Community Liaison Group 9 July 2015 Agenda Introductions Minutes from previous meeting CLG update Operational report Maintenance schedule Mitigation measures Complements and complaints Community Fund Terms of


  1. Community Liaison Group 9 July 2015

  2. Agenda  Introductions  Minutes from previous meeting  CLG update  Operational report  Maintenance schedule  Mitigation measures  Complements and complaints  Community Fund  Terms of Reference  Next steps

  3. CLG Update  Third meeting of the CLG, inc site tour  Useful site tour held in June  Additional members signed up – now stand at 13  Looking to sign further residential members

  4. Operational Report Generation and Importation

  5. GEL's importation / generation mix (2001-2015) 450,000 Importation On-island generation 400,000 350,000 300,000 250,000 MWh 200,000 150,000 100,000 50,000 0 2001/02 2002/03 2003/04 2004/05 2005/06 2006/07 2007/08 2008/09 2009/10 2010/11 2011/12 2012/13 2013/14 2014/15 Budget 2015/16

  6. Cumulative Customer Minutes Lost 80.0 Generation Distribution 70.0 60.0 50.0 40.0 30.0 20.0 10.0 -

  7. GEL's importation / generation mix (Jan 2014 - Dec 2015) 45,000 Importation On-island generation 40,000 35,000 30,000 25,000 MWh 20,000 15,000 10,000 5,000 0 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Note: July-December is expected.

  8. Maintenance Schedule In Progress  2D – July 2015  4C – July 2015 Scheduled  1D – August 2015  Reactor reinstatement – October 2015 Complete  2C  3C

  9. Power Station Improvements  Extension to the acoustic wall due to be completed July 2015  Radiator screening on D Station roof – in progress due to be completed July 2015  New exhaust silencer in D Station – in progress due to be completed July 2015  Other minor improvements underway

  10. Complements and Complaints Comment Date Notes Complaint from Neighbour 08/06/2015 Complaint about water running down the Hougue Jehannet Road from D Station. 21/05/2015 – 19 x complaints regarding Complaints regarding fallout on boats and cards. pollution (fallout) 09/07/2015 Comment Date Notes Compliment received regarding a 04/06/2015 Customer stated she received excellent service member of the Showroom staff. from GEL and delivery was quick.

  11. Community Fund  Advertisement of fund to commence shortly  Via CLG  Newsletters  Social media  Press release  No requests have been received to date

  12. Next Steps  Topics to discuss  Date of next meeting