Department of Public Works • Introductions • Project Schedule/Budget • Community Comments • Review Existing Conditions • Present Preliminary Design Concepts • Discussion
Department of Public Works PROJECT BUDGET AND SCHEDULE • Total Project Budget: $1.6M • Funded by the 2011 Road Repaving & Street Safety Bond • Project Schedule: • Planning: Dec 2012 - March 2013 • Design: April 2013 - Dec 2013 • Construction: January 2014 - August 2014 • Next Community Meeting #3: • March - TBD
Department of Public Works Community Meeting #1 Feedback Summary of comments: 1. Neighborhood Identity: • Quiet / Serene / Safe / Low Key • Convenient: Food / Shops/ Transit • Retro / Beachy / Arty / Funky 2. Needs more: • Seating & Meeting Areas (Parklet) • Planters & Landscape • Art 3. Attract New Businesses & People to Taraval 4. Parking & Traffic Needs: • Better Signage • Improved Beach Connection • Parking for Local Residents 5. Clean , Repair and Paint • Litter Removal (more Trash Receptacles) • Sidewalk & Pothole Repair • Building Façade Improvements
Department of Public Works Community Meeting #1 Feedback Ranking of Streetscape Elements: 1. Trash Receptacles/Litter Cleanup 2. Street Trees (palms) 3. Sidewalk Planting 4. Benches/seating 5. Parklet 6. Public Art 7. Gateway to Taraval 8. Street Lighting 9. Pedestrian Scale Lighting / Bulbouts / Banners 10. Bike Racks
• Project includes Taraval from 46 th to 48 th streets Taraval Streetscape Project Existing Conditions Department of Public Works
+/- 60 ’ Roadway +/- 10’ Sidewalks Taraval Streetscape Project Existing Conditions Department of Public Works
• Lack of green space • Dominant roadway • Poor road condition Taraval Streetscape Project Existing Conditions Department of Public Works
• Fractured surface • Faded lane striping Taraval Streetscape Project Existing Conditions Department of Public Works
• Parallel and perpendicular parking conditions Taraval Streetscape Project Existing Conditions Department of Public Works
• Worn sidewalk in disrepair • Multiple colors and finishes Taraval Streetscape Project Existing Conditions Department of Public Works
• Transit shelter replacement(in progress) Taraval Streetscape Project Existing Conditions Department of Public Works
48 th and Taraval: Beach Gateway • 46 th and Taraval: Transit Oriented • Taraval Streetscape Project Existing Conditions Department of Public Works
Design Inspiration Taraval Streetscape Project Design Inspiration Department of Public Works
Taraval Streetscape Project Design Imagery Department of Public Works
Taraval Streetscape Project Design Imagery Department of Public Works
Taraval Streetscape Project Design Imagery Department of Public Works
Taraval Streetscape Project Design Process Department of Public Works
Taraval Streetscape Project Design Process Department of Public Works
Taraval Streetscape Project Design Process Department of Public Works
Taraval Streetscape Project Design Process Department of Public Works
Taraval Streetscape Project Preliminary Plan Overview Department of Public Works
47 TH Ave. 46 TH Ave. Taraval Street • Taraval: 46 th to 47 th Avenue Taraval Streetscape Project Preliminary Plan Department of Public Works
46 TH Ave. 47 TH Ave. Bashful Bull Taraval Street Riptide Congregation B’nai • Rip Tide Parklet Taraval Streetscape Project Potential Parklet Locations Department of Public Works
47 TH Ave. 46 TH Ave. Bashful Bull Taraval Street Riptide Congregation B’nai • The Bashful Bull Parklet Taraval Streetscape Project Potential Parklet Locations Department of Public Works
47 TH Ave. 48 TH Ave. Taraval Street Gateway Elements: Potential Locations • Taraval: 47 th to 48 th Avenue Taraval Streetscape Project Preliminary Plan Department of Public Works
Taraval Streetscape Project Existing Condition Department of Public Works
Taraval Streetscape Project Gateway Elements Department of Public Works
Taraval Streetscape Project Crosswalk Treatments Department of Public Works
Taraval Streetscape Project Sustainable Elements Department of Public Works
Existing Section Taraval Streetscape Project Preliminary Sections Department of Public Works
Proposed Section A-A Taraval Streetscape Project Preliminary Sections Department of Public Works
Proposed Section B-B Taraval Streetscape Project Preliminary Sections Department of Public Works
Existing Condition Taraval Streetscape Project Existing Parking Counts Department of Public Works
Condition A Taraval Streetscape Project Potential Parking Counts Department of Public Works
Condition B Taraval Streetscape Project Potential Parking Counts Department of Public Works
Condition C Taraval Streetscape Project Potential Parking Counts Department of Public Works
Discussion: • Parklet Location • Gateway Elements • Landscape/Parking Layout Taraval Streetscape Project Department of Public Works
Questions and Additional Comments Project Website http://www.sfdpw.org/index.aspx?page=1648 Contact Info: Meghan Tiernan 415.558.4541 Meghan.Tiernan@sfdpw.org Taraval Streetscape Project Department of Public Works
Recommend
More recommend