lexington club
play

LEXINGTON CLUB LEXINGTON HOMES HANK STILLWELL LEGAL Developer: - PowerPoint PPT Presentation

Presentation to Planning Commission September 20 2011 LEXINGTON CLUB LEXINGTON HOMES HANK STILLWELL LEGAL Developer: Lexington Homes Legal: PROJECT Rathje & Woodward, LLC TEAM Environmental: Huff & Huff, Inc.


  1. Presentation to Planning Commission September 20 2011 LEXINGTON CLUB LEXINGTON HOMES

  2. HANK STILLWELL LEGAL

  3. • Developer: Lexington Homes • Legal: PROJECT Rathje & Woodward, LLC TEAM • Environmental: Huff & Huff, Inc. • Planner & Architect: BSB Design, Inc. • Landscape Architect: Pugsley & La Haie, Ltd. • Civil Engineer: Wills Burke Kelsey Associates, Ltd. (WBK) • Traffic Engineer: Kenig, Lindgren, O’Hara, Aboona, Inc. (KLOA)

  4. JIM HUFF ENVIRONMENTAL

  5. BACKGROUND • Huff & Huff has worked for the City of St. Charles for over 25 years. – Consultant of Record for the First Street Redevelopment remediation – Just completed a remediation of a LUST at the St. Charles CC – Completed the environmental work on the new Red Gate Bridge • Huff & Huff, Inc. has been involved with this site since 2006. We have: – Reviewed previous reports – Conducted soil borings – Conducted a series of test pits across the site

  6. • SITE HISTORY Original Manufacturing Buildings constructed in early 1900s. • Rope nets and hammocks were manufactured from early 1900s into the late 1920s. • From the late 1920s to 2005, pressed wood pulp and fibrous composite products were manufactured. Large Quantity Generator of Hazardous Waste. • Had coal ‐ fired boiler at one time.

  7. • REC ‐ 1: Former Buried Drum Area IDENTIFIED RECOGNIZED • REC ‐ 2: Former Settling Lagoons ENVIRONMENTAL CONDITIONS • REC ‐ 3: Mounds on Western Portion of Property • REC ‐ 4: Former Leaking Gasoline UST • REC ‐ 5: Former Panapol UST • REC ‐ 6, 7, 8 & 9: Former Heating Oil UST and Press Pits • REC ‐ 10: Abandoned Phenol UST • RC ‐ 11: Former Lacquer AST and Peroxide Storage Shed

  8. • Install Monitoring wells at RECs and at perimeter of REMEDIATION site APPROACH • Remove all pits and sumps and associated impacted soil and sample • Enroll in IEPA Site Remediation Program for focused No Further Remediation Letter for Contaminants associated with this site • Prioritize RECs by location • Complete delineation and remediation by REC • Prepare Reports by REC, including Site Investigation Report, Risk Assessment, Remedial Action Plan, and Remedial Action Completion Reports and submit to IEPA for review

  9. • Based on work completed to date, an estimated ESTIMATED 8,000 to 9,000 cubic yards of impacted soil will REMEDIATION need to be removed and landfilled. • Our goal is to remediate the site so as not require any engineered barriers or construction worker cautions.

  10. PLANNING TERRY SMITH

  11. LANDSCAPE ARCHITECTURE SHARON DICKSON

  12. ARCHITECTURE JOE SAFIN

  13. TRAFFIC ENGINEERING LUAY ABOONA

  14. CIVIL ENGINEERING CHRIS LINDLEY

Recommend


More recommend