RICHLAND COUNTY TRANSPORTATION PENNY PROGRAM Town of Irmo January 10, 2019 Program Funding Categories Bike / Ped./ Administration, Greenway, $32,100,000 $80,888,356 Bus Service, Roadway $300,991,000 Projects, $656,020,644 Summary of


  1. RICHLAND COUNTY TRANSPORTATION PENNY PROGRAM Town of Irmo January 10, 2019

  2. Program Funding Categories Bike / Ped./ Administration, Greenway, $32,100,000 $80,888,356 Bus Service, Roadway $300,991,000 Projects, $656,020,644 Summary of Bike/Ped./Greenway, Administration, and Roadway Projects= $769,009,000

  3. Projects By The Numbers 87 BIKEWAYS 15 GREENWAYS 15 INTERSECTIONS 7 NEIGHBORHOOD IMPROVEMENTS 56 SIDEWALKS 5 SPECIAL PROJECTS 14 WIDENINGS

  4. Financials To Date $ 320.3 M Sales Tax Collections $ 15.7 M Outside Funding $ 89.9 M Disbursed to Comet $ 12.3 M Mitigation Bank $ 17.2 M Program Expenditures $ 196.3 M Project Expenditures $ 38.3 M Design / Planning & Delivery $ 9.7 M Right-of-Way $ 148.2 M Construction $ 316 M Total Expenditures To Date

  5. www.richlandpenny.com CALL EMAIL INFO@RICHLANDPENNY.COM 1-844-RC PENNY

  6. Interactive Map CALL EMAIL INFO@RICHLANDPENNY.COM 1-844-RC PENNY

  7. Clemson Road Widening Clemson Road (Chimneyridge Drive to Old Clemson Road) CALL EMAIL INFO@RICHLANDPENNY.COM 1-844-RC PENNY

  8. Recent Construction Three Rivers Greenway CALL EMAIL INFO@RICHLANDPENNY.COM 1-844-RC PENNY

  9. Recent Construction Shop Road Extension – Phase 1 CALL EMAIL INFO@RICHLANDPENNY.COM 1-844-RC PENNY

  10. Recent Construction North Main Street Widening CALL EMAIL INFO@RICHLANDPENNY.COM 1-844-RC PENNY

  11. Recent Construction Sidewalk Construction CALL EMAIL INFO@RICHLANDPENNY.COM 1-844-RC PENNY

  12. Recent Construction CALL EMAIL INFO@RICHLANDPENNY.COM 1-844-RC PENNY

  13. Construction Complete Bluff Road Widening – Phase 1

  14. Construction Complete Greene St Improvements – Phase 1

  15. Construction Complete Summit Ridge / Summit Pkwy Kennerly Rd / Coogler Rd

  16. Construction Complete Broad River Rd / Rushmore Rd North Springs Rd / Risdon Way

  17. Construction Complete Farrow Rd / Pisgah Church Rd North Springs Rd / Clemson Rd / Rhame Rd

  18. Construction Complete Lincoln Tunnel Greenway

  19. Construction Complete Riverbanks Zoo Pedestrian Bridge

  20. Construction Complete Franklin St. Wildwood Ave. Windover St.

  21. District 1 Active / Completed Projects Roadway Widening • Broad River Rd Widening Intersections • Kennerly Rd / Coogler Rd Sidewalks / Bikeways • along Broad River Rd Roadway Resurfacing Broad River Corridor Improvements • Completed (59) Greystone Blvd Intersection • • Construction Phase (37) Bush River Rd Intersection • St. Andrews Rd Intersection • CALL EMAIL INFO@RICHLANDPENNY.COM 1-844-RC PENNY

  22. District 1 Active / Completed Projects Dirt Road Paving Completed Projects (6) In Construction / Procurement (8) Amenity Ct Amick Dr • • Cabin Cove Rd Howard Coogler Rd • • Cedar Grove Ln Julian Addy Cir • • Miller Rd Manus Rd • • Shady Grove Church Rd Ken Webber Rd • • Tiger Paw Ln Summer Haven Rd • • Haven Cir • In Design / Rights of Way (5) Mrs Macks Rd • Stone House Dr • Tall Oaks Dr • Eastview Dr Upcoming Projects (11) • Ollie Dailey Rd • Thelma Hicks Rd • CALL EMAIL INFO@RICHLANDPENNY.COM 1-844-RC PENNY

  23. Kennerly/Coogler Roundabout

  24. Broad River Rd Widening END PROJECT Shady Grove Rd . Dutch Fork Rd. Koon Rd . END PROJECT Shady Grove Rd. BEGIN PROJECT Royal Tower Rd . Farming Creek Rd . Woodrow St. CALL EMAIL INFO@RICHLANDPENNY.COM 1-844-RC PENNY

  25. Broad River Rd Widening Project Data Ranked #10 of (14) Roadway Widenings • Approx. 2.5 miles of improvements • Approx. 22,500 vehicles per day (current) • Approx. 34,500 vehicles per day (2043) • High vehicular accident statistics (rear-end/angle) • Current Cost Estimate = approx. $40 million •

  26. Broad River Rd Widening Typical Section 85 FEET CALL EMAIL INFO@RICHLANDPENNY.COM 1-844-RC PENNY

  27. Project Development Activities To-Date Traffic Counts / Studies Preliminary Roadway Design • • Field Surveys Value Engineering • • Utility Surveys (SUE) Alignment Studies / Revisions • • Preliminary Geotechnical Studies Intersection Studies / Relocations • • Jurisdictional Determinations Cost Evaluations • • Cultural Resource Studies Rights-of-Way Roadway Design • • Hazardous Material Studies Utility Coordination • • Pavement Evaluation & Design SCDOT Coordination • • Public Meeting / Public Coord. •

  28. Project Development Process Data Collections / Project Studies • Preliminary Design & Plans • Design Verifications & Value Engineering • • Rights-of-Way Plans & Acquisitions Construction Design & Plans • Project Letting •

  29. Project Challenges High Peak Traffic Volumes • Multiple Failing Traffic Movements • Existing & Current Development • Rights-of-Way Impacts • Geometry & Intersection Modifications • Utility Coordination / Utility Relocations •

  30. Project Schedule Begin Rights-of-Way Acquisitions 3 rd quarter 2019 Begin Construction 2021 Construction Duration approx. 24 – 30 months

  31. Richland County Transportation Penny Program RICHLANDPENNY.COM 201 ARBOR LAKE DRIVE COLUMBIA, SC 29223 1-844-RC PENNY