TAXIWAY ALPHA REHAB CONSTRUCTION Shane A. Nixon. Airport Project Manager
Limits of Construction
Area A Limits of Construction Area A1-30 days • Area A2-60 days • Work within A1 • and A2 may occur simultaneously All work within Twy • E object free area/taxiway safety area shall be completed at night
Area B Limits of Construction Area B1-20 days • Area B2-50 days • Work within Area B1 • and B2 may occur simultaneously
Crushing and removal
Scarifying and drying dirt
Undercut Area and Undercut Repair
Concrete Pavement Section and Shoulder Joint Detail
Concrete Treated Base (CTB) Placement
Trenching in Lighting Conduit, Installing Underdrain
Light Can Installation and Backfill
Concrete Joint and Elevation Plans
Reinforced Concrete Slabs
Production Concrete Pours
Concrete Production Pours
Production Concrete Pours
Saw Cutting Joints and Installing/Coring Taxiway Edge Lighting
Area A/B- Finished Product
Area C Area C -60 days • 60-day closure of Twy • Romeo Twy Golf nightime • closure Work may be • performed currently with work in Area D
Area D Area D- 30 days • 6” Mill and Pave Operation •
Area C and Area D
Areas C and D Paving
Area C and D Paving
Area E All work within • Area E shall be completed between Friday at 2300 to Sunday at 1800. Work in Area E • must complete within 10 consecutive calendar days
CLT Airport: Building an Airport for the Future!
Recommend
More recommend