Who We Are The Lee County Port Authority ( LCPA ) operates both Southwest Florida International Airport and Page Field in Fort Myers. RSW FMY Southwest Florida Page Field International Airport 3 | flylcpa.com
LCPA Funding The Port Authority operates as an enterprise fund with revenue generated from airport operations. No ad valorem (property) tax dollars support the airport operations or construction. Sources of revenue include rents and fees from our tenants and user fees from travelers, which fund our operations. Construction Projects funded by Passenger Facility Charges and grants from the Federal Aviation Administration and Florida Department of Transportation. Total RSW Revenue 2019 FY to-date through March 5 | flylcpa.com
RSW Economic Benefit Airports bring in more than passengers, they bring in dollars! Total Output from Southwest Florida InternationalAirport 8 | flylcpa.com
Page Field (FMY) LCPA manages Page Field general aviation airport. This airport primarily supports recreational flying, business activity, and flight training. The airport offers aircraft maintenance and also has one of Florida’s top-rated fixed-base operators. 4 | flylcpa.com
FMY – New Multi Use Hangar 25,000 sq ft hangar recently constructed to meet increased customers/aircraft 6 | flylcpa.com
FMY - South Quad Hangars and Ramp Tear down / reconstruct thirty-nine (39) T-hangars and improve ramp 7 | flylcpa.com
Southwest Florida International Airport (RSW) RSW has 4,000 people working at the airport, as well as its own fire and police departments. We maintain roadways and buildings on 7,000 acres of land. RSW is the third-largest airport in the nation for land mass and is the second busiest single runway airport in the nation, behind San Diego. 4 | flylcpa.com
RSW – Skyplex Development Area Skyplex is located on the north side of RSW and has more than 1,100 acres of land designated for aviation and non-aviation development. 9 | flylcpa.com
RSW - Skyplex Blvd Skyplex Boulevard is an internal roadway within the Skyplex development area. This road will link Daniels Parkway and Chamberlin Parkway. The project is currently under construction and will open summer/fall 2019. 10 | flylcpa.com
RSW - Skyplex Tenants Publix Super Markets Inc. is the largest employee-owned grocery chain and one of the 10 largest-volume supermarket chains in the United States. Gartner , Inc. is an S&P 500 global research and advisory firm. Alta Resources is a integrated business process outsourcing service company 11 | flylcpa.com
RSW – Landside Pavement Rehabilitation Currently under phased design. Phase 1 planned for construction 2020. 12 | flylcpa.com
RSW – Airside Pavement Rehabilitation Currently under phased design. Project 1 planned for construction 2020. 13 | flylcpa.com
RSW – Rental Car Relocation Rental car maintenance area will be relocated closer to the terminal to improve operational efficiency and dated facilities. Early in evaluation stage.
RSW – Maintenance Building Expansion Existing facility is 15,981 sq ft. Additional 6,250 sq ft is currently being constructed, along with 16 additional parking spaces.
Passenger Processing Modernization Modernization of all signage and counters (ticket, gate, curb, rental car). Construction to commence 2019. To be completed in 2020. 16 | flylcpa.com
RSW – Terminal Expansion Project Objectives: - Further Enhance the RSW Passenger Experience - Shorten Passenger Wait Times - Consolidate TSA Checkpoint Operations - Increase Post-Security Concessions - Create Connectivity Between Concourses - Add Amenities - Enhance Aesthetic Character Design: 2018 - 2019 Construction: 2020 - 2023 17 | flylcpa.com
Existing vs. Planned Terminal Expansion 18 | flylcpa.com
Existing vs. Planned Terminal Expansion 19 | flylcpa.com
Terminal Expansion Renderings - External 20 | flylcpa.com
Terminal Expansion Renderings - Internal Virtual Fly Through 21 | flylcpa.com
RSW – New Air Traffic Control Tower & Terminal Radar Approach Control Existing tower cab elevation is 121’. New tower cab elevation will be 208’. Construction will commence summer 2019 and take 3 years to complete. 22 | flylcpa.com
RSW - Airport of the Future A 9,100' parallel runway is planned, permitted, and mitigated Proposed Parallel Runway 23 | flylcpa.com