inf5181
play

INF5181 Project idea Kristoffer Wang Improvement Context System - PowerPoint PPT Presentation

INF5181 Project idea Kristoffer Wang Improvement Context System development at a Health Clinic Development started 2010 First Launch 2011 Small and Inexperienced Team Project Leader is unfamiliar with IT-projects


  1. INF5181 Project idea – Kristoffer Wang

  2. Improvement Context — System development at a Health Clinic — Development started 2010 — First Launch 2011 — Small and Inexperienced Team — Project Leader is unfamiliar with IT-projects — No formalized methods

  3. Problems — Releases to end user have a lot of bugs — Normally 2-5 major bugs per release — Twice as many minor bugs — Poor communication between developers — Poor Testing

  4. Improvement — Goals: — No major bugs in releases to end users — 75% reduction in minor bugs — Steps to Improvement: — Map the current development process — Identify Problems and Weaknesses — Improve Development Process — Use relevant research and litterature