Project Limits East Street (Main Street to 7 th Street) Poplar Avenue/Ferry Road (7 th Street to Susquehanna River Bridge) Full Depth Replacement Columbia Blvd. (East Street to Park Street) Milling and Overlay
Project Schedule • Preliminary Design (Current Phase) o Preliminary Engineering Plans o Environmental Studies Right-of-Way Clearance – Spring 2019 to Summer 2020 • Final Design – Summer 2019 to Summer 2020 • Utility Relocation Work – 2019 and 2020 • Contract Award Date – Late 2020 • Construction – Spring 2021 – Fall 2023 •
Project Scope East Street (Main Street to Columbia Boulevard)
Project Scope East Street (Columbia Boulevard to 7 th Street)
Project Scope Poplar Street (7 th Street to 9 th Street)
Project Scope Poplar Street/Ferry Road (9 th Street to Susquehanna River)
Project Typical Section
Project Scope Columbia Boulevard (East Street to Park Street)
Project Scope Local Streetscape Project
Proposed Traffic Control Plan Poplar Street-Ferry Road-East Street (6 th St. to Susq. River Bridge) • Full roadway closure of S.R. 0487 • Posted detour in both directions • Work to be done in phases to maximize access to property owners and businesses
Traffic Control Plan Phase 1
Traffic Control Plan Phase 1
Traffic Control Plan Phase 2
Traffic Control Plan Phase 3
Traffic Control Plan Phase 4
Traffic Control Plan Phase 5
Proposed Traffic Control Plan East Street (Main Street to 6 th Street) • East Street has wide 46-foot cross-section • Roadway closure in NB direction with posted detours • Roadway to remain open in SB direction • Work to be done in phases to maximize access to property owners and businesses
Traffic Control Plan Phases 6-8
Traffic Control Plan Phase 6
Traffic Control Plan Phase 7
Traffic Control Plan Phase 8
Proposed Traffic Control Plan • Contractor will determine order of phasing • Contractor will not be permitted to close travel lanes on the East Street section and Poplar Street/Ferry Road section at the same time • Contractor will hold a public meeting prior to construction to explain schedule
Proposed Traffic Control Plan • Signing for business access • Emergency responder coordination • Pedestrian Access and Detours Details • Tree Trimming and Removal
Contact Information Justin Gochenauer PennDOT Project Manager PennDOT Engineering District 3-0 715 Jordan Avenue P .O. Box 218 Montoursville, PA 17754 (717) 221-2010 c-jgochena@pa.gov
Thank you for Attending Tonight’s Meeting Please help us by completing a project survey form and submitting in the designated Comment Box or mailing it to the PennDOT Project Manager
Thank you for Attending Tonight’s Meeting You are invited to proceed to the Cafeteria, review the Project Displays and meet with the PennDOT Project Design Team
Recommend
More recommend