new elementary school 42
play

New Elementary School #42 Construction Documents Report Scott - PowerPoint PPT Presentation

New Elementary School #42 Construction Documents Report Scott Washington Director, School Construction March 24, 2016 Project Update Provided paved access path from buss loop to the community walking path at the rear of the building


  1. New Elementary School #42 Construction Documents Report Scott Washington Director, School Construction March 24, 2016

  2. Project Update • Provided paved access path from buss loop to the community walking path at the rear of the building • Reconfiguration kitchen area to accommodate new equipment and to centralize the kitchen manager office • Update the building elevations in coordination with the county Design Advisory Panel

  3. Site Plan New Elementary School #42

  4. New Elementary School #42 Sc ho o l b us pa rking fo r 18 b usse s. T he b us drive wa y is se pa ra te fro m the pa re nt A dro p-o ff drive wa y to re duc e ve hic ula r c o ng e stio n o n site . T o pro vide a s muc h c a r pa rking o n site a s po ssib le , 110 pa rking spa c e s ha ve B b e e n pro vide d a mo ng the thre e a re a s o n site . Pa re nt dro p-o ff a nd pic kup a re a a dja c e nt to the ma in e ntra nc e with a n C a mple q ue uing a re a to e limina te inte rfe re nc e with the ma in pa rking lo t. Se rvic e drive with e me rg e nc y ve hic le D a c c e ss to the pa ve d pla y a re a . Pa ve d pla y a re a a dja c e nt to E g ymna sium a nd c a fe to rium. Sto rm wa te r ma na g e me nt b io -re te ntio n F fa c ilitie s in a dditio n to the unde rg ro und sto rm wa te r ma na g e me nt fa c ility. Pla yfie lds ha ve b e e n lo c a te d a dja c e nt to the g ymna sium, c a fe to rium, a nd lo c ke r ro o ms, suc h tha t stude nts will no t G ha ve to c ro ss ve hic ula r ro a ds o r drive wa ys to a c c e ss. H L o c a tio ns o f o utdo o r c la ssro o m a re a s. E nlar ge d Site Plan

  5. New Elementary School #42 L E GE ND K inde rg a rte n / E a rly Childho o d Grade s 1-5 iii iii Spe c ia l E duc a tio n Ce ntral Suppo rt Spa c e s Administrative Spac e s Building Se rvic e s Re c . a nd Pa rks iv iv i ii Constr uc tion Doc ume nt 0 8 16 32 F ir st F loor Plan Schematic Design First Floor Plan

  6. New Elementary School #42 L E GE ND K inde rg a rte n / E a rly Childho o d Grade s 1-5 iii iii Spe c ia l E duc a tio n Ce ntral Suppo rt Spa c e s Administrative Spac e s Building Se rvic e s Re c . a nd Pa rks iv iii Constr uc tion Doc ume nt 0 8 16 32 Se c ond F loor Plan Schematic Design First Floor Plan

  7. le vation New Elementary School #42 ont E r F

  8. Total Project Budget Base Construction Estimate $32,994,732 Architect/Engineering Fee $2,474,585 Construction Management Fee $2,350,000 Related Costs $1,666,000 Project Contingency $1,666,000 Equipment and Technology $2,333,520 Alternate #1: Outdoor Classroom at Main Entrance $232,978 Alternate #2: Instructional Gazebo at Bus Loop $114,350 Alternate #3: Sod in lieu of Seed $46,975 Alternate #4: Neighborhood Storm water tie ‐ in $28,373 Project Total Budget $43,907,513 Funding Projections FY16 $2,807,000 FY17 $16,526,000 FY18 $20,658,000 FY19 $4,132,000 Total Funding Projections $44,123,000

  9. New Elementary School #42 Summary • Schedule – Receive bids June 2016 – Construction starts September 2016 – Completion August 2018 • Request approval of construction documents and allow staff to proceed to project bid