The Renaissance Plan An Initiative of Goal 3 of Envisioning 2024 Overview of the Renaissance Plan Ky Snyder VP Operations Zack Knipe Director Planning, Design and Construction James Miyashiro Chief Public Safety Andre Mallie Assistant


  1. The Renaissance Plan An Initiative of Goal 3 of Envisioning 2024

  2. Overview of the Renaissance Plan Ky Snyder VP Operations Zack Knipe Director Planning, Design and Construction James Miyashiro Chief Public Safety Andre Mallie Assistant Vice President Auxiliary Services

  3. Construction Projects in the Renaissance Plan • Learning Commons • Copley Library • Camino, Founders and Sacred Heart Halls • Knauss Center for Business Education • Olin Hall

  4. Construction Projects in the Renaissance Plan - Construction Schedule: Five-Project Plan

  5. Construction Projects in the Renaissance Plan - Learning Commons Mixed-use educational facility featuring 24-hour collaborative study space, grab-n- go food service, and outdoor study space • Tom Herrinton Lead Stakeholder Representative • 13 Classrooms • 9 Collaborative study rooms • Towne square Project Manager Meaghan Christman

  6. Construction Projects in the Renaissance Plan - Copley Library I nterior renovation of student study space, staff space, and collection • Theresa Byrd Lead Stakeholder Representative • Over 1,000 seats • 3 Classrooms • 38 Collaborative study spaces • Faculty/Staff reading room Project Manager Erin Borzage

  7. Construction Projects in the Renaissance Plan - Camino / Founders / Sacred Heart Modernization and improvements to the original campus structures • First Stakeholder Representatives meeting December 12, 2018 • Multiple Stakeholders sub-groups • Kristin Moran Lead Stakeholder Representative • Construction start June 2020 • Opening August 2021 Project Manager Zachary Randel

  8. Knauss Center for Business Education • First Stakeholder Representatives meeting December 17, 2018 • David Light Lead Stakeholder Representative • Construction start spring 2021 • Opening August 2022 Project Manager Erin Borzage

  9. Olin Hall • Work to commence following Knauss Center being fully occupied • Programming for Olin will be coordinated with Knauss Center programming • Primarily a deferred maintenance project with opportunities for enhancements with successful fund raising efforts • Construction will last approximately 12 months Project Manager TBD

  10. Logistics Planning - June 2019 to August 2020 (Summer 2019)

  11. Logistics Planning (Summer 2019) Transportation and Mobility Plan: June 2019 to August 23, 2019 • Full closure of Manion Way from Copley to The Immaculata • All parking spaces on Manion Way will be closed • SOLES surface lot closed • Assisted access into the SOLES Garage through exit (green line)

  12. Logistics Planning (Academic Year 2019 - 2020) Transportation and Mobility Plan: August 23, 2019 to June 2020 • After reopening of Manion Way, one-way traffic northbound and eastbound on Manion Way • Temporary loss of 21 parking spaces • Access to SOLES surface lot and garage opens

  13. Logistics Planning Temporary Offices • MRHRR: Library Staff – May 2019 • LRC Basement: Library Staff – May 2019 • Modular Building: Library Staff – May 2019 Study Spaces • MRHRR open during construction regular hours • SLP to be open same hours as library • Saints Tekakwitha and Serra Hall open same hours as library

  14. Logistics Planning (Summer 2019) Dining Services: June 2019 to August 2019 • Food Truck (Torero To Go) – relocate to Kroc IPJ (from Copley) • Regular summer services - Open Tu Mercado, Pavilion Dining, La Gran Terraza, Food Truck, Missions Café (July only) - Closed Bert’s Bistro, La Paloma, Aromas

  15. Logistics Planning (Academic Year 2019 - 2020) Dining Services: September 2019 to May 2020 • Regular academic year services. All units open. - Aromas - Bert’s Bistro - Blue Spoon - La Gran Terraza - La Paloma - Missions Café - Pavilion Dining - Torero To Go (food truck) at Kroc IPJ - Tu Mercado

  16. Logistics Planning (Summer 2019) Housing / Conference Services: June 2019 to August 2019 • No changes

  17. Logistics Planning (Academic Year 2019 - 2020) Housing / Conference Services: September 2019 to May 2020 • No changes

  18. Logistics Planning - June 2020 to August 2020 (Summer 2020) • Lay Down Logistics • Transportation and Mobility • Temporary Offices • Dining Services • Housing/Conference Services * Draft plan to be presented at September 24 th and 26 th Forums * Final draft plan to be presented at December 3 rd and 5 th Forums