t2k experiment 1 the physics potential and the status of
play

T2K Experiment 1 The physics potential and the status of the - PowerPoint PPT Presentation

T2K Experiment 1 The physics potential and the status of the neutrino beam line Masahiro Shibata (KEK) for T2K collaboration Tokai to Kamioka (T2K) experiment Long base line (295 km) neutrino oscillation experiment with - high


  1. T2K Experiment 1 – The physics potential and the status of the neutrino beam line – Masahiro Shibata (KEK) for T2K collaboration

  2. Tokai to Kamioka (T2K) experiment ● Long base line (295 km) neutrino oscillation experiment with - high intensity proton beam (750 kW) of J-PARC main ring - world largest water Cherenkov neutrino detector (Super-Kamiokande)

  3. Physics motivation ● ν μ disappearance - precise measurement of θ 23 and Δm 2 23 - θ 23 is maximal mixing? ● Direct measurement of ν e appearance - discovery of finite θ 13 - θ 13 ≠0 → CP violation measurement in the future ⇒ to conclude for neutrino flavor mixing to find how matter dominated universe was made   ν θ θ − δ θ θ ν i    1 0 0  cos 0 sin e  cos sin 0              e 13 13 12 12 1 ν = θ θ − θ θ ν   0 cos sin 0 1 0 sin cos 0         µ 23 23 12 12 2           − δ ν − θ θ − θ θ ν i 0 sin cos sin e 0 cos 0 0 1           τ 23 23 13 13 3

  4. Outline of T2K experiment 1. Produce narrow band intense ν beam 2. Measure neutrino flux at ND (Φ ND obs ) and FD (Φ SK obs ) 3. Estimate neutrino flux at FD (Φ SK exp ) from Φ ND obs 4. Compare Φ SK exp and Φ SK obs ⇒ derive oscillation parameters (θ,Δm 2 )

  5. Neutrino energy reconstruction ● Interaction with nucleon in detector material is utilized. ● Neutrino energy is derived from Charge Current Quasi Elastic scattering (CCQE). CCQE p CC-inelastic Neutral Current (NC)

  6. Goal: ν μ disappearance SK, K2K, MINOS sin 2 2 θ 23 > 0.92 |Δm 2 23 | = 2.3~3.0×10 -3 eV 2 T2K goal δ(Δm 2 23 )<10 -4 eV 2 δ(sin 2 2θ 23 )<0.01 δ(Δm 2 23 )<10 -4 eV 2 δ(sin 2 2θ 23 )<0.01 @ 90% C.L. (stat. error only)

  7. Goal: ν e appearance ● CHOOZ sin 2 2 θ 13 < 0.19 ● MINOS (FNAL W&C Seminar 27/Feb/2009) observed: 35 events sin 2 2 θ 13 ~0.008 (δ=0,π) expected BG: 27±5±2 events sin 2 2θ 13 < 0.24 T2K goal sin 2 2 θ 13 ~0.008 (δ=0,π) @ 90% C.L. 90% C.L.

  8. Current status of the neutrino beam line

  9. Outline of neutrino beam line Horn Target Neutrino monitor building π to Kamioka ν p UA1 magnet for Primary proton beam line Near detector (ND280) Beam dump Target station 9 Decay volume

  10. Primary beam line 11 NC mags Preparation Section Preparation Section 10 NC mags ARC Section ARC Section 28 SC combined func mags (+3 SC corr mags from BNL) ● All mags installed ● SC mags cooled down ● Successfully operated Final Focusing Section Final Focusing Section

  11. Proton beam monitors ● Intensity monitor: current transformer (CT) ● Position monitor: electro static monitor (ESM) ● Profile monitor: segmented secondary emission monitor (SSEM) optical transition radiation monitor (OTR) ● Beam loss monitor (BLM): ionization chamber CT ESM ● All monitors (except few) were installed. ● Operation test was done during MR commissioning. (except OTR) ● First signal was measured by BLM. OTR SSEM Abort line Same ext. devices BLM Neutrino line

  12. Secondary beam line Decay volume (DV) Target station (TS) Beam dump (BD) Feb. 3, 2009 ● Most components have been installed. (except horn2,3) ● Vacuum test of the He chamber was successfully finished. ● Installation of ceiling concrete blocks on TS & BD is on going.

  13. Target and horns ● Target & Horn 1 were installed. ● Interference between Horn 2,3 & He chamber was found. ● 2 months delay was foreseen for modification. Target ● decide operation with target & Horn 1 only from Apr. ● Horn 2, 3 will be installed during summer shutdown. Horn 1 Horn 3 ● No actual impact on overall T2K schedule. Horn 2

  14. Muon monitor Installed the support structure Beam into the muon pit. (2/13) Installed all 7 ionization chambers and 49 silicon PIN photodiodes. • Readout electronics is installed in Hut. • Cabling / gas-piping is also finished. • Measured noise-level during MR operation is small enough. ( ± 0.5mV) NU3 Hut Chamber Silicon Muon pit Achieved alignment precision of 1 mm. (18.5 m below ground)

  15. Schedule Apr. ~ May 2009 ● First beam commissioning with target and Horn 1 ● 0.1 % beam intensity (4×10 11 p/pulse, single shot operation) ● Extract and transport the proton beam to the target ● Observe muon monitor signal to confirm neutrino production and focusing to Kamioka direction June ~ Sept. 2009 ● Install Horn 2 and Horn 3 Oct. ~ Nov. 2009 ● Beam commissioning with full setup Dec. 2009 ~ June 2010 ● After 100kW stable operation of accelerator is achieved ● Physics run 100kW × 10 7 s ~ 10 20 POT ● First physics result in 2010

  16. Summary ● T2K experiment - Long base line (295km) neutrino oscillation observation - Narrow band high intensity neutrino beam from J-PARC ● Physics goal (with 5×10 21 POT) - ν μ disappearance: δ(sin 2 θ 23 ) < 0.01, δ(Δm 2 23 ) < 10 -4 eV 2 - ν e appearance: sin 2 θ 13 ~ 0.008 ● Beam line status - Beam line construction is almost completed. - First commissioning will start from April with target & Horn 1 configuration. - Horn 2 & Horn 3 will be installed during summer shutdown. - Full setup commissioning will start in October 2009. - First physics result in 2010.

Recommend


More recommend