jun-18 Sep-18 Eastside Catalyst Project Dec-18 Mar-19 Salmonberry Critical Task Timeline Operational Tasks - STIA Member Agencies In Process Canyon Planning Advisory Committee Nehalem Planning Advisory Comm Planned Nehalem Segment Planning Canyon Scoping Canyon Segment Planning Valley Planning Advisory Committee Valley Segment Planning WashingtonCounty Land Use Planning POTB/STIA Railbanking O&M Work Group Eastside Catalyst Project TC BrownfieldsProject TillamookCatalyst Project Mar-17 Jun-17 Sep-17 Dec-17 Mar-18 Jun-18 Sep-18 Dec-18 Mar-19 Jun-19 Sep-19 Dec-19 Fundraising (Capacity Building) EstablishCapital Campaign Committee Capital Campaign (ongoing) Benefits Study Interpretive Plan Development Fundraising and Development Tasks - TFHT

  16. Join us for the journey www.salmonberrytrail.org