School Building Committee – August 20, 2018 Wareham Elementary 1 School Project
PROJECT TIMELINE Wareham Elementary School DETAILED DESIGN (DDS & CDS) MILESTONES o DDs Issued for Estimates o DDs Submitted to MSBA o 60% CDs Issued for Estimates o 60% CDs Submitted to MSBA o 90% CDs Issued for Estimates o 90% CDs Submitted to MSBA FEASIBILITY STUDY (PDP & PSR) HIGHLIGHTS o 100% CDs Completed o SC Approves Educational Plan BIDDING/CONSTRUCTION MILESTONES & Initial space Summary o SBC Approves Ed. Plan & ISS o Prequalify Filed Sub Trades o SBC Approves PDP Alternatives o Prequalify GC or Solicit CM Proposals YOU ARE o SBC Approves PDP o Advertisements & Bidding HERE 2020 2017 2018 2019 -2022 FEASIBILITY STUDY (PDP & PSR) HIGHLIGHTS BIDDING/CONSTRUCTION MILESTONES o PDP Submit to MSBA (1.24.18) o Phase 1 New Building* o Systems Commissioning o SBC Approves PSR o Punchlist & Closeout o PSR Submission Deadline (5.21.18) o Building Occupancy o Phase 2 Site Improvements* SCHEMATIC DESIGN HIGHLIGHTS *Phasing subject to final selected option o MSBA FAS Meeting (06.06.18) o MSBA Board Meeting - Approved PSR (6.27.18) o SBC Meeting to Review Costs o SBC Approval of SD o SD Submitted to MSBA (10.17.18) o Town Meeting on Scope & Budget o Town-Wide Debt Exclusion Vote on Project Scope & Budget (11.06.18) o MSBA Approves SD at Board Meeting (12.12.18) Preliminary Design Program Detailed Design MSBA BOARD VOTE Town Vote THE BIG PICTURE Oct ‘17 – Jan ‘18 November 6, 2018 2019 June 27, 2018 Key Dates Preferred Schematic Report Schematic Design MSBA BOARD VOTE Jan ‘18 – Apr ‘18 May ‘18 – Nov ‘18 December 12, 2018 Last updated 11.17.17 Wareham Elementary 2 School Project
MSBA Process MSBA Process MSBA Process MSBA Process Wareham Elementary 3 School Project
WORKING GROUP RECAPS Wareham Elementary 4 School Project
WORKING GROUP RECAP SITE PLAN DEVELOPMENT AUG. 1 st ,2018 SITE PLAN DEVELOPMENT Wareham Elementary 5 School Project
MINOT FOREST ELEMENTARY SCHOOL PREVIOUS SITE PLAN DEVELOPMENT SKETCH WORKING GROUP RECAP SITE PLAN DEVELOPMENT AUG. 1 ST ,2018 Wareham Elementary 6 School Project
WORKING GROUP RECAP SITE PLAN DEVELOPMENT AUG. 1 ST ,2018 Wareham Elementary 7 School Project
MINOT FOREST ELEMENTARY SCHOOL LATEST SITE PLAN DEVELOPMENT SKETCH WORKING GROUP RECAP SITE PLAN DEVELOPMENT AUG. 1 ST ,2018 Wareham Elementary 8 School Project
WORKING GROUP RECAP SITE PLAN DEVELOPMENT AUG. 1 ST ,2018 ARCHAEOLOGY Wareham Elementary 9 School Project
ARCHAEOLOGICAL INTENSIVE SURVEY WORKING GROUP RECAP WORKING GROUP RECAP SITE PLAN DEVELOPMENT AUG. 1 ST ,2018 Wareham Elementary 10 School Project
WORKING GROUP RECAP SITE PLAN DEVELOPMENT AUG. 1 ST ,2018 PLAY EQUIPMENT Wareham Elementary 11 School Project
WORKING GROUP RECAP SITE PLAN DEVELOPMENT AUG. 1 ST ,2018 Wareham Elementary 12 School Project
WORKING GROUP RECAP SITE PLAN DEVELOPMENT AUG. 1 ST ,2018 Wareham Elementary 13 School Project
WORKING GROUP RECAP SITE DESIGN AUG. 9 TH ,2018 SITE DESIGN WORKING GROUP Wareham Elementary 14 School Project
WORKING GROUP RECAP SITE DESIGN AUG. 9 TH ,2018 Overall Site Plan Wareham Elementary 15 School Project
WORKING GROUP RECAP SITE DESIGN AUG. 9 TH ,2018 Site Plan Wareham Elementary 16 School Project
WORKING GROUP RECAP INTERIOR MATERIALS AUG. 9 TH 2018 INTERIOR MATERIALS WORKING GROUP Site Visits Duxbury Co-Located Middle/High school Hanover Elementary School 7/23/18 Wareham Elementary 17 School Project
WORKING GROUP RECAP • FEEDBACK ON SITE VISITS INTERIOR MATERIALS AUG. 9 TH 2018 DUXBURY HANOVER DUXBURY HANOVER Wareham Elementary 18 School Project
WORKING GROUP RECAP • FLOOR FINISHES INTERIOR MATERIALS AUG. 9 TH 2018 TERRAZZO PORCELAIN TILE RESILIENT FLOORING • VCT • LVT • RUBBER • LINOLEUM CARPET Wareham Elementary 19 School Project
WORKING GROUP RECAP • FLOOR FINISHES – SECOND LEVEL INTERIOR MATERIALS AUG. 9 TH 2018 Wareham Elementary 20 School Project
WORKING GROUP RECAP • FLOOR FINISHES – THIRD LEVEL INTERIOR MATERIALS AUG. 9 TH 2018 Wareham Elementary 21 School Project
WORKING GROUP RECAP • FLOOR FINISHES – FIRST LEVEL INTERIOR MATERIALS AUG. 9 TH 2018 Wareham Elementary 22 School Project
WORKING GROUP RECAP • WALL FINISHES INTERIOR MATERIALS AUG. 9 TH 2018 TILE • CERAMIC • PORCELAIN GWB MASONRY • GFCMU • CMU • BRICK PANELING • PLASTIC LAMINATE • WOOD VENEER • ACOUSTIC FABRIC Wareham Elementary 23 School Project
WORKING GROUP RECAP • CEILING FINISHES INTERIOR MATERIALS AUG. 9 TH 2018 ACT GW SPECIALTY • WOOD • METAL Wareham Elementary 24 School Project
WORKING GROUP RECAP • MAJOR SPACES INTERIOR MATERIALS AUG. 9 TH 2018 ENTRY LOBBY/CORRIDOR CORRIDORS CLASSROOMS CAFETERIA INNOVATION CENTER Wareham Elementary 25 School Project
WORKING GROUP RECAP EXTERIOR MATERAILS AUG. 9 TH 2018 EXTERIOR MATERIALS WORKING GROUP Site Visits Duxbury Co-located Middle / High School Hanover Elementary School 7/23/18 Wareham Elementary 26 School Project
WORKING GROUP RECAP EXTERIOR ENVELOPE MATERIALS EXTERIOR MATERAILS AUG. 9 TH 2018 • BRICK VENEER: DIFFERENT COLORS AND RECESSING ACCENTS, VARIED COURSINGS • CAST STONE: DECORATIVE BANDING, WINDOW HEADS, WINDOW SILLS, WALL (LOW AND HIGH) • METAL FASCIA • GLASS AND METAL FRAMED WINDOWS: CURTAIN WALL, STOREFRONT, WINDOW SYSTEMS • METAL PANEL • G.F.R.C.: GLASS FIBER REINFORCED CONCRETE (SIMULATES STONE LOOK): COLUMNS, CROWN MOLDINGS, DECORATIVE PANELS. • METAL SOFFIT PANELS Wareham Elementary 27 School Project
DUXBURY WORKING GROUP RECAP EXTERIOR MATERAILS AUG. 9 TH 2018 Wareham Elementary 30 School Project
HANOVER WORKING GROUP RECAP EXTERIOR MATERAILS AUG. 9 TH 2018 Wareham Elementary 31 School Project
WORKING GROUP RECAP EXTERIOR MATERAILS AUG. 9 TH 2018 Wareham Elementary School Massing Studies Wareham Elementary 32 School Project
WORKING GROUP RECAP EXTERIOR MATERAILS AUG. 9 TH 2018 Front Axonometric Rear Axonometric Wareham Elementary 33 School Project
WORKING GROUP RECAP Front View EXTERIOR MATERAILS AUG. 9 TH 2018 East View Wareham Elementary 34 School Project
WORKING GROUP RECAP EXTERIOR MATERAILS AUG. 9 TH 2018 Pre-K / K View Wareham Elementary 35 School Project
• Building Systems • Sustainability Goals Wareham Elementary 36 School Project
GENERAL DESIGN UPDATES Wareham Elementary 37 School Project
x Wareham Elementary 38 School Project
Wareham Elementary 39 School Project
Wareham Elementary 40 School Project
Wareham Elementary 41 School Project
Wareham Elementary 42 School Project
Wareham Elementary 43 School Project
Wareham Elementary 44 School Project
Wareham Elementary 45 School Project
Wareham Elementary 46 School Project
Wareham Elementary 47 School Project
Wareham Elementary 48 School Project
Wareham Elementary 49 School Project
Option 1 Wareham Elementary 50 School Project
Option 1 Wareham Elementary 51 School Project
Option 2 Wareham Elementary 52 School Project
Option 2 Wareham Elementary 53 School Project
Option 3 Wareham Elementary 54 School Project
Option 3 Wareham Elementary 55 School Project
WORKPLAN/UPCOMING MEETINGS • Site and Building Security • Building Systems • User Interviews Wareham Elementary 56 School Project
Key Dates / Next Steps Key Dates / Next Steps Key Dates / Next Steps Key Dates / Next Steps Sept 5, 2018: Schematic Estimate Package Complete Sept 6, 2018: Town Warrant Article Due Sept 21, 2018: DRAFT Schematic Estimates Due Sept 25, 2018: Schematic Estimate Reconciliation Oct 1, 2018: SBC Final Vote on Value Management Options Oct 3, 2018: MSBA Deadline to Submit Project Budget Oct 17, 2018: MSBA Deadline to Submit Schematic Design (SD) Oct 22, 2018: Town Meeting Vote – 2/3 Approval Required Nov 6, 2018: Ballot Vote for Project Funding Dec 12, 2018: MSBA Board of Directors Meeting (Approval of Schematic Design & Budget) Wareham Elementary 57 School Project
THANK YOU Wareham Elementary 58 School Project