Five Corners Sewers Phase II Construction Update Neighborhood Meeting Easton Middle School Auditorium 98 Columbus Avenue May 29, 2019 1
Welcome! Tonight's Topics: 1. Brief Background & Project Update 2. Project Schedule 3. Traffic Management – (Beta) 4. Public Outreach 5. Next Steps 2
Phase 2 Sewer Collection System 3
Phase 2 Design & Construction Schedule Sept 2015: Design began for Phases 1 & 2 July 2017: 50% Design Complete Aug. 2017: PEF Applications to DEP April 2018: 75% Design Complete & Permitting May 2018: Annual Town Meeting – Construction Appropriation & Easements for Phase 2 Oct. 2018: Final Plans/SRF Funding Feb. 2019: SRF Permission to Advertise Apr. 2019: Received Construction Bids May 2019: Constr. Contract signed with C. Naughton Jun 2019: Begin Construction Summer/Fall 2020: Initial Sewer Connections Commence Fall 2020: Finish Construction/Final Paving 4
Phase 2 Detailed Construction Schedule May 2019 Pre-Construction Meeting (with Contractor) May 2019 Public Workshop (address concerns before construction) June 2019 Sewer Construction Begins June 2019 Set up temporary water / Begin Traffic Detour on Foundry St June/July 2019 Betterment Update / Workshop Dec. 2019 – April 2020 Winter shutdown (Traffic Detour Suspended) April 2020 – Fall 2020 Continued sewer construction – completed over summer. Summer/Fall 2020 Sewer Connections may begin Fall 2020 Final paving-all streets (Traffic Detour) • Effectively 2 construction seasons (2019/2020) • Sewer & water installed on Foundry (2019) • Onsite Representative for coordination/issues/concerns • Traffic Management is key (will adjust as needed) 5
Foundry Street Detour 6 Foundry Street Eastbound Closure
Foundry Street Detour 7 Temporary Signals at Highland Street
Foundry Street Detour 8 Route 106 Eastbound Detour Route
Foundry Street Detour 9 Highland Plaza/Avalon Exit Detour Route
Foundry Street Detour 10 Foundry Street Eastbound Closure
Foundry Street Detour 11 Foundry St/Five Corners Area Local Access Detour
Temporary Traffic Signal Foundry Street • Foundry Street southbound widened to provide a left turn lane to Highland Street at Highland • Advance phase provided for southbound left turn Street • Pedestrian accommodation provided Bay Road at • Two phase operation: Bay Road, Highland Highland Street • Detection provided – signal will be responsive to traffic demand Street 12
Signal Timing Adjustments Timing Adjustments at Foundry St (Rte 106/123)/Eastman St (Rte 106)/Robert Dr (Highland Plaza/Avalon) Timing/Phasing Adjustments at Five Corners Extensive observation and monitoring during detour operations Opportunity to adjust and be responsive to operational concerns 13
Other Construction Impacts Short duration detour used for Poquanticut Ave/South St (north of Foundry) Poquanticut SB traffic maintained, NB traffic detoured via South St Remaining streets constructed with short term one-way alternating traffic with police details South St (south of Foundry) Depot St Foundry St (east of Five Corners) Bay Road (both north and south of Five Corners) Access to abutting properties maintained 48 hour notice required when impacts are necessary 14
Construction Coordination / Public Outreach • Easton Town Crier Updates (email) • Variable Message Boards (in advance of and during construction) • DPW Project Website: www.fivecornerssewer.com 15
Construction Coordination • Variable Message Boards (already deployed) • Waze Traffic Partner • Coordinate with Schools, Police & Fire • Maintain access to all properties – • Weekly coordination with Police Details to maximize business access / minimize impacts • Extra customized signage as needed • Highland Street Detour – Police Presence 16
Public Inquiries - Points of Contact DPW Project Website: www.fivecornerssewer.com Email: fivecorners@easton.ma.us Phone: (888) 527-6797 Onsite/Field Contact: Chris Munroe (Field Rep) Munroec@peercpc.com (802) 598-1155 Our Team is available to you twenty-four hours a day, seven days a week. Should you have any questions or concerns, please reach out to us using one of the above methods. 17
Next Steps Construction Begins: Week of May 28 th – Construction Staging • Week of June 3 rd – Begin Temporary Water System • • Immediately Following: • Set up traffic detour: • 1 lane traffic on Foundry (westbound) • Detour on Highland (eastbound) Betterment Update Workshop Return your Sewer Service Form to: Chris Munroe (Field Rep) Munroec@peercpc.com (802) 598-1155 18
Questions / Discussion DPW Project Website: www.fivecornerssewer.com Email: fivecorners@easton.ma.us Phone: (888) 527-6797 Onsite/Field Contact: Chris Munroe (Field Rep) Munroec@peercpc.com (802) 598-1155 19